13-02113-01-BR
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,359,864 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… |
|---|---|---|---|---|---|---|
| 1 | A2004420 | T-GINKGO BILOBA 2-1/2 | 5 | EACH | $605.00 | |
| 2 | A2006516 | T-QUERCUS BICOL 2 | 11 | EACH | $605.00 | |
| 3 | B2002220 | T-CRAT VR WK TF 2-1/2 | 6 | EACH | $605.00 | |
| 4 | B2006220 | T-SYRING RET TF 2-1/2 | 7 | EACH | $605.00 | |
| 5 | X0300249 | REMOV EX GATE | 1 | EACH | $1,225.38 | |
| 6 | X0322918 | PRO MAN/CB CON OV SS | 4 | EACH | $3,200.00 | |
| 7 | X0322936 | REMOV EX FLAR END SEC | 1 | EACH | $500.00 | |
| 8 | X0325522 | REINS EX STL GT ASSMB | 1 | EACH | $2,859.97 | |
| 9 | X2010400 | STUMP REMOVAL ONLY | 100 | UNIT | $3.30 | |
| 10 | X2020410 | EARTH EXCAVATION SPL | 374 | CU YD | $40.00 | |
| 11 | X2510900 | TURF REINF MAT SPL | 1,737 | SQ YD | $27.50 | |
| 12 | X2800500 | INLET PROTECTION SPL | 6 | EACH | $165.00 | |
| 13 | X4021000 | TEMP ACCESS- PRIV ENT | 3 | EACH | $500.00 | |
| 14 | X4023000 | TEMP ACCESS- ROAD | 2 | EACH | $1,250.00 | |
| 15 | X4024000 | TEMP ACCESS- FLD ENT | 1 | EACH | $500.00 | |
| 16 | X5091755 | PARAPET RAILING SPL | 127 | FOOT | $211.35 | |
| 17 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $20,000.00 | |
| 18 | Z0013797 | STAB CONSTR ENTRANCE | 200 | SQ YD | $32.00 | |
| 19 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,000.00 | |
| 20 | Z0046304 | P UNDR FOR STRUCT 4 | 103 | FOOT | $35.00 | |
| 21 | Z0076870 | UNDR CONNECT TO STR | 1 | EACH | $650.00 | |
| 22 | 20100110 | TREE REMOV 6-15 | 982 | UNIT | $13.20 | |
| 23 | 20100210 | TREE REMOV OVER 15 | 360 | UNIT | $17.60 | |
| 24 | 20101100 | TREE TRUNK PROTECTION | 17 | EACH | $137.50 | |
| 25 | 20101200 | TREE ROOT PRUNING | 17 | EACH | $99.00 | |
| 26 | 20101300 | TREE PRUN 1-10 | 12 | EACH | $82.50 | |
| 27 | 20101350 | TREE PRUN OVER 10 | 5 | EACH | $110.00 | |
| 28 | 20200100 | EARTH EXCAVATION | 2,990 | CU YD | $18.00 | |
| 29 | 20400800 | FURNISHED EXCAVATION | 959 | CU YD | $30.00 | |
| 30 | 20800150 | TRENCH BACKFILL | 28 | CU YD | $50.00 | |
| 31 | 21001000 | GEOTECH FAB F/GR STAB | 2,579 | SQ YD | $3.00 | |
| 32 | 21101505 | TOPSOIL EXC & PLAC | 2,209 | CU YD | $16.00 | |
| 33 | 25000312 | SEEDING CL 4A | 1.25 | ACRE | $1,331.00 | |
| 34 | 25000314 | SEEDING CL 4B | 0.5 | ACRE | $2,662.00 | |
| 35 | 25100127 | MULCH METHOD 3A | 1.75 | ACRE | $3,993.00 | |
| 36 | 25100635 | HD EROS CONTR BLANKET | 5,225 | SQ YD | $2.20 | |
| 37 | 28000250 | TEMP EROS CONTR SEED | 105 | POUND | $6.60 | |
| 38 | 28000305 | TEMP DITCH CHECKS | 120 | FOOT | $16.50 | |
| 39 | 28000400 | PERIMETER EROS BAR | 3,737 | FOOT | $2.20 | |
| 40 | 28100107 | STONE RIPRAP CL A4 | 491 | SQ YD | $60.00 | |
