Bid tab 78628

Let Mar 9, 2018 · District 9 · Williamson

‹ Mar 2018 results

130CLV-1

Let date
Friday, March 9, 2018
Contract
78628 · job page
District
District 9
County
Williamson
Highway
Limits
Culvert replacement across six lanes of traffic on IL 148, 1.1 miles north of IL 13 near the City of Energy (SN 100-7042).
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Sierra Bravo Contractors, LLC Low bidder $179,791
2 Samron Midwest Contracting, Inc. $196,168 +9.1%
3 E. T. Simonds Construction Company $208,420 +15.9%
4 Scanlon Excavating & Concrete, Inc. $350,177 +94.8%

Bid tab: unit prices 16 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Sierra Bravo Co…#2 Samron Midwest …#3 E. T. Simonds C…#4 Scanlon Excavat…
1X7015005 CHANGEABLE MESSAGE SN74CAL DA $112.31 $70.00 $50.00 $75.00
220200100 EARTH EXCAVATION801CU YD $11.79 $21.00 $17.38 $36.00
320700220 POROUS GRAN EMBANK752CU YD $39.99 $55.00 $50.41 $55.00
442000060 WELDED WIRE REINF471SQ YD $11.82 $8.00 $8.73 $18.00
542000500 PCC PVT 10471SQ YD $90.75 $90.00 $92.93 $150.00
644000100 PAVEMENT REM471SQ YD $13.99 $18.00 $20.51 $35.00
748101620 AGGREGATE SHLDS B 1021SQ YD $73.87 $50.00 $107.74 $100.00
850105220 PIPE CULVERT REMOV194FOOT $31.98 $19.00 $53.16 $95.00
950800105 REINFORCEMENT BARS363POUND $3.30 $4.00 $4.05 $10.00
1054002020 EXPAN BOLTS 3/430EACH $32.05 $20.00 $55.52 $25.00
11542A1105 P CUL CL A 2 60194FOOT $249.19 $240.00 $224.95 $525.00
1254248510 CONCRETE COLLAR11.8CU YD $386.13 $1,000.00 $1,719.75 $650.00
1367100100 MOBILIZATION1L SUM $8,561.48 $10,000.00 $10,051.53 $21,000.00
1470101830 TRAF CONT-PROT BLR 211L SUM $3,855.83 $1,000.00 $3,872.55 $20,000.00
1578001100 PT PVT MK LTRS & SYMB27SQ FT $17.38 $9.00 $16.87 $20.00
1678001110 PAINT PVT MK LINE 4356FOOT $3.83 $5.00 $3.72 $8.00