17-00132-00-MS
- Let date
- Friday, November 6, 2020
- Contract
- 61G77 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- Intersection improvements including curb "bump outs", bus shelters, covered bicycle parking, pavement markings, signage and a pedestrian activated cross- walk warning system on Broadway Avenue from Rice Street to Main Street in Melrose Park.
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $356,565 | ||
| 2 | Martam Construction Incorporated | $367,638 | +3.1% | |
| 3 | Landmark Contractors, Inc. | $383,930 | +7.7% | |
| 4 | A Lamp Concrete Contractors, Inc. | $389,756 | +9.3% | |
| 5 | Alliance Contractors, Inc. | $413,026 | +15.8% | |
| 6 | Sumit Construction Co., Inc. | $419,807 | +17.7% | |
| 7 | Copenhaver Construction, Inc. | $444,282 | +24.6% | |
| 8 | MYS, Incorporated | $483,284 | +35.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 Martam Construc… | #3 Landmark Contra… | #4 A Lamp Concrete… | #5 Alliance Contra… | #6 Sumit Construct… | #7 Copenhaver Cons… | #8 MYS, Incorporat… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX002258 | STRUCTURE ADJ | 4 | EACH | $425.00 | $600.00 | $215.00 | $468.00 | $750.00 | $600.00 | $600.00 | $500.00 | |
| 2 | XX003689 | BUS SHELTER | 2 | EACH | $15,607.52 | $12,800.00 | $12,840.00 | $15,000.00 | $13,710.00 | $12,000.00 | $23,000.00 | $25,000.00 | |
| 3 | XX007021 | PED ACT CRSS WARN SYS | 1 | EACH | $36,453.00 | $34,000.00 | $35,000.00 | $40,000.00 | $36,453.00 | $40,000.00 | $40,000.00 | $43,500.00 | |
| 4 | XX008269 | WAYFINDING SIGN | 5 | EACH | $3,178.00 | $3,300.00 | $3,180.00 | $3,500.00 | $3,178.00 | $600.00 | $300.00 | $3,500.00 | |
| 5 | XX008686 | BIKE SHELTER | 1 | EACH | $20,541.62 | $16,600.00 | $24,960.45 | $25,000.00 | $18,100.00 | $15,000.00 | $28,000.00 | $20,000.00 | |
| 6 | XX009424 | 10 DIA DIP SS PIPE | 130 | FOOT | $92.00 | $75.00 | $155.00 | $101.00 | $83.00 | $210.00 | $115.00 | $200.00 | |
| 7 | X0321309 | CONCRETE PAD | 40 | SQ YD | $65.28 | $65.00 | $73.60 | $150.00 | $90.00 | $90.00 | $90.00 | $125.00 | |
| 8 | X0322917 | PRO SS CONN TO EX MAN | 1 | EACH | $825.00 | $1,800.00 | $917.05 | $908.00 | $1,000.00 | $4,000.00 | $1,500.00 | $900.00 | |
| 9 | X0327979 | PAVMT MRKG REM GRIND | 850 | SQ FT | $1.75 | $1.40 | $1.85 | $1.95 | $3.00 | $3.00 | $4.00 | $3.50 | |
| 10 | X4401198 | HMA SURF REM VAR DP | 1,030 | SQ YD | $4.97 | $14.00 | $13.80 | $8.00 | $13.80 | $20.00 | $15.00 | $23.00 | |
| 11 | X6022402 | MAN TA 4D T1F CL SPL | 1 | EACH | $7,950.00 | $4,500.00 | $8,372.55 | $8,750.00 | $6,000.00 | $6,500.00 | $3,000.00 | $5,500.00 | |
| 12 | X6022805 | CB TA 4D T1F OL SPL | 3 | EACH | $5,150.00 | $3,800.00 | $3,930.00 | $5,700.00 | $7,500.00 | $5,000.00 | $3,000.00 | $4,750.00 | |
| 13 | X7200105 | SIGN PANEL T1 SPL | 30 | SQ FT | $142.00 | $50.00 | $142.00 | $160.00 | $142.00 | $36.00 | $55.00 | $160.00 | |
| 14 | Z0003855 | BICYCLE RACKS | 4 | EACH | $721.31 | $500.00 | $929.65 | $800.00 | $1,020.00 | $550.00 | $900.00 | $825.00 | |
| 15 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $15.00 | $18.00 | $16.00 | $20.00 | $20.00 | $16.00 | $24.00 | $25.00 | |
| 16 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $5,000.00 | $6,113.70 | $6,000.00 | $1,000.00 | $10,000.00 | $7,000.00 | $5,000.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 25 | CU YD | $67.34 | $132.00 | $78.90 | $100.00 | $20.00 | $48.00 | $65.00 | $75.00 | |
| 18 | 20800150 | TRENCH BACKFILL | 15 | CU YD | $23.00 | $145.00 | $71.35 | $26.00 | $60.00 | $45.00 | $60.00 | $40.00 | |
| 19 | 21101615 | TOPSOIL F & P 4 | 200 | SQ YD | $10.00 | $12.00 | $10.00 | $33.00 | $10.00 | $8.00 | $11.00 | $11.50 | |
| 20 | 25200110 | SODDING SALT TOLERANT | 200 | SQ YD | $15.00 | $17.00 | $15.00 | $33.00 | $15.00 | $18.00 | $17.00 | $17.25 | |
