3CR-1;4CR-1
- Let date
- Friday, March 7, 2025
- Contract
- 78844 · job page
- District
- District 9
- County
- Hardin
- Highway
- Limits
- Box culvert replacement on IL 34 over Tributary of Pinhook Creek, about 0.7 miles south of the Pope County line and on IL 34 over a Ditch located 1.5 miles north of IL 146 and approximately 0.5 miles south of Eichorn.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $897,358 | ||
| 2 | Samron Midwest Contracting, Inc. | $909,688 | +1.4% | |
| 3 | E. T. Simonds Construction Company | $1,262,484 | +40.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Samron Midwest … | #3 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X5810103 | MEMB WTRPRF SYS B STR | 225 | SQ YD | $40.00 | $27.00 | $98.11 | |
| 2 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $5,250.00 | $8,660.84 | $12,959.17 | |
| 3 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $15,712.78 | $22,000.00 | $16,461.01 | |
| 4 | Z0054517 | ROCK FILL - FOUNDATN | 129 | TON | $44.34 | $20.00 | $65.04 | |
| 5 | 20100110 | TREE REMOV 6-15 | 51 | UNIT | $132.54 | $90.00 | $114.60 | |
| 6 | 20100500 | TREE REMOV ACRES | 0.1 | ACRE | $33,798.70 | $1,600.00 | $92,546.80 | |
| 7 | 20200100 | EARTH EXCAVATION | 1,685 | CU YD | $15.52 | $30.00 | $52.39 | |
| 8 | 20200200 | ROCK EXCAVATION | 19 | CU YD | $198.73 | $300.00 | $1,094.46 | |
| 9 | 20700220 | POROUS GRAN EMBANK | 915 | CU YD | $61.16 | $36.00 | $85.15 | |
| 10 | 25000210 | SEEDING CL 2A | 0.45 | ACRE | $8,925.00 | $5,700.00 | $9,350.00 | |
| 11 | 25000350 | SEEDING CL 7 | 0.45 | ACRE | $420.00 | $410.00 | $440.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 41 | POUND | $4.20 | $2.00 | $4.40 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 41 | POUND | $4.20 | $2.00 | $4.40 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 41 | POUND | $4.20 | $2.00 | $4.40 | |
| 15 | 25000700 | AGR GROUND LIMESTONE | 0.9 | TON | $299.26 | $1,000.00 | $313.50 | |
| 16 | 25100115 | MULCH METHOD 2 | 0.45 | ACRE | $8,925.00 | $6,000.00 | $9,350.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 45 | POUND | $6.10 | $2.00 | $12.39 | |
| 18 | 28000400 | PERIMETER EROS BAR | 596 | FOOT | $5.93 | $7.00 | $12.29 | |
| 19 | 28100107 | STONE RIPRAP CL A4 | 28 | SQ YD | $83.07 | $95.00 | $83.87 | |
| 20 | 28100109 | STONE RIPRAP CL A5 | 150 | SQ YD | $87.77 | $60.00 | $80.46 | |
| 21 | 28200200 | FILTER FABRIC | 178 | SQ YD | $5.52 | $4.00 | $3.68 | |
| 22 | 28300400 | AGGREGATE DITCH | 70 | TON | $68.07 | $50.00 | $74.40 | |
| 23 | 42000060 | WELDED WIRE REINF | 371 | SQ YD | $11.79 | $9.00 | $21.55 | |
| 24 | 42000500 | PCC PVT 10 | 371 | SQ YD | $196.15 | $135.00 | $232.91 | |
| 25 | 44000100 | PAVEMENT REM | 371 | SQ YD | $30.07 | $10.00 | $53.10 | |
| 26 | 44004250 | PAVED SHLD REMOVAL | 60 | SQ YD | $25.78 | $6.00 | $82.50 | |
| 27 | 48102100 | AGG WEDGE SHLD TYPE B | 4 | TON | $84.45 | $72.00 | $310.15 | |
| 28 | 48300500 | PCC SHOULDERS 10 | 124 | SQ YD | $152.20 | $180.00 | $279.38 | |
| 29 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $15,960.13 | $30,000.00 | $22,045.99 | |
| 30 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $15,960.13 | $20,000.00 | $13,308.61 | |
| 31 | 50200450 | REM/DISP UNS MATL-STR | 108 | CU YD | $39.66 | $20.00 | $45.55 | |
| 32 | 50800205 | REINF BARS, EPOXY CTD | 12,560 | POUND | $2.57 | $2.00 | $2.00 | |
| 33 | 52200020 | TEMP SOIL RETEN SYSTM | 333 | SQ FT | $147.91 | $0.0100 | $270.00 | |
| 34 | 54001002 | BOX CUL END SEC C2 | 2 | EACH | $49,050.08 | $55,000.00 | $46,873.77 | |
| 35 | 54003000 | CONC BOX CUL | 69.3 | CU YD | $1,770.87 | $2,000.00 | $2,160.44 | |
| 36 | 54010604 | PCBC 6X4 | 74 | FOOT | $682.06 | $1,200.00 | $1,075.33 | |
| 37 | 54011206 | PCBC 12X6 | 64 | FOOT | $1,348.01 | $1,900.00 | $1,837.89 | |
| 38 | 59100100 | GEOCOMPOSITE WALL DR | 225 | SQ YD | $15.08 | $9.00 | $58.94 | |
| 39 | 66600105 | FUR ERECT ROW MARKERS | 16 | EACH | $196.35 | $600.00 | $205.70 | |
| 40 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,749.65 | $2,000.00 | $2,200.00 | |
| 41 | 67100100 | MOBILIZATION | 1 | L SUM | $53,839.52 | $54,000.00 | $105,156.13 | |
| 42 | 70100100 | TRAF CONT-PROT 701316 | 1 | EACH | $20,790.00 | $16,000.00 | $16,320.00 | |
| 43 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $735.00 | $1,750.00 | $10,083.35 | |
| 44 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $620.87 | $0.0100 | $0.0100 | |
| 45 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $15,750.00 | $8,000.00 | $24,000.00 | |
| 46 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $945.00 | $1,200.00 | $990.00 | |
| 47 | 70107025 | CHANGEABLE MESSAGE SN | 84 | CAL DA | $99.34 | $135.00 | $86.75 | |
| 48 | 78001110 | PAINT PVT MK LINE 4 | 1,341 | FOOT | $4.24 | $5.00 | $4.44 | |
| 49 | 78300201 | PVT MKG REM GRINDING | 427 | SQ FT | $16.80 | $11.00 | $17.60 | |
| 50 | 86200300 | UNINTER POWER SUP EXT | 1 | EACH | $0.0100 | $0.0100 | $0.0100 |