21-00138-00-RS
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $921,953 | ||
| 2 | Builders Paving, LLC | $938,000 | +1.7% | |
| 3 | Arrow Road Construction Co. | $973,789 | +5.6% | |
| 4 | R. W. Dunteman Company | $1,072,048 | +16.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 Builders Paving… | #3 Arrow Road Cons… | #4 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029634 | WEED CONTR PRE-EM GRN | 6 | POUND | $20.00 | $25.00 | $25.00 | $25.00 | |
| 2 | XX008163 | TEMPORARY RAMP SPL | 8 | EACH | $800.00 | $400.00 | $200.00 | $506.36 | |
| 3 | XX008910 | PAVEMENT MARKING SPL | 355 | SQ FT | $14.00 | $13.95 | $14.00 | $13.95 | |
| 4 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,500.00 | $1,000.00 | $500.00 | $3,500.00 | |
| 5 | X2600012 | REM & REL SN P&P ASSY | 2 | EACH | $200.00 | $300.00 | $350.00 | $350.00 | |
| 6 | X4404700 | SIDEWALK REM SPL | 3,294 | SQ FT | $4.00 | $3.00 | $4.00 | $1.79 | |
| 7 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,350.00 | $800.00 | $1,334.00 | $3,250.00 | |
| 8 | X6030310 | FR & LIDS ADJUST SPL | 1 | EACH | $2,800.00 | $2,000.00 | $2,776.00 | $6,950.00 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,400.00 | $6,000.00 | $5,000.00 | $20,000.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $12.00 | $25.00 | $18.00 | $18.00 | |
| 11 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20101400 | NITROGEN FERT NUTR | 6 | POUND | $5.00 | $3.00 | $3.00 | $3.00 | |
| 14 | 20101600 | POTASSIUM FERT NUTR | 6 | POUND | $5.00 | $3.00 | $3.00 | $3.00 | |
| 15 | 20201200 | REM & DISP UNS MATL | 290 | CU YD | $115.00 | $50.00 | $25.00 | $46.74 | |
| 16 | 21001000 | GEOTECH FAB F/GR STAB | 870 | SQ YD | $2.00 | $2.00 | $0.0100 | $1.63 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 274 | SQ YD | $9.00 | $6.00 | $6.00 | $6.00 | |
| 18 | 25200110 | SODDING SALT TOLERANT | 274 | SQ YD | $11.00 | $9.00 | $9.00 | $9.00 | |
| 19 | 25200200 | SUPPLE WATERING | 1 | UNIT | $10.00 | $0.0100 | $0.0100 | $0.0100 | |
| 20 | 28000510 | INLET FILTERS | 76 | EACH | $220.00 | $178.00 | $178.00 | $178.00 | |
| 21 | 30300001 | AGG SUBGRADE IMPROVE | 290 | CU YD | $10.00 | $50.00 | $15.00 | $36.66 | |
| 22 | 31101200 | SUB GRAN MAT B 4 | 523 | SQ YD | $4.00 | $8.00 | $4.00 | $8.31 | |
| 23 | 40600290 | BIT MATLS TACK CT | 16,121 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.6900 | |
| 24 | 40600400 | MIX CR JTS FLANGEWYS | 3 | TON | $1,900.00 | $775.00 | $1,650.00 | $556.68 | |
| 25 | 40600982 | HMA SURF REM BUTT JT | 154 | SQ YD | $30.00 | $40.00 | $15.00 | $13.77 | |
| 26 | 40603080 | HMA BC IL-19.0 N50 | 2,929 | TON | $90.00 | $84.00 | $89.00 | $92.05 | |
| 27 | 40604060 | HMA SC IL-9.5 D N50 | 2,005 | TON | $91.00 | $92.00 | $102.50 | $106.81 | |
| 28 | 42400200 | PC CONC SIDEWALK 5 | 3,245 | SQ FT | $9.00 | $8.00 | $8.00 | $7.99 | |
| 29 | 42400800 | DETECTABLE WARNINGS | 359 | SQ FT | $46.00 | $45.00 | $40.00 | $42.00 | |
| 30 | 44000157 | HMA SURF REM 2 | 477 | SQ YD | $8.00 | $9.50 | $8.25 | $3.21 | |
| 31 | 44000169 | HMA SURF REM 5 | 17,433 | SQ YD | $6.90 | $6.25 | $6.90 | $6.97 | |
| 32 | 44000500 | COMB CURB GUTTER REM | 472 | FOOT | $12.00 | $13.00 | $10.00 | $9.02 | |
