20-F3000-06-BT
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $3,654,428 | ||
| 2 | Herlihy Mid-Continent Company | $4,913,365 | +34.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Herlihy Mid-Con… |
|---|---|---|---|---|---|---|---|
| 1 | A2006512 | T-QUERCUS BICOL 1-1/2 | 10 | EACH | $880.00 | $450.00 | |
| 2 | A2007112 | T-QUERCUS RUBRA 1-1/2 | 10 | EACH | $880.00 | $450.00 | |
| 3 | K1005418 | TEMPORARY SEEDING | 3.5 | ACRE | $110.00 | $1,200.00 | |
| 4 | K1005421 | SEEDING SPL | 0.75 | ACRE | $4,950.00 | $4,500.00 | |
| 5 | XX007606 | LIMESTONE SCRN SURF 2 | 2,096 | SQ YD | $4.10 | $8.55 | |
| 6 | XX008287 | BOARDWALK STRUCTURE | 11,969 | SQ FT | $145.00 | $165.00 | |
| 7 | XX008864 | INSTALL SIGN | 2 | EACH | $1,350.00 | $1,500.00 | |
| 8 | XX009531 | TREE ROOT PRUNING SPL | 500 | FOOT | $27.50 | $5.00 | |
| 9 | X0322508 | PED TRUSS SUPERSTR | 1,800 | SQ FT | $216.00 | $245.00 | |
| 10 | X0326806 | WASHOUT BASIN | 1 | L SUM | $2,000.00 | $3,500.00 | |
| 11 | X0327997 | TRASH RECEPTACLES | 2 | EACH | $800.00 | $2,845.00 | |
| 12 | X2011001 | HIGH VIS TEMP FENCE | 1,150 | FOOT | $3.30 | $7.63 | |
| 13 | X2510900 | TURF REINF MAT SPL | 356 | SQ YD | $13.20 | $45.00 | |
| 14 | X2511630 | EROS CONT BLANKET SPL | 13,324 | SQ YD | $1.54 | $2.10 | |
| 15 | X6640104 | FENCE REMOVAL | 31 | FOOT | $11.44 | $10.40 | |
| 16 | X6640624 | RUSTIC RAIL FENCE | 192 | FOOT | $67.28 | $61.16 | |
| 17 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $5,000.00 | $5,350.00 | |
| 18 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $0.0100 | $151,129.21 | |
| 19 | Z0013797 | STAB CONSTR ENTRANCE | 190 | SQ YD | $0.0100 | $54.00 | |
| 20 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $47,400.00 | $286,822.62 | |
| 21 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 22 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 23 | 20100110 | TREE REMOV 6-15 | 746 | UNIT | $27.50 | $24.00 | |
| 24 | 20100210 | TREE REMOV OVER 15 | 542 | UNIT | $38.50 | $34.00 | |
| 25 | 20101000 | TEMPORARY FENCE | 170 | FOOT | $8.80 | $6.00 | |
| 26 | 20101300 | TREE PRUN 1-10 | 35 | EACH | $27.50 | $85.00 | |
| 27 | 20101350 | TREE PRUN OVER 10 | 35 | EACH | $110.00 | $200.00 | |
| 28 | 20200100 | EARTH EXCAVATION | 1,140 | CU YD | $35.00 | $49.00 | |
| 29 | 20201200 | REM & DISP UNS MATL | 860 | CU YD | $35.00 | $53.00 | |
| 30 | 20400800 | FURNISHED EXCAVATION | 3,940 | CU YD | $30.00 | $58.00 | |
| 31 | 21001000 | GEOTECH FAB F/GR STAB | 3,938 | SQ YD | $3.50 | $3.40 | |
| 32 | 21101505 | TOPSOIL EXC & PLAC | 5,134 | CU YD | $22.00 | $27.00 | |
| 33 | 21101600 | TOPSOIL F & P VAR DP | 130 | SQ YD | $7.70 | $10.00 | |
| 34 | 21101625 | TOPSOIL F & P 6 | 5,910 | SQ YD | $6.60 | $7.25 | |
| 35 | 25000115 | SEEDING CL 1B | 0.25 | ACRE | $2,750.00 | $3,200.00 | |
| 36 | 25000310 | SEEDING CL 4 | 2.25 | ACRE | $2,530.00 | $2,900.00 | |
| 37 | 25000324 | SEEDING CL 5B | 0.25 | ACRE | $2,750.00 | $5,100.00 | |
| 38 | 25000750 | MOWING | 1 | ACRE | $550.00 | $500.00 | |
| 39 | 25200200 | SUPPLE WATERING | 25 | UNIT | $102.30 | $100.00 | |
| 40 | 28000305 | TEMP DITCH CHECKS | 128 | FOOT | $11.00 | $15.00 | |
| 41 | 28000400 | PERIMETER EROS BAR | 7,178 | FOOT | $3.03 | $2.75 | |
| 42 | 28100107 | STONE RIPRAP CL A4 | 298 | SQ YD | $80.00 | $134.00 | |
| 43 | 28100705 | STONE DUMP RIP CL A3 | 42 | SQ YD | $100.00 | $126.00 | |
| 44 | 28200200 | FILTER FABRIC | 340 | SQ YD | $6.00 | $25.00 | |
| 45 | 30300001 | AGG SUBGRADE IMPROVE | 860 | CU YD | $55.00 | $61.00 | |
