13B-3
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,448,907 | ||
| 2 | E. T. Simonds Construction Company | $1,499,274 | +3.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 2,239 | SQ YD | $9.00 | $8.62 | |
| 2 | X5810103 | MEMB WTRPRF SYS B STR | 294 | SQ YD | $22.00 | $36.11 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $37,000.00 | $12,016.18 | |
| 4 | Z0023500 | FILL EXIST CULVERTS | 6.3 | CU YD | $500.00 | $1,084.25 | |
| 5 | Z0054517 | ROCK FILL - FOUNDATN | 420 | TON | $60.00 | $50.24 | |
| 6 | 20100500 | TREE REMOV ACRES | 0.05 | ACRE | $16,000.00 | $93,380.40 | |
| 7 | 20200100 | EARTH EXCAVATION | 1,814 | CU YD | $21.00 | $23.52 | |
| 8 | 20200500 | EARTH EXC WID | 81 | CU YD | $65.00 | $78.03 | |
| 9 | 20700220 | POROUS GRAN EMBANK | 323 | CU YD | $74.00 | $96.06 | |
| 10 | 25000210 | SEEDING CL 2A | 1.33 | ACRE | $3,900.00 | $3,822.50 | |
| 11 | 25000350 | SEEDING CL 7 | 1.33 | ACRE | $940.00 | $935.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 120 | POUND | $2.00 | $1.76 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 120 | POUND | $2.00 | $1.76 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 120 | POUND | $2.00 | $1.76 | |
| 15 | 25000700 | AGR GROUND LIMESTONE | 2.66 | TON | $387.00 | $385.00 | |
| 16 | 25100115 | MULCH METHOD 2 | 1.33 | ACRE | $2,800.00 | $2,722.50 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 133 | POUND | $2.00 | $5.34 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 27 | FOOT | $14.00 | $22.91 | |
| 19 | 28000400 | PERIMETER EROS BAR | 570 | FOOT | $4.00 | $8.01 | |
| 20 | 28100107 | STONE RIPRAP CL A4 | 601 | SQ YD | $60.00 | $51.23 | |
| 21 | 28200200 | FILTER FABRIC | 601 | SQ YD | $3.00 | $4.18 | |
| 22 | 35100100 | AGG BASE CSE A | 393 | TON | $26.00 | $66.40 | |
| 23 | 35600716 | HMA BC WID 10 | 446 | SQ YD | $125.00 | $80.72 | |
| 24 | 40600275 | BIT MATLS PR CT | 2,500 | POUND | $1.68 | $0.0100 | |
| 25 | 40600290 | BIT MATLS TACK CT | 1,908 | POUND | $1.78 | $0.0100 | |
| 26 | 40600990 | TEMPORARY RAMP | 42 | SQ YD | $34.00 | $70.22 | |
| 27 | 40604062 | HMA SC IL-9.5 D N70 | 113 | TON | $237.00 | $265.12 | |
| 28 | 42000060 | WELDED WIRE REINF | 284 | SQ YD | $8.00 | $14.71 | |
| 29 | 42000500 | PCC PVT 10 | 284 | SQ YD | $159.00 | $168.64 | |
| 30 | 44000100 | PAVEMENT REM | 246 | SQ YD | $30.00 | $32.29 | |
| 31 | 44004250 | PAVED SHLD REMOVAL | 394 | SQ YD | $10.00 | $31.04 | |
| 32 | 48203029 | HMA SHOULDERS 8 | 228 | SQ YD | $245.00 | $109.06 | |
| 33 | 48203037 | HMA SHOULDERS 10 | 663 | SQ YD | $126.00 | $99.31 | |
| 34 | 48300500 | PCC SHOULDERS 10 | 172 | SQ YD | $81.00 | $143.41 | |
| 35 | 50100100 | REM EXIST STRUCT | 1 | EACH | $40,853.13 | $40,578.93 | |
| 36 | 50200450 | REM/DISP UNS MATL-STR | 244 | CU YD | $24.00 | $45.56 | |
| 37 | 50800205 | REINF BARS, EPOXY CTD | 27,790 | POUND | $2.00 | $1.95 | |
| 38 | 50800515 | BAR SPLICERS | 198 | EACH | $32.00 | $30.21 | |
| 39 | 50900207 | STEEL RAILING TY CO-10 | 78 | FOOT | $264.00 | $343.53 | |
| 40 | 51500100 | NAME PLATES | 1 | EACH | $530.00 | $495.00 | |
| 41 | 52200020 | TEMP SOIL RETEN SYSTM | 589 | SQ FT | $230.00 | $127.43 | |
| 42 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $21,000.00 | $22,520.65 | |
| 43 | 54003000 | CONC BOX CUL | 193.4 | CU YD | $1,200.00 | $1,610.64 | |
| 44 | 54011204 | PCBC 12X4 | 54 | FOOT | $1,690.00 | $1,741.29 | |
| 45 | 59100100 | GEOCOMPOSITE WALL DR | 294 | SQ YD | $14.00 | $30.76 | |
| 46 | 63000001 | SPBGR TY A 6FT POSTS | 175 | FOOT | $48.00 | $50.44 | |
| 47 | 63100119 | TRAF BAR TERM T14 | 4 | EACH | $6,000.00 | $7,469.00 | |
| 48 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $4,300.00 | $5,368.00 | |
| 49 | 63200310 | GUARDRAIL REMOV | 689 | FOOT | $9.00 | $13.78 | |
| 50 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,000.00 | $2,000.00 | |
| 51 | 67100100 | MOBILIZATION | 1 | L SUM | $85,053.00 | $104,166.55 | |
| 52 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $15,000.00 | $15,026.50 | |
| 53 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $10,000.00 | $0.0100 | |
| 54 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $3,000.00 | $7,456.09 | |
| 55 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $0.0100 | $0.0100 | |
| 56 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $18,899.90 | $35,530.00 | |
| 57 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $1,200.00 | $876.70 | |
| 58 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $80.00 | $88.98 | |
| 59 | 70300100 | SHORT TERM PAVT MKING | 108 | FOOT | $3.00 | $1.16 | |
| 60 | 70300150 | SHRT TRM PAVT MK REM | 36 | SQ FT | $41.00 | $18.56 | |
| 61 | 70400100 | TEMP CONC BARRIER | 687.5 | FOOT | $35.00 | $32.36 | |
| 62 | 70400125 | PIN TEMP CONC BARRIER | 74 | EACH | $28.00 | $43.30 | |
| 63 | 70400200 | REL TEMP CONC BARRIER | 687.5 | FOOT | $3.00 | $2.59 | |
| 64 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $10,000.00 | $8,257.40 | |
| 65 | 70600332 | IMP ATTN REL FRN TL3 | 2 | EACH | $1,200.00 | $5,522.10 | |
| 66 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $55.00 | |
| 67 | 78001110 | PAINT PVT MK LINE 4 | 3,431 | FOOT | $2.00 | $1.40 | |
| 68 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $12.00 | $11.00 | |
| 69 | 78300200 | RAISED REF PVT MK REM | 10 | EACH | $44.00 | $53.87 | |
| 70 | 78300201 | PVT MKG REM GRINDING | 750 | SQ FT | $7.00 | $10.91 | |
| 71 | 86200300 | UNINTER POWER SUP EXT | 1 | EACH | $0.0100 | $3,080.00 |