20-00016-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Alliance Contractors, Inc. Low bidder | $2,849,871 | ||
| 2 | Lenny Hoffman Excavating, Inc. | $2,987,655 | +4.8% | |
| 3 | Lorig Construction Company | $3,074,214 | +7.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Alliance Contra… | #2 Lenny Hoffman E… | #3 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX008916 | CONT STIFFNESS COLUMN | 1 | L SUM | $294,000.00 | $605,000.00 | $300,000.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,500.00 | $11,725.00 | $250.00 | |
| 3 | X0900064 | MEMB WTRPRF SYS B STR | 192 | SQ YD | $59.97 | $95.00 | $65.00 | |
| 4 | X1200274 | TEMP BYPASS PUMP SYS | 1 | L SUM | $549,200.00 | $375,000.00 | $1,000.00 | |
| 5 | X2130010 | EXPLOR TRENCH SPL | 100 | FOOT | $25.00 | $45.00 | $110.00 | |
| 6 | X2511630 | EROS CONT BLANKET SPL | 7,800 | SQ YD | $1.50 | $1.72 | $1.50 | |
| 7 | X4021000 | TEMP ACCESS- PRIV ENT | 9 | EACH | $250.00 | $500.00 | $800.00 | |
| 8 | X4400196 | HMA SURF REM SPL | 81 | SQ YD | $16.00 | $23.00 | $10.00 | |
| 9 | X4420210 | TEMPORARY PATCHING | 135 | SQ YD | $175.00 | $50.00 | $40.00 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $113,625.00 | $183,200.00 | $550,000.00 | |
| 11 | X7810300 | RCSD REFL PAVT MARKER | 270 | EACH | $33.54 | $34.00 | $30.00 | |
| 12 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,700.00 | $10,000.00 | $225,000.00 | |
| 13 | Z0022800 | FENCE REMOVAL | 450 | FOOT | $9.50 | $10.00 | $11.00 | |
| 14 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 16 | 20100110 | TREE REMOV 6-15 | 1,186 | UNIT | $14.95 | $17.20 | $15.00 | |
| 17 | 20100210 | TREE REMOV OVER 15 | 711 | UNIT | $21.45 | $24.75 | $22.00 | |
| 18 | 20101100 | TREE TRUNK PROTECTION | 15 | EACH | $225.00 | $258.75 | $90.00 | |
| 19 | 20101200 | TREE ROOT PRUNING | 15 | EACH | $85.00 | $97.75 | $240.00 | |
| 20 | 20200100 | EARTH EXCAVATION | 972 | CU YD | $10.00 | $30.00 | $46.00 | |
| 21 | 20200600 | EXC & GR EX SHOULDER | 9 | UNIT | $1,500.00 | $400.00 | $700.00 | |
| 22 | 20201200 | REM & DISP UNS MATL | 852 | CU YD | $15.00 | $30.00 | $61.00 | |
| 23 | 20400800 | FURNISHED EXCAVATION | 159 | CU YD | $1.00 | $25.00 | $55.00 | |
| 24 | 20700220 | POROUS GRAN EMBANK | 66 | CU YD | $70.00 | $30.00 | $200.00 | |
| 25 | 20800150 | TRENCH BACKFILL | 675 | CU YD | $32.00 | $30.00 | $61.00 | |
| 26 | 21101615 | TOPSOIL F & P 4 | 7,800 | SQ YD | $4.20 | $0.1000 | $4.20 | |
| 27 | 25000210 | SEEDING CL 2A | 1.5 | ACRE | $2,200.00 | $25,047.00 | $2,200.00 | |
| 28 | 25000314 | SEEDING CL 4B | 0.5 | ACRE | $4,500.00 | $25,047.00 | $4,500.00 | |