| 46 | 35101600 | AGG BASE CSE B 4 | 24 | SQ YD | $10.00 | $25.00 | |
| 47 | 35102000 | AGG BASE CSE B 8 | 6,547 | SQ YD | $13.00 | $25.00 | |
| 48 | 40600275 | BIT MATLS PR CT | 9,175 | POUND | $0.0100 | $0.0100 | |
| 49 | 40600290 | BIT MATLS TACK CT | 1,835 | POUND | $0.0100 | $0.0100 | |
| 50 | 40600982 | HMA SURF REM BUTT JT | 168 | SQ YD | $0.0100 | $30.00 | |
| 51 | 40603080 | HMA BC IL-19.0 N50 | 431 | TON | $90.00 | $142.00 | |
| 52 | 40604060 | HMA SC IL-9.5 D N50 | 372 | TON | $92.00 | $157.00 | |
| 53 | 42400300 | PC CONC SIDEWALK 6 | 200 | SQ FT | $12.00 | $30.00 | |
| 54 | 42400800 | DETECTABLE WARNINGS | 40 | SQ FT | $40.00 | $85.00 | |
| 55 | 44201690 | CL D PATCH T1 4 | 100 | SQ YD | $40.00 | $70.00 | |
| 56 | 44201692 | CL D PATCH T2 4 | 100 | SQ YD | $40.00 | $60.00 | |
| 57 | 44201694 | CL D PATCH T3 4 | 100 | SQ YD | $40.00 | $50.00 | |
| 58 | 44201696 | CL D PATCH T4 4 | 100 | SQ YD | $40.00 | $40.00 | |
| 59 | 50200100 | STRUCTURE EXCAVATION | 487 | CU YD | $38.00 | $51.50 | |
| 60 | 50300225 | CONC STRUCT | 21.8 | CU YD | $1,600.00 | $3,500.00 | |
| 61 | 50300300 | PROTECTIVE COAT | 229 | SQ YD | $2.00 | $5.00 | |
| 62 | 50301350 | CONC SUPSTR APP SLAB | 21.2 | CU YD | $600.00 | $1,750.00 | |
| 63 | 50800205 | REINF BARS, EPOXY CTD | 6,100 | POUND | $2.25 | $2.01 | |
| 64 | 51200961 | FUR M S PILE 16X0.312 | 184 | FOOT | $168.00 | $67.20 | |
| 65 | 51202305 | DRIVING PILES | 184 | FOOT | $0.0100 | $1.00 | |
| 66 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $6,000.00 | $25,000.00 | |
| 67 | 51500100 | NAME PLATES | 1 | EACH | $1,000.00 | $1,500.00 | |
| 68 | 52000110 | PREF JT STRIP SEAL | 26 | FOOT | $280.00 | $285.00 | |
| 69 | 542A0217 | P CUL CL A 1 12 | 14 | FOOT | $100.00 | $256.00 | |
| 70 | 542A0220 | P CUL CL A 1 15 | 87 | FOOT | $100.00 | $258.00 | |
| 71 | 542A0229 | P CUL CL A 1 24 | 18 | FOOT | $125.00 | $286.00 | |
| 72 | 54213657 | PRC FLAR END SEC 12 | 2 | EACH | $1,000.00 | $1,549.00 | |
| 73 | 54213660 | PRC FLAR END SEC 15 | 10 | EACH | $1,250.00 | $1,643.00 | |
| 74 | 54213669 | PRC FLAR END SEC 24 | 2 | EACH | $1,500.00 | $1,974.00 | |
| 75 | 58600101 | GRANULAR BACKFILL STR | 38 | CU YD | $60.00 | $137.00 | |
| 76 | 58700300 | CONCRETE SEALER | 169 | SQ FT | $2.00 | $4.00 | |
| 77 | 59100100 | GEOCOMPOSITE WALL DR | 34 | SQ YD | $50.00 | $30.00 | |
| 78 | 60146304 | P UNDR FOR STRUCT 4 | 70 | FOOT | $30.00 | $43.25 | |
| 79 | 60600605 | CONC CURB TB | 31 | FOOT | $50.00 | $75.00 | |
| 80 | 66900200 | NON SPL WASTE DISPOSL | 2,380 | CU YD | $90.00 | $87.00 | |
| 81 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,925.00 | $400.00 | |
| 82 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,475.00 | $4,900.00 | |
| 83 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,475.00 | $500.00 | |
| 84 | 66901006 | REG SUB MON | 20 | CAL DA | $990.00 | $750.00 | |
| 85 | 67100100 | MOBILIZATION | 1 | L SUM | $206,854.01 | $294,900.00 | |
| 86 | 72000100 | SIGN PANEL T1 | 57.5 | SQ FT | $27.50 | $28.00 | |
| 87 | 72400100 | REMOV SIN PAN ASSY TA | 2 | EACH | $82.50 | $500.00 | |
| 88 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $302.50 | $1,100.00 | |
| 89 | 72900100 | METAL POST TY A | 188 | FOOT | $16.50 | $18.00 | |
| 90 | 73000100 | WOOD SIN SUPPORT | 69 | FOOT | $27.50 | $30.00 | |
| 91 | 78000100 | THPL PVT MK LTR & SYM | 64 | SQ FT | $30.25 | $10.00 | |
| 92 | 78001110 | PAINT PVT MK LINE 4 | 2,937 | FOOT | $0.8300 | $2.25 |