$46.17Avg low bid / SQ FT
$43.83Avg of all bids
—Avg engineer's estimate
15Jobs · 798.3 SQ FT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 9 | 560.3 | $44.32 | $38.89 |
| 2025 | 6 | 238 | $50.52 | $61.19 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 66P22 | BureauDistrict 3 | 5 SQ FT | $30.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Jul 31, 2026 | 91669 | EdgarDistrict 5 | 36 SQ FT | $77.25 | Evergreen Roadworks, LLC |
| Jun 12, 2026 | 85791 | WinnebagoDistrict 2 | 2 SQ FT | $157.00 | N-Trak Group LLC |
| Feb 27, 2026 | 61M26 | CookDistrict 1 | 240 SQ FT | $30.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61M27 | CookDistrict 1 | 77 SQ FT | $25.00 | A Lamp Concrete Contractors, Inc. |
| Feb 27, 2026 | 61M28 | CookDistrict 1 | 73 SQ FT | $25.00 | A Lamp Concrete Contractors, Inc. |
| Jan 16, 2026 | 64U16 | HenryDistrict 2 | 45 SQ FT | $150.00 | Advanced Asphalt Company |
| Jan 16, 2026 | 97871 | St. ClairDistrict 8 | 73.3 SQ FT | $46.25 | The Kilian Corporation |
| Jan 16, 2026 | 64U21 | LeeDistrict 2 | 9 SQ FT | $55.00 | Martin & Company Excavating |
| Nov 7, 2025 | 61J94 | CookDistrict 1 | 41 SQ FT | $30.00 | A Lamp Concrete Contractors, Inc. |
| Nov 7, 2025 | 62U41 | CookDistrict 1 | 125 SQ FT | $50.00 | Lorig Construction Company |
| Aug 1, 2025 | 99760 | WilliamsonDistrict 9 | 23 SQ FT | $90.00 | Samron Midwest Contracting, Inc. |
| Apr 25, 2025 | 78373 | WilliamsonDistrict 9 | 22 SQ FT | $56.00 | Samron Midwest Contracting, Inc. |
| Apr 25, 2025 | 64U31 | CarrollDistrict 2 | 18 SQ FT | $45.00 | Martin & Company Excavating |
| Mar 7, 2025 | 64U33 | WhitesideDistrict 2 | 9 SQ FT | $48.00 | Civil Constructors Inc. dba Helm Civil and Valley Construction Co., J.V. |