$86.09Avg low bid / SQ YD
$84.17Avg of all bids
—Avg engineer's estimate
67Jobs · 50,450.2 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 7 | 1,778 | $202.43 | $210.72 |
| 2025 | 10 | 2,326 | $171.31 | $183.52 |
| 2024 | 13 | 2,246.2 | $150.73 | $155.45 |
| 2023 | 6 | 1,861 | $149.91 | $150.22 |
| 2022 | 8 | 32,987 | $66.94 | $70.97 |
| 2021 | 7 | 6,395 | $72.54 | $73.50 |
| 2020 | 2 | 160 | $116.38 | $119.01 |
| 2019 | 8 | 888 | $108.69 | $135.73 |
| 2018 | 6 | 1,809 | $99.62 | $109.27 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 78990 | FranklinDistrict 9 | 130 SQ YD | $200.00 | Samron Midwest Contracting, Inc. |
| Jul 31, 2026 | 78520 | JeffersonDistrict 9 | 176 SQ YD | $163.75 | E. T. Simonds Construction Company |
| Jul 31, 2026 | 78935 | JeffersonDistrict 9 | 184 SQ YD | $186.63 | E. T. Simonds Construction Company |
| Jun 12, 2026 | 78A13 | UnionDistrict 9 | 692 SQ YD | $203.08 | E. T. Simonds Construction Company |
| Apr 24, 2026 | 78495 | JeffersonDistrict 9 | 291 SQ YD | $140.00 | Samron Midwest Contracting, Inc. |
| Jan 16, 2026 | 62K62 | CookDistrict 1 | 178 SQ YD | $310.07 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 78C03 | SalineDistrict 9 | 127 SQ YD | $270.08 | Sierra Bravo Contractors, LLC |
| Nov 7, 2025 | 62U41 | CookDistrict 1 | 89 SQ YD | $170.00 | Lorig Construction Company |
| Nov 7, 2025 | 78B23 | FranklinDistrict 9 | 374 SQ YD | $125.00 | Samron Midwest Contracting, Inc. |
| Sep 19, 2025 | 78793 | PulaskiDistrict 9 | 273 SQ YD | $171.82 | E. T. Simonds Construction Company |
| Jun 13, 2025 | 99752 | PerryDistrict 9 | 37 SQ YD | $215.00 | C-Hill Civil Contractors, Inc. |
| Jun 13, 2025 | 74648 | WayneDistrict 7 | 281 SQ YD | $164.41 | E. T. Simonds Construction Company |
| Jun 13, 2025 | 78399 | SalineDistrict 9 | 345 SQ YD | $163.00 | Samron Midwest Contracting, Inc. |
| Jun 13, 2025 | 78A15 | UnionDistrict 9 | 115 SQ YD | $357.92 | Sierra Bravo Contractors, LLC |
| Apr 25, 2025 | 64N98 | OgleDistrict 2 | 161 SQ YD | $108.35 | William Charles Construction Company, LLC |
| Apr 25, 2025 | 74A26 | RichlandDistrict 7 | 280 SQ YD | $171.13 | Howell Paving, Inc. |
| Mar 7, 2025 | 78844 | HardinDistrict 9 | 371 SQ YD | $196.15 | Sierra Bravo Contractors, LLC |
| Nov 8, 2024 | 78949 | PerryDistrict 9 | 116 SQ YD | $171.00 | Samron Midwest Contracting, Inc. |
| Sep 20, 2024 | 61K63 | CookDistrict 1 | 96 SQ YD | $100.00 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Sep 20, 2024 | 61K70 | CookDistrict 1 | 277 SQ YD | $119.00 | A Lamp Concrete Contractors, Inc. |
| Sep 20, 2024 | 62W88 | CookDistrict 1 | 324 SQ YD | $117.50 | D. Construction, Inc. |
| Aug 2, 2024 | 78911 | JeffersonDistrict 9 | 284 SQ YD | $159.00 | Samron Midwest Contracting, Inc. |
| Jun 14, 2024 | 66N52 | KankakeeDistrict 3 | 52 SQ YD | $170.00 | Tobey's Construction & Cartage, Inc. |
| Jun 14, 2024 | 78718 | JohnsonDistrict 9 | 152 SQ YD | $200.00 | Samron Midwest Contracting, Inc. |
| Jun 14, 2024 | 62N40 | Dupage, CookDistrict 1 | 336 SQ YD | $137.00 | John Burns Construction Company |
| Apr 26, 2024 | 97807 | MadisonDistrict 8 | 18 SQ YD | $210.00 | DMS Contracting, Inc. |
| Apr 26, 2024 | 78999 | White, HamiltonDistrict 9 | 172 SQ YD | $200.00 | Samron Midwest Contracting, Inc. |
| Mar 8, 2024 | 78948 | JohnsonDistrict 9 | 191 SQ YD | $149.72 | Sierra Bravo Contractors, LLC |
| Jan 19, 2024 | 78830 | HamiltonDistrict 9 | 200 SQ YD | $175.00 | Samron Midwest Contracting, Inc. |
| Jan 19, 2024 | 76R91 | MadisonDistrict 8 | 28.2 SQ YD | $208.70 | Stutz Excavating, Inc. |
| Nov 17, 2023 | 78199 | PerryDistrict 9 | 170 SQ YD | $142.28 | E. T. Simonds Construction Company |
