217Let jobs
$1,809,450,852Total low bids
$1,668,447,515Total estimates
+8.5%Low bids vs estimates
Aug 2023 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 28, 2023 | 6451-43-001MMC - 645143001 | De Witt Yoakum |
HOT-MIX COLD-LAIDUS 183 · | $292,500 | $292,500 | BRAUNTEX MATERIALS, INC. | 0.0% | 1 |
| Aug 3, 2023 | 0047-18-089F 2B23(048) | Grayson Paris |
WIDEN ROAD - ADD LANESUS 75 · | $172,021,665 | $196,535,605 | SEMA CONSTRUCTION, INC. | +14.3% | 4 |
| Aug 3, 2023 | 0188-09-051F 2022(510) | Fort Bend Houston |
WIDEN ROAD - ADD LANESFM 723 · | $125,496,640 | $144,686,970 | ZACHRY CONSTRUCTION CORPORATION | +15.3% | 5 |
| Aug 3, 2023 | 0270-01-051F 2B23(121) | De Witt Yoakum |
WIDEN ROAD - ADD LANESSH 72 · | $63,364,496 | $74,026,222 | HUNTER INDUSTRIES, LTD. | +16.8% | 1 |
| Aug 3, 2023 | 0191-02-066F 2023(722) | Cherokee Tyler |
INTERCHANGE IMPROVEMENT (NEW OR UPDATE)US 69 · | $66,240,110 | $66,711,336 | EAST TEXAS BRIDGE, INC. | +0.7% | 3 |
| Aug 3, 2023 | 0047-06-158STP 2024(041)MM | Collin Dallas |
HIGHWAY IMPROVEMENTUS 75 · | $54,383,909 | $58,488,663 | WEBBER, LLC | +7.5% | 2 |
| Aug 3, 2023 | 0495-02-064BR 2B23(276) | Van Zandt Tyler |
BRIDGE REPLACEMENTIH 20 · | $31,709,757 | $39,144,960 | INDUS ROAD & BRIDGE, INC. | +23.4% | 2 |
| Aug 3, 2023 | 0312-04-022C 312-4-22 | Wise Fort Worth |
RECONSTRUCT EXISTING ROADWAYFM 730 · | $42,191,646 | $38,322,905 | SEMA CONSTRUCTION, INC. | -9.2% | 4 |
| Aug 3, 2023 | 6450-13-001RMC - 645013001 | Bell Waco |
TOTAL MAINTENANCEIH 35 · | $38,574,454 | $37,852,917 | ROY JORGENSEN ASSOCIATES, INC. | -1.9% | 2 |
| Aug 3, 2023 | 1685-01-090CM 2021(643) | Harris Houston |
INTERCHANGE IMPROVEMENTFM 1960 · | $24,735,709 | $27,298,741 | SER CONSTRUCTION PARTNERS, LLC | +10.4% | 4 |
| Aug 3, 2023 | 0067-07-094BR 2B23(042) | Lubbock Lubbock |
BRIDGE REPLACEMENTIH 27 · | $16,947,086 | $24,330,102 | WEBBER, LLC | +43.6% | 2 |
| Aug 3, 2023 | 0092-02-135F 2B23(093) | Dallas Dallas |
FDCR, FLEX PAV REP, & BRIDGE SCOUR REPIH 45 · | $8,541,987 | $16,982,607 | RAGLE CONSTRUCTION, INC. | +98.8% | 2 |
| Aug 3, 2023 | 0108-09-052F 2B23(049) | Hopkins Paris |
REHABILITATE EXISTING ROADWAYSH 19 · | $15,519,702 | $16,786,586 | HIGHWAY 19 CONSTRUCTION LLC | +8.2% | 2 |
| Aug 3, 2023 | 1057-03-045STP 2B23(055) | Cameron Pharr |
REHABILITATE EXISTING ROADWAYFM 510 · | $14,086,164 | $15,675,731 | FOREMOST PAVING, INC. | +11.3% | 4 |
| Aug 3, 2023 | 0844-03-013BR 2B23(021) | Collingsworth Childress |
BRIDGE REPLACEMENTFM 1547 · | $9,306,195 | $10,872,131 | HODGES AND SON CONSTRUCTION COMPANY, INC. | +16.8% | 5 |
| Aug 3, 2023 | 0559-02-037STP 2B23(064)HES | Henderson Tyler |
