$20,363.10Avg low bid / EACH
$19,972.38Avg of all bids
—Avg engineer's estimate
28Jobs · 49 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 12 | 23 | $20,347.52 | $20,128.88 |
| 2025 | 16 | 26 | $20,376.88 | $19,826.67 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 61M10 | Kane, DupageDistrict 1 | 3 EACH | $26,456.16 | K-Five Construction Corporation |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 1 EACH | $22,692.08 | D. Construction, Inc. |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 3 EACH | $19,479.76 | Martam Construction Incorporated |
| Jun 12, 2026 | 64N73 | StephensonDistrict 2 | 1 EACH | $22,855.60 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Jun 12, 2026 | 76U38 | Madison, St.clairDistrict 8 | 2 EACH | $14,700.00 | Gerstner Electric, Inc. |
| Jun 12, 2026 | 80C89 | Cook, LakeDistrict 1 | 3 EACH | $17,318.43 | H & H Electric Co. |
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 3 EACH | $19,559.68 | Plote Construction, Inc. |
| Apr 24, 2026 | 62P51 | CookDistrict 1 | 1 EACH | $19,491.14 | Martam Construction Incorporated |
| Apr 24, 2026 | 76R78 | St.clairDistrict 8 | 3 EACH | $20,150.00 | Gerstner Electric, Inc. |
| Feb 27, 2026 | 80B75 | LakeDistrict 1 | 1 EACH | $20,262.00 | Peter Baker & Son Co. |
| Jan 16, 2026 | 66R42 | KankakeeDistrict 3 | 1 EACH | $25,000.00 | Van-Mack Electric Co. |
| Jan 16, 2026 | 85780 | Rock IslandDistrict 2 | 1 EACH | $19,400.00 | McCarthy Improvement Company |
| Nov 7, 2025 | 62R63 | CookDistrict 1 | 1 EACH | $16,248.61 | Dunnet Bay Construction Company |
| Nov 7, 2025 | 61L43 | CookDistrict 1 | 1 EACH | $16,800.00 | K-Five Construction Corporation |
| Sep 19, 2025 | 62B64 | CookDistrict 1 | 1 EACH | $20,269.00 | R. W. Dunteman Company |
| Sep 19, 2025 | 70F21 | McleanDistrict 5 | 4 EACH | $23,272.33 | Rowe Construction, a div of UCM, Inc. |
| Aug 1, 2025 | 62W57 | CookDistrict 1 | 1 EACH | $20,700.00 | Hecker and Company, Inc. |
| Aug 1, 2025 | 91653 | McleanDistrict 5 | 1 EACH | $24,511.71 | Rowe Construction, a div of UCM, Inc. |
| Jun 13, 2025 | 62N39 | Dupage, CookDistrict 1 | 4 EACH | $22,007.80 | Meade Inc. |
| Jun 13, 2025 | 62X42 | CookDistrict 1 | 2 EACH | $22,300.00 | Hecker and Company, Inc. |
| Apr 25, 2025 | 62N33 | DupageDistrict 1 | 1 EACH | $18,900.00 | John Burns Construction Company |
| Apr 25, 2025 | 70991 | ChampaignDistrict 5 | 1 EACH | $28,600.00 | Cross Construction, Inc. |
| Mar 7, 2025 | 62W60 | Cook, DupageDistrict 1 | 3 EACH | $17,723.73 | H & H Electric Co. |
| Mar 7, 2025 | 62W61 | VariousDistrict 1 | 1 EACH | $15,869.97 | H & H Electric Co. |
| Mar 7, 2025 | 61L09 | CookDistrict 1 | 1 EACH | $19,474.00 | Home Towne Electric, Inc. |
| Mar 7, 2025 | 61J84 | KaneDistrict 1 | 1 EACH | $15,148.00 | R. W. Dunteman Company |
| Jan 17, 2025 | 61J91 | KaneDistrict 1 | 1 EACH | $18,158.00 | Geneva Construction Company |
| Jan 17, 2025 | 61K94 | CookDistrict 1 | 2 EACH | $18,114.00 | R. W. Dunteman Company |