| 29 | 25000400 | NITROGEN FERT NUTR | 180 | POUND | $2.00 | $1.15 | $2.00 | |
| 30 | 25000600 | POTASSIUM FERT NUTR | 180 | POUND | $2.00 | $1.15 | $2.00 | |
| 31 | 28000305 | TEMP DITCH CHECKS | 100 | FOOT | $8.00 | $12.00 | $8.00 | |
| 32 | 28000400 | PERIMETER EROS BAR | 2,440 | FOOT | $3.00 | $3.00 | $3.00 | |
| 33 | 28000510 | INLET FILTERS | 9 | EACH | $180.00 | $180.00 | $180.00 | |
| 34 | 28100107 | STONE RIPRAP CL A4 | 44 | SQ YD | $200.00 | $105.00 | $180.00 | |
| 35 | 28200200 | FILTER FABRIC | 45 | SQ YD | $1.00 | $20.00 | $6.00 | |
| 36 | 40600290 | BIT MATLS TACK CT | 13,094 | POUND | $0.0100 | $0.0100 | $0.2000 | |
| 37 | 40600370 | LONG JOINT SEALANT | 7,824 | FOOT | $2.77 | $3.38 | $4.00 | |
| 38 | 40600400 | MIX CR JTS FLANGEWYS | 5 | TON | $100.00 | $172.50 | $500.00 | |
| 39 | 40600982 | HMA SURF REM BUTT JT | 158 | SQ YD | $1.00 | $20.70 | $25.00 | |
| 40 | 40603080 | HMA BC IL-19.0 N50 | 40 | TON | $224.25 | $166.75 | $260.00 | |
| 41 | 40603200 | P HMA BC IL-4.75 N50 | 1,150 | TON | $97.75 | $123.85 | $115.00 | |
| 42 | 40604060 | HMA SC IL-9.5 D N50 | 2,370 | TON | $83.70 | $103.90 | $99.00 | |
| 43 | 40800050 | INCIDENTAL HMA SURF | 69 | TON | $185.00 | $104.65 | $250.00 | |
| 44 | 44000160 | HMA SURF REM 2 3/4 | 19,980 | SQ YD | $4.20 | $3.32 | $4.50 | |
| 45 | 44000400 | GUTTER REM | 204 | FOOT | $15.00 | $20.00 | $16.00 | |
| 46 | 44201717 | CL D PATCH T2 6 | 335 | SQ YD | $30.00 | $64.91 | $80.00 | |
| 47 | 44201721 | CL D PATCH T3 6 | 335 | SQ YD | $30.00 | $64.91 | $80.00 | |
| 48 | 44201723 | CL D PATCH T4 6 | 335 | SQ YD | $30.00 | $64.91 | $80.00 | |
| 49 | 48101200 | AGGREGATE SHLDS B | 420 | TON | $91.80 | $63.19 | $55.00 | |
| 50 | 48203029 | HMA SHOULDERS 8 | 490 | SQ YD | $43.30 | $75.65 | $80.00 | |
| 51 | 50105220 | PIPE CULVERT REMOV | 328 | FOOT | $725.00 | $10.00 | $50.00 | |
| 52 | 50200450 | REM/DISP UNS MATL-STR | 115 | CU YD | $15.00 | $21.00 | $75.00 | |
| 53 | 50800105 | REINFORCEMENT BARS | 36,740 | POUND | $1.70 | $2.00 | $1.50 | |
| 54 | 50901720 | BICYCLE RAILING | 31 | FOOT | $1,048.16 | $419.75 | $365.00 | |
| 55 | 51500100 | NAME PLATES | 1 | EACH | $1,000.00 | $1,150.00 | $555.05 | |
| 56 | 54003000 | CONC BOX CUL | 197 | CU YD | $1,505.00 | $1,731.00 | $2,400.00 | |
| 57 | 542A0217 | P CUL CL A 1 12 | 17 | FOOT | $183.00 | $183.00 | $115.00 | |
| 58 | 542A8215 | P CUL CL A 2 EQRS 30 | 37 | FOOT | $276.00 | $236.00 | $180.00 | |
| 59 | 54213657 | PRC FLAR END SEC 12 | 4 | EACH | $2,576.00 | $1,576.00 | $1,500.00 | |
| 60 | 54213660 | PRC FLAR END SEC 15 | 1 | EACH | $2,842.00 | $1,842.00 | $1,600.00 | |