| 21 | 28000510 | INLET FILTERS | 5 | EACH | $150.00 | $150.00 | $155.00 | $165.00 | $50.00 | $300.00 | $40.00 | $200.00 | |
| 22 | 35101600 | AGG BASE CSE B 4 | 40 | SQ YD | $24.16 | $18.00 | $10.75 | $13.00 | $20.00 | $6.25 | $12.00 | $12.00 | |
| 23 | 40600290 | BIT MATLS TACK CT | 470 | POUND | $2.00 | $1.00 | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.0200 | $1.15 | |
| 24 | 40603080 | HMA BC IL-19.0 N50 | 145 | TON | $103.84 | $135.00 | $157.40 | $109.00 | $157.40 | $150.00 | $170.00 | $170.00 | |
| 25 | 40604060 | HMA SC IL-9.5 D N50 | 90 | TON | $99.18 | $162.00 | $310.70 | $141.00 | $310.70 | $210.00 | $350.00 | $225.00 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 6,000 | SQ FT | $5.41 | $7.00 | $8.00 | $8.10 | $8.20 | $11.00 | $7.00 | $10.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 80 | SQ FT | $29.64 | $40.00 | $30.60 | $35.00 | $35.00 | $40.00 | $28.00 | $35.00 | |
| 28 | 44000100 | PAVEMENT REM | 350 | SQ YD | $10.24 | $18.00 | $12.10 | $19.00 | $20.00 | $22.00 | $15.00 | $30.00 | |
| 29 | 44000500 | COMB CURB GUTTER REM | 470 | FOOT | $5.89 | $6.00 | $11.80 | $6.00 | $20.00 | $10.00 | $8.00 | $15.00 | |
| 30 | 44000600 | SIDEWALK REM | 2,800 | SQ FT | $2.55 | $2.00 | $2.00 | $1.30 | $6.00 | $3.50 | $3.00 | $5.00 | |
| 31 | 60257900 | MAN RECONST | 1 | EACH | $1,450.00 | $1,600.00 | $1,965.00 | $1,600.00 | $3,500.00 | $1,100.00 | $1,000.00 | $1,500.00 | |
| 32 | 60500040 | REMOV MANHOLES | 1 | EACH | $310.00 | $600.00 | $735.10 | $345.00 | $500.00 | $700.00 | $600.00 | $500.00 | |
| 33 | 60500060 | REMOV INLETS | 2 | EACH | $90.00 | $200.00 | $359.90 | $100.00 | $100.00 | $200.00 | $350.00 | $300.00 | |
| 34 | 60604100 | COMB CC&G TB6.12 MOD | 570 | FOOT | $24.26 | $32.00 | $45.75 | $40.00 | $43.40 | $45.00 | $26.00 | $40.00 | |
| 35 | 66900200 | NON SPL WASTE DISPOSL | 40 | CU YD | $83.74 | $125.00 | $95.10 | $50.00 | $59.00 | $80.00 | $80.00 | $125.00 | |
| 36 | 66900205 | SPL WASTE DISPOSAL | 15 | CU YD | $259.15 | $325.00 | $101.50 | $100.00 | $63.00 | $250.00 | $280.00 | $400.00 | |
| 37 | 66900210 | HAZARD WASTE DISPOSAL | 15 | CU YD | $654.15 | $685.00 | $538.45 | $150.00 | $500.00 | $600.00 | $700.00 | $750.00 | |
| 38 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,450.00 | $1,800.00 | $1,500.00 | $1,900.00 | $1,500.00 | $1,500.00 | $1,800.00 | $2,100.00 | |
| 39 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,600.00 | $2,500.00 | $1,700.00 | $3,250.00 | $1,700.00 | $4,000.00 | $4,100.00 | $2,800.00 | |
| 40 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,800.00 | $2,500.00 | $2,000.00 | $990.00 | $2,000.00 | $3,200.00 | $3,000.00 | $2,500.00 | |
| 41 | 66901006 | REG SUB MON | 4 | CAL DA | $940.00 | $800.00 | $650.00 | $750.00 | $650.00 | $500.00 | $1,050.00 | $1,100.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $49,382.08 | $22,000.00 | $18,600.00 | $21,000.00 | $34,200.00 | $15,000.00 | $25,150.00 | $25,000.00 | |
| 43 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $7,789.02 | $25,800.00 | $5,400.00 | $25,000.00 | $5,300.00 | $15,000.00 | $55,000.00 | $2,500.00 | |
| 44 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | $100.00 | $200.00 | $7,500.00 | |
| 45 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $100.00 | $100.00 | $200.00 | $5,000.00 | |
| 46 | 70103815 | TR CONT SURVEILLANCE | 4 | CAL DA | $800.00 | $800.00 | $200.00 | $500.00 | $1,200.00 | $700.00 | $0.0100 | $2.00 | |
| 47 | 78000400 | THPL PVT MK LINE 6 | 40 | FOOT | $5.50 | $3.00 | $1.85 | $6.05 | $5.50 | $4.00 | $7.00 | $3.00 | |
| 48 | 78000600 | THPL PVT MK LINE 12 | 1,500 | FOOT | $2.55 | $4.40 | $2.95 | $2.85 | $2.55 | $7.00 | $3.00 | $4.65 | |
| 49 | 78000650 | THPL PVT MK LINE 24 | 160 | FOOT | $10.00 | $9.00 | $4.85 | $11.00 | $10.00 | $14.00 | $12.00 | $9.50 |