| 41 | 28200200 | FILTER FABRIC | 691 | SQ YD | $3.00 | |
| 42 | 30300001 | AGG SUBGRADE IMPROVE | 374 | CU YD | $50.00 | |
| 43 | 30300112 | AGG SUBGRADE IMPR 12 | 2,579 | SQ YD | $16.00 | |
| 44 | 35101800 | AGG BASE CSE B 6 | 483 | SQ YD | $10.00 | |
| 45 | 40600290 | BIT MATLS TACK CT | 1,063 | POUND | $0.0100 | |
| 46 | 40603080 | HMA BC IL-19.0 N50 | 794 | TON | $73.00 | |
| 47 | 40604060 | HMA SC IL-9.5 D N50 | 266 | TON | $79.00 | |
| 48 | 44000100 | PAVEMENT REM | 2,335 | SQ YD | $12.00 | |
| 49 | 44000200 | DRIVE PAVEMENT REM | 152 | SQ YD | $11.00 | |
| 50 | 48101500 | AGGREGATE SHLDS B 6 | 560 | SQ YD | $10.00 | |
| 51 | 48203027 | HMA SHOULDERS 7 1/2 | 504 | SQ YD | $35.00 | |
| 52 | 50100100 | REM EXIST STRUCT | 1 | EACH | $30,000.00 | |
| 53 | 50105220 | PIPE CULVERT REMOV | 144 | FOOT | $15.00 | |
| 54 | 50200100 | STRUCTURE EXCAVATION | 253 | CU YD | $35.00 | |
| 55 | 50300225 | CONC STRUCT | 44.6 | CU YD | $900.00 | |
| 56 | 50300255 | CONC SUP-STR | 101.8 | CU YD | $1,350.00 | |
| 57 | 50300260 | BR DECK GROOVING | 322 | SQ YD | $13.00 | |
| 58 | 50300300 | PROTECTIVE COAT | 404 | SQ YD | $1.50 | |
| 59 | 50301350 | CONC SUPSTR APP SLAB | 90.7 | CU YD | $400.00 | |
| 60 | 50800205 | REINF BARS, EPOXY CTD | 72,620 | POUND | $1.80 | |
| 61 | 51200959 | FUR M S PILE 14X0.312 | 1,200 | FOOT | $60.00 | |
| 62 | 51202305 | DRIVING PILES | 1,200 | FOOT | $0.0100 | |
| 63 | 51203200 | TEST PILE MET SHELLS | 4 | EACH | $4,000.00 | |
| 64 | 51204650 | PILE SHOES | 24 | EACH | $350.00 | |
| 65 | 51500100 | NAME PLATES | 1 | EACH | $600.00 | |
| 66 | 54213453 | END SECTIONS 18 | 4 | EACH | $750.00 | |
| 67 | 54213459 | END SECTIONS 24 | 1 | EACH | $900.00 | |
| 68 | 550A0090 | STORM SEW CL A 1 18 | 31 | FOOT | $75.00 | |
| 69 | 550A0380 | STORM SEW CL A 2 18 | 353 | FOOT | $80.00 | |
| 70 | 550A0410 | STORM SEW CL A 2 24 | 98 | FOOT | $92.00 | |
| 71 | 58600101 | GRANULAR BACKFILL STR | 790 | CU YD | $50.00 | |
| 72 | 59100100 | GEOCOMPOSITE WALL DR | 33 | SQ YD | $35.00 | |
| 73 | 60100060 | CONC HDWL FOR P DRAIN | 3 | EACH | $300.00 | |
| 74 | 60108204 | PIPE UNDERDR T 2 4 | 1,865 | FOOT | $20.00 | |
| 75 | 60108206 | PIPE UNDERDR T 2 6 | 170 | FOOT | $30.00 | |
| 76 | 60200805 | CB TA 4 DIA T8G | 5 | EACH | $3,000.00 | |
| 77 | 60224005 | MAN TA 6 DIA T8G | 1 | EACH | $5,000.00 | |
| 78 | 63100089 | TRAF BAR TERM T6B | 4 | EACH | $3,707.51 | |
| 79 | 63100169 | TR BAR TRM T1 SPL FLR | 4 | EACH | $3,650.48 | |
| 80 | 63200310 | GUARDRAIL REMOV | 108 | FOOT | $8.51 | |
| 81 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $4,000.00 | |
| 82 | 67100100 | MOBILIZATION | 1 | L SUM | $76,973.46 | |
| 83 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $49.29 |