23-00102-00-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $448,478 | ||
| 2 | D. Construction, Inc. | $453,611 | +1.1% | |
| 3 | Gallagher Asphalt Corporation | $469,756 | +4.7% | |
| 4 | Lindahl Brothers, Inc. | $471,380 | +5.1% | |
| 5 | K-Five Construction Corporation | $489,489 | +9.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 D. Construction… | #3 Gallagher Aspha… | #4 Lindahl Brother… | #5 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0004514 | HMA DRIVEWAY PAVT 4 | 390 | SQ YD | $55.50 | $35.00 | $50.00 | $60.00 | $32.10 | |
| 2 | Z0017400 | DRAIN UTIL STR ADJ | 28 | EACH | $475.00 | $600.00 | $430.00 | $655.00 | $1,125.00 | |
| 3 | Z0017700 | DRAIN UTIL STR RECON | 1 | EACH | $1,275.00 | $1,500.00 | $1,280.00 | $1,805.00 | $2,125.00 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 60 | SQ FT | $31.00 | $25.00 | $20.00 | $30.00 | $30.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 7 | 21101615 | TOPSOIL F & P 4 | 500 | SQ YD | $0.0100 | $1.10 | $1.00 | $1.00 | $7.00 | |
| 8 | 25200110 | SODDING SALT TOLERANT | 500 | SQ YD | $0.0100 | $25.30 | $23.00 | $23.00 | $15.00 | |
| 9 | 25200200 | SUPPLE WATERING | 15 | UNIT | $0.0100 | $27.50 | $23.00 | $25.00 | $0.0100 | |
| 10 | 28000510 | INLET FILTERS | 22 | EACH | $175.00 | $250.00 | $180.00 | $323.00 | $175.00 | |
| 11 | 35101600 | AGG BASE CSE B 4 | 255 | SQ YD | $5.25 | $5.50 | $5.00 | $5.50 | $5.00 | |
| 12 | 35800100 | PREPARATION OF BASE | 170 | SQ YD | $0.0100 | $5.00 | $0.0100 | $5.00 | $0.0100 | |
| 13 | 35800200 | AGG BASE REPAIR | 100 | TON | $0.0100 | $50.00 | $0.0100 | $24.25 | $18.00 | |
| 14 | 40201000 | AGGREGATE-TEMP ACCESS | 75 | TON | $47.00 | $50.00 | $40.00 | $40.00 | $20.00 | |
| 15 | 40600290 | BIT MATLS TACK CT | 5,405 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 16 | 40600370 | LONG JOINT SEALANT | 2,900 | FOOT | $4.85 | $4.84 | $5.00 | $4.20 | $5.25 | |
| 17 | 40600982 | HMA SURF REM BUTT JT | 100 | SQ YD | $0.0100 | $0.0100 | $40.00 | $28.00 | $5.00 | |
| 18 | 40603200 | P HMA BC IL-4.75 N50 | 350 | TON | $124.50 | $103.00 | $145.00 | $122.00 | $165.00 | |
| 19 | 40604060 | HMA SC IL-9.5 D N50 | 925 | TON | $84.50 | $81.00 | $100.00 | $85.00 | $105.00 | |
| 20 | 42300300 | PCC DRIVEWAY PAVT 7 | 15 | SQ YD | $104.00 | $110.00 | $100.00 | $115.00 | $100.00 | |
| 21 | 42400200 | PC CONC SIDEWALK 5 | 2,300 | SQ FT | $10.25 | $11.00 | $10.00 | $10.00 | $10.00 | |
| 22 | 42400800 | DETECTABLE WARNINGS | 60 | SQ FT | $30.00 | $31.90 | $29.00 | $40.00 | $29.00 | |
| 23 | 44000159 | HMA SURF REM 2 1/2 | 8,005 | SQ YD | $3.05 | $2.50 | $3.30 | $5.00 | $5.00 | |
| 24 | 44000200 | DRIVE PAVEMENT REM | 405 | SQ YD | $31.00 | $29.70 | $17.00 | $25.00 | $18.00 | |
| 25 | 44000500 | COMB CURB GUTTER REM | 1,670 | FOOT | $15.50 | $16.50 | $15.00 | $10.00 | $15.00 | |
| 26 | 44000600 | SIDEWALK REM | 2,300 | SQ FT | $2.00 | $2.20 | $2.00 | $3.80 | $2.00 | |
| 27 | 44201749 | CL D PATCH T1 9 | 20 | SQ YD | $131.44 | $150.00 | $200.00 | $110.00 | $35.00 | |
| 28 | 44201753 | CL D PATCH T2 9 | 50 | SQ YD | $101.83 | $120.00 | $150.00 | $110.00 | $35.00 | |
| 29 | 44201757 | CL D PATCH T3 9 | 50 | SQ YD | $94.94 | $110.00 | $120.00 | $110.00 | $35.00 | |
| 30 | 44201759 | CL D PATCH T4 9 | 50 | SQ YD | $86.26 | $100.00 | $110.00 | $110.00 | $35.00 | |
| 31 | 60605000 | COMB CC&G TY B-6.24 | 1,670 | FOOT | $64.00 | $49.50 | $46.00 | $40.00 | $45.00 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $24,000.00 | $25,000.00 | $28,000.00 | $26,500.00 | $29,606.80 | |
| 33 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $16,300.00 | $7,500.00 | $20,000.00 | $9,500.00 | |
| 34 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 35 | 70300100 | SHORT TERM PAVT MKING | 600 | FOOT | $0.0100 | $0.0100 | $2.20 | $1.00 | $4.00 | |
| 36 | 70300150 | SHRT TRM PAVT MK REM | 200 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $2.00 | |
| 37 | 78000100 | THPL PVT MK LTR & SYM | 40 | SQ FT | $5.50 | $6.05 | $6.00 | $5.50 | $5.50 | |
| 38 | 78000200 | THPL PVT MK LINE 4 | 5,260 | FOOT | $0.8500 | $0.9000 | $1.10 | $0.8200 | $0.8200 | |
| 39 | 78000400 | THPL PVT MK LINE 6 | 195 | FOOT | $1.45 | $1.54 | $1.50 | $1.40 | $1.40 | |
| 40 | 78000600 | THPL PVT MK LINE 12 | 350 | FOOT | $2.80 | $3.03 | $3.00 | $2.75 | $2.75 | |
| 41 | 78000650 | THPL PVT MK LINE 24 | 50 | FOOT | $5.65 | $6.05 | $6.00 | $5.50 | $5.50 | |
| 42 | 78100100 | RAISED REFL PAVT MKR | 125 | EACH | $49.00 | $52.80 | $58.00 | $48.00 | $48.00 | |
| 43 | 78300200 | RAISED REF PVT MK REM | 125 | EACH | $0.0100 | $10.00 | $10.00 | $30.00 | $16.00 | |
| 44 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $1,928.32 | $1,650.00 | $1,950.00 | $1,828.00 | $1,828.00 | |
| 45 | 87301305 | ELCBL C LEAD 14 1PR | 60 | FOOT | $0.2500 | $19.04 | $0.2500 | $0.2400 | $0.2400 | |
| 46 | 88600100 | DET LOOP T1 | 80 | FOOT | $19.31 | $28.19 | $18.50 | $18.30 | $18.30 | |
| 47 | 89502300 | REM ELCBL FR CON | 60 | FOOT | $0.0500 | $9.15 | $0.0200 | $0.0200 | $0.0200 |