| Jun 16, 2023 | 78915 | FranklinDistrict 9 | 741 SQ YD | $116.79 | Sierra Bravo Contractors, LLC |
| Jun 16, 2023 | 62G41 | KaneDistrict 1 | 41 SQ YD | $161.09 | Martam Construction Incorporated and Dunnet Bay Construction Company JV |
| Jun 16, 2023 | 78790 | JacksonDistrict 9 | 555 SQ YD | $213.71 | E. T. Simonds Construction Company |
| Apr 28, 2023 | 61H93 | CookDistrict 1 | 59 SQ YD | $190.00 | Alliance Contractors, Inc. |
| Jan 20, 2023 | 78682 | WhiteDistrict 9 | 295 SQ YD | $107.92 | E. T. Simonds Construction Company |
| Nov 18, 2022 | 78893 | FranklinDistrict 9 | 546 SQ YD | $133.30 | Sierra Bravo Contractors, LLC |
| Nov 18, 2022 | 68F38 | Peoria, TazewellDistrict 4 | 1,410 SQ YD | $151.33 | ICC Group Inc. |
| Sep 23, 2022 | 78834 | WhiteDistrict 9 | 509 SQ YD | $125.00 | Samron Midwest Contracting, Inc. |
| Apr 29, 2022 | 62P45 | CookDistrict 1 | 840 SQ YD | $12.00 | Judlau Contracting, Inc. |
| Apr 29, 2022 | 74A07 | ClayDistrict 7 | 717 SQ YD | $112.69 | Howell Paving, Inc. |
| Mar 11, 2022 | 62M47 | Cook, LakeDistrict 1 | 24 SQ YD | $225.00 | Arrow Road Construction Co. |
| Jan 21, 2022 | 61G73 | Will, CookDistrict 1 | 28,570 SQ YD | $60.00 | D. Construction, Inc. |
| Jan 21, 2022 | 74860 | LawrenceDistrict 7 | 371 SQ YD | $129.00 | Kieffer Bros. Construction Co., Inc. |
| Nov 5, 2021 | 74320 | WabashDistrict 7 | 1,668 SQ YD | $72.81 | Sierra Bravo Contractors, LLC |
| Nov 5, 2021 | 78829 | MassacDistrict 9 | 232 SQ YD | $96.00 | Samron Midwest Contracting, Inc. |
| Apr 23, 2021 | 78622 | HamiltonDistrict 9 | 146 SQ YD | $99.94 | Sierra Bravo Contractors, LLC |
| Mar 5, 2021 | 78336 | FranklinDistrict 9 | 160 SQ YD | $77.87 | Sierra Bravo Contractors, LLC |
| Mar 5, 2021 | 78501 | SalineDistrict 9 | 507 SQ YD | $95.00 | Samron Midwest Contracting, Inc. |
| Mar 5, 2021 | 61G60 | MchenryDistrict 1 | 3,566 SQ YD | $64.96 | Martam Construction Incorporated |
| Jan 15, 2021 | 78805 | HamiltonDistrict 9 | 116 SQ YD | $115.00 | Samron Midwest Contracting, Inc. |
| Jul 31, 2020 | 78731 | JeffersonDistrict 9 | 34 SQ YD | $216.00 | Brown Electric, Inc. |
| Apr 24, 2020 | 95861 | MaconDistrict 7 | 126 SQ YD | $89.50 | Kinney Contractors, Inc. |
| Nov 8, 2019 | 61F97 | CookDistrict 1 | 206 SQ YD | $114.90 | Landmark Contractors, Inc. |
| Nov 8, 2019 | 78675 | HamiltonDistrict 9 | 188 SQ YD | $114.19 | E. T. Simonds Construction Company |
| Jul 12, 2019 | 78652 | HardinDistrict 9 | 80 SQ YD | $127.93 | Sierra Bravo Contractors, LLC |
| Jul 12, 2019 | 78676 | PerryDistrict 9 | 107 SQ YD | $100.00 | Sierra Bravo Contractors, LLC |
| Jun 14, 2019 | 78635 | JacksonDistrict 9 | 120 SQ YD | $98.42 | Sierra Bravo Contractors, LLC |
| Jun 14, 2019 | 76M23 | MadisonDistrict 8 | 4 SQ YD | $206.25 | Stutz Excavating, Inc. |
| Mar 8, 2019 | 68B78 | WarrenDistrict 4 | 178 SQ YD | $94.45 | Gunther Construction, a div of UCM, Inc. |
| Mar 8, 2019 | 78637 | WilliamsonDistrict 9 | 5 SQ YD | $200.00 | Samron Midwest Contracting, Inc. |
| Nov 9, 2018 | 74619 | LawrenceDistrict 7 | 149 SQ YD | $185.00 | Allendale Gravel Co., Inc. |
| Jun 15, 2018 | 78326 | JeffersonDistrict 9 | 244 SQ YD | $82.29 | E. T. Simonds Construction Company |
| Jun 15, 2018 | 78390 | WhiteDistrict 9 | 262 SQ YD | $101.56 | E. T. Simonds Construction Company |
| Mar 9, 2018 | 78264 | WhiteDistrict 9 | 449 SQ YD | $91.59 | E. T. Simonds Construction Company |
| Mar 9, 2018 | 78628 | WilliamsonDistrict 9 | 471 SQ YD | $90.75 | Sierra Bravo Contractors, LLC |
| Jan 19, 2018 | 78470 | HamiltonDistrict 9 | 234 SQ YD | $94.41 | Kieffer Bros. Construction Co., Inc. |