| 61 | 54214515 | PRC FL END S EQ RS 30 | 2 | EACH | $3,696.00 | $2,696.00 | $3,300.00 | |
| 62 | 550A0050 | STORM SEW CL A 1 12 | 209 | FOOT | $85.00 | $80.00 | $67.00 | |
| 63 | 550A0340 | STORM SEW CL A 2 12 | 844 | FOOT | $85.00 | $80.00 | $61.00 | |
| 64 | 550A0360 | STORM SEW CL A 2 15 | 240 | FOOT | $95.00 | $90.00 | $75.00 | |
| 65 | 59100100 | GEOCOMPOSITE WALL DR | 192 | SQ YD | $35.00 | $35.00 | $35.00 | |
| 66 | 59300100 | CONTR LOW-STRENG MATL | 155 | CU YD | $210.00 | $190.00 | $300.00 | |
| 67 | 60200805 | CB TA 4 DIA T8G | 1 | EACH | $5,410.00 | $3,419.00 | $4,500.00 | |
| 68 | 60240301 | INLETS TB T8G | 5 | EACH | $3,135.00 | $2,150.00 | $3,000.00 | |
| 69 | 60602800 | CONCRETE GUTTER TY B | 204 | FOOT | $75.00 | $86.00 | $40.00 | |
| 70 | 63000001 | SPBGR TY A 6FT POSTS | 560 | FOOT | $31.23 | $40.25 | $35.00 | |
| 71 | 63000030 | SPGR ATT TO CULVERT | 38 | FOOT | $215.00 | $316.25 | $275.00 | |
| 72 | 63000035 | BCK SD PROT OF GRDRL | 365 | FOOT | $17.16 | $20.70 | $18.00 | |
| 73 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,843.72 | $4,025.00 | $3,500.00 | |
| 74 | 63200310 | GUARDRAIL REMOV | 410 | FOOT | $7.82 | $8.00 | $5.00 | |
| 75 | 64200108 | SHOULDER RUM STRIP 8 | 2,760 | FOOT | $2.22 | $3.45 | $3.00 | |
| 76 | 67100100 | MOBILIZATION | 1 | L SUM | $173,000.00 | $167,000.00 | $150,000.00 | |
| 77 | 70300100 | SHORT TERM PAVT MKING | 5,931 | FOOT | $0.5000 | $0.0100 | $0.5000 | |
| 78 | 70300150 | SHRT TRM PAVT MK REM | 3,037 | SQ FT | $0.5000 | $0.0100 | $0.5000 | |
| 79 | 72400100 | REMOV SIN PAN ASSY TA | 2 | EACH | $105.00 | $115.00 | $100.00 | |
| 80 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.26 | $74.75 | $65.00 | |
| 81 | 78000100 | THPL PVT MK LTR & SYM | 146 | SQ FT | $5.75 | $5.75 | $5.00 | |
| 82 | 78000200 | THPL PVT MK LINE 4 | 22,984 | FOOT | $0.6500 | $0.8600 | $0.7500 | |
| 83 | 78000400 | THPL PVT MK LINE 6 | 582 | FOOT | $0.7500 | $1.03 | $0.9000 | |
| 84 | 78000600 | THPL PVT MK LINE 12 | 478 | FOOT | $3.32 | $1.15 | $1.00 | |
| 85 | 78000650 | THPL PVT MK LINE 24 | 26 | FOOT | $5.75 | $5.75 | $5.00 | |
| 86 | 78011000 | GRV RCSD PM LTR & SYM | 146 | SQ FT | $2.75 | $2.30 | $2.00 | |
| 87 | 78011025 | GRV RCSD PVT MRKG 5 | 22,984 | FOOT | $0.4500 | $0.4000 | $0.3500 | |
| 88 | 78011035 | GRV RCSD PVT MRKG 7 | 582 | FOOT | $0.9500 | $0.5100 | $0.4500 | |
| 89 | 78011065 | GRV RCSD PVT MRKG 13 | 478 | FOOT | $3.00 | $1.15 | $1.00 | |
| 90 | 78011125 | GRV RCSD PVT MRKG 25 | 26 | FOOT | $3.35 | $2.30 | $2.00 | |
| 91 | 78200005 | GRDRAIL REF TYPE A | 10 | EACH | $14.18 | $11.50 | $10.00 |