| 33 | 44201701 | CL D PATCH T1 5 | 54 | SQ YD | $15.00 | $69.00 | $85.00 | $22.00 | |
| 34 | 44201705 | CL D PATCH T2 5 | 49 | SQ YD | $14.00 | $63.00 | $80.00 | $22.00 | |
| 35 | 44201709 | CL D PATCH T3 5 | 50 | SQ YD | $13.00 | $54.00 | $70.00 | $22.00 | |
| 36 | 44201711 | CL D PATCH T4 5 | 1,739 | SQ YD | $12.00 | $38.50 | $17.00 | $22.00 | |
| 37 | 60250200 | CB ADJUST | 1 | EACH | $725.00 | $550.00 | $713.00 | $650.00 | |
| 38 | 60255500 | MAN ADJUST | 1 | EACH | $725.00 | $800.00 | $713.00 | $685.00 | |
| 39 | 60260100 | INLETS ADJUST | 2 | EACH | $725.00 | $800.00 | $713.00 | $650.00 | |
| 40 | 60265700 | VV ADJUST | 1 | EACH | $725.00 | $800.00 | $713.00 | $685.00 | |
| 41 | 60605000 | COMB CC&G TB6.24 | 472 | FOOT | $55.00 | $53.00 | $55.00 | $45.00 | |
| 42 | 66900200 | NON SPL WASTE DISPOSL | 870 | CU YD | $0.1000 | $15.00 | $1.00 | $90.51 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,950.00 | $2,000.00 | $4,000.00 | $2,000.00 | |
| 44 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,950.00 | $2,300.00 | $3,800.00 | $2,300.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $900.00 | $2,100.00 | $500.00 | $2,100.00 | |
| 46 | 66901006 | REG SUB MON | 1 | CAL DA | $680.00 | $1,000.00 | $5,000.00 | $1,000.00 | |
| 47 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $3,500.00 | $3,000.00 | $3,500.00 | $3,300.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $51,000.00 | $55,937.75 | $58,000.00 | $63,042.57 | |
| 49 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $16,500.00 | $10,459.16 | $57,000.00 | $13,200.00 | |
| 50 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $100.00 | $1.00 | $1.00 | |
| 51 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $100.00 | $1.00 | $1.00 | |
| 52 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $100.00 | $2,500.00 | $2,500.00 | |
| 53 | 70300100 | SHORT TERM PAVT MKING | 3,968 | FOOT | $0.1000 | $0.0100 | $0.6000 | $1.22 | |
| 54 | 70300150 | SHRT TRM PAVT MK REM | 1,984 | SQ FT | $0.1000 | $0.0100 | $0.0100 | $1.36 | |
| 55 | 72000100 | SIGN PANEL T1 | 58 | SQ FT | $22.00 | $30.00 | $35.00 | $35.00 | |
| 56 | 72800100 | TELES STL SIN SUPPORT | 130 | FOOT | $16.00 | $15.00 | $14.00 | $14.00 | |
| 57 | 78000100 | THPL PVT MK LTR & SYM | 894 | SQ FT | $5.00 | $5.50 | $5.50 | $5.75 | |
| 58 | 78000200 | THPL PVT MK LINE 4 | 9,071 | FOOT | $0.7500 | $0.9000 | $0.9000 | $0.9500 | |
| 59 | 78000400 | THPL PVT MK LINE 6 | 849 | FOOT | $1.00 | $2.25 | $2.25 | $1.45 | |
| 60 | 78000600 | THPL PVT MK LINE 12 | 458 | FOOT | $2.00 | $3.50 | $3.50 | $3.32 | |
| 61 | 78000650 | THPL PVT MK LINE 24 | 136 | FOOT | $5.00 | $5.50 | $5.50 | $10.00 | |
| 62 | 78100100 | RAISED REFL PAVT MKR | 189 | EACH | $40.00 | $40.00 | $40.00 | $55.00 | |
| 63 | 78300200 | RAISED REF PVT MK REM | 189 | EACH | $15.00 | $15.00 | $6.00 | $9.83 | |
| 64 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $1,270.00 | $1,270.00 | $1,156.70 | $2,500.00 | |
| 65 | 88600100 | DET LOOP T1 | 510 | FOOT | $17.00 | $16.37 | $16.30 | $17.00 | |
| 66 | 89502376 | REBUILD EX HANDHOLE | 1 | EACH | $1,255.00 | $1,254.00 | $1,968.50 | $2,200.00 |