24-00035-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $448,788 | ||
| 2 | D. Construction, Inc. | $453,961 | +1.2% | |
| 3 | Geneva Construction Company LLC. | $457,332 | +1.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 D. Construction… | #3 Geneva Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX006947 | HMA DRIVE REM & REP | 92 | SQ YD | $85.00 | $50.00 | $41.00 | |
| 2 | X0327036 | BIKE PATH REM | 24 | SQ YD | $35.00 | $50.00 | $24.00 | |
| 3 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,600.00 | $1,500.00 | $1,300.00 | |
| 4 | X7200061 | TEMP INFO SIGNING | 77.1 | SQ FT | $20.00 | $30.00 | $12.00 | |
| 5 | 21101615 | TOPSOIL F & P 4 | 50 | SQ YD | $10.00 | $11.00 | $10.00 | |
| 6 | 25200110 | SODDING SALT TOLERANT | 50 | SQ YD | $75.00 | $82.50 | $75.00 | |
| 7 | 25200200 | SUPPLE WATERING | 5 | UNIT | $0.0100 | $0.0100 | $0.0100 | |
| 8 | 28000250 | TEMP EROS CONTR SEED | 10 | POUND | $3.31 | $36.41 | $3.31 | |
| 9 | 28000510 | INLET FILTERS | 2 | EACH | $250.00 | $300.00 | $225.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 11,470 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 11 | 40600370 | LONG JOINT SEALANT | 5,407 | FOOT | $3.50 | $4.38 | $3.30 | |
| 12 | 40600400 | MIX CR JTS FLANGEWYS | 5 | TON | $600.00 | $0.0100 | $175.00 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 134 | SQ YD | $20.00 | $0.0100 | $20.00 | |
| 14 | 40603080 | HMA BC IL-19.0 N50 | 2,140 | TON | $71.00 | $68.00 | $73.00 | |
| 15 | 40604060 | HMA SC IL-9.5 D N50 | 1,435 | TON | $72.00 | $73.00 | $79.00 | |
| 16 | 42400200 | PC CONC SIDEWALK 5 | 290 | SQ FT | $15.00 | $20.00 | $11.95 | |
| 17 | 42400800 | DETECTABLE WARNINGS | 30 | SQ FT | $65.00 | $50.00 | $31.20 | |
| 18 | 44000164 | HMA SURF REM 3 3/4 | 16,980 | SQ YD | $3.75 | $3.80 | $3.70 | |
| 19 | 44000500 | COMB CURB GUTTER REM | 76 | FOOT | $26.50 | $15.00 | $16.00 | |
| 20 | 44000600 | SIDEWALK REM | 225 | SQ FT | $8.00 | $5.00 | $3.00 | |
| 21 | 44201709 | CL D PATCH T3 5 | 170 | SQ YD | $40.00 | $56.00 | $50.00 | |
| 22 | 44201711 | CL D PATCH T4 5 | 510 | SQ YD | $40.00 | $55.00 | $45.00 | |
| 23 | 60608300 | COMB CC&G TM2.12 | 76 | FOOT | $75.00 | $50.00 | $52.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $19,503.12 | $15,000.00 | $27,400.00 | |
| 25 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $5,500.00 | $15,843.00 | $1.00 | |
| 26 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $500.00 | $0.0100 | $5,600.00 | |
| 27 | 70300100 | SHORT TERM PAVT MKING | 900 | FOOT | $1.00 | $0.0100 | $0.0100 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 300 | SQ FT | $4.50 | $0.0100 | $0.0100 | |
| 29 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 1,500 | FOOT | $0.4500 | $0.0100 | $0.4500 | |
| 30 | 78000100 | THPL PVT MK LTR & SYM | 15.6 | SQ FT | $15.00 | $8.25 | $7.50 | |
| 31 | 78000200 | THPL PVT MK LINE 4 | 21,565 | FOOT | $0.7500 | $0.8100 | $0.7400 | |
| 32 | 78000400 | THPL PVT MK LINE 6 | 179 | FOOT | $1.32 | $1.29 | $1.17 | |
| 33 | 78000600 | THPL PVT MK LINE 12 | 50 | FOOT | $2.65 | $4.13 | $3.75 | |
| 34 | 78000650 | THPL PVT MK LINE 24 | 33 | FOOT | $10.00 | $8.25 | $7.50 |