HAZARD ELIMINATION & SAFETYFM 315 · | $11,302,404 | $9,287,827 | BIG CREEK CONSTRUCTION, LTD. | -17.8% | 2 |
| Aug 3, 2023 | 0535-06-049F 2B23(083) | Fayette Yoakum |
CONSTRUCT REST AREAIH 10 · | $10,245,886 | $9,282,087 | HUNTER INDUSTRIES, LTD. | -9.4% | 4 |
| Aug 3, 2023 | 1191-05-009F 2B23(028) | Robertson Bryan |
PREVENTIVE MAINTENANCEFM 937 · | $11,938,892 | $9,087,363 | BIG CREEK CONSTRUCTION, LTD. | -23.9% | 3 |
| Aug 3, 2023 | 0972-03-021F 2B23(134) | Jones Abilene |
CONSTRUCT NEW ROADFM 1082 · | $8,058,458 | $8,867,739 | GILVIN-TERRILL, LTD. | +10.0% | 2 |
| Aug 3, 2023 | 1597-04-012C 1597-4-12 | Comanche Brownwood |
WIDEN ROAD - ADD SHOULDERSFM 1702 · | $7,845,148 | $8,679,973 | JAY MILLS CONTRACTING, INCORPORATED | +10.6% | 3 |
| Aug 3, 2023 | 0932-02-044F 2B23(154) | Jefferson Beaumont |
ADD SHOULDERS AND OVERLAYFM 365 · | $7,617,748 | $7,997,541 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | +5.0% | 2 |
| Aug 3, 2023 | 6444-58-001RMC - 644458001 | Van Zandt Tyler |
MILL AND INLAYFM 16 · | $5,012,428 | $7,319,995 | EAST TEXAS BRIDGE, INC. | +46.0% | 3 |
| Aug 3, 2023 | 0483-01-052F 2B23(147) | La Salle Laredo |
REHABILITATE EXISTING ROADWAYSH 97 · | $6,853,144 | $7,207,235 | HUNTER INDUSTRIES, LTD. | +5.2% | 3 |
| Aug 3, 2023 | 1158-01-011F 2B23(123) | Culberson El Paso |
PREVENTIVE MAINTENANCEFM 2185 · | $6,485,395 | $6,981,729 | DAN WILLIAMS COMPANY | +7.7% | 3 |
| Aug 3, 2023 | 2800-01-010F 2B23(054) | Red River Paris |
REHABILITATE EXISTING ROADWAYFM 1487 · | $8,263,651 | $6,756,222 | A. K. GILLIS & SONS, LLC | -18.2% | 5 |
| Aug 3, 2023 | 0683-02-074F 2023(389) | Travis Austin |
INSTALL ADVANCED TRAFFIC MANAGEMENT SYSTEMRM 620 · | $6,736,713 | $6,473,033 | SICE, INC. | -3.9% | 3 |
| Aug 3, 2023 | 0275-04-069STP 2B23(012)TAPS | Carson Amarillo |
TRANSPORTATION NON-ROADWAYIH 40 · | $5,701,286 | $6,318,690 | J. LEE MILLIGAN, INC. | +10.8% | 4 |
| Aug 3, 2023 | 0720-01-044STP 2B23(029)HES | Grimes Bryan |
WIDEN ROAD - ADD SHOULDERSFM 149 · | $4,928,888 | $5,572,269 | LARRY YOUNG PAVING, INC. | +13.1% | 4 |
| Aug 3, 2023 | 1129-01-028F 2022(862) | Burleson Bryan |
REHABILITATE EXISTING ROADFM 975 · | $4,752,058 | $5,263,760 | TEXAS MATERIALS GROUP, INC. | +10.8% | 3 |
| Aug 3, 2023 | 0912-72-662STP 2B23(160)HES | Harris Houston |
HAZARD ELIMINATION & SAFETYVA · | $2,107,066 | $4,864,313 | RAGLE CONSTRUCTION, INC. | +130.9% | 1 |
| Aug 3, 2023 | 0902-48-894BR 1502(322) | Tarrant Fort Worth |
BRIDGE REPLACEMENTCS · | $6,465,444 | $4,807,165 | HARPER BROTHERS CONSTRUCTION LLC | -25.6% | 4 |
| Aug 3, 2023 | 2979-01-013STP 2B23(113)HES | Denton Dallas |
HIGHWAY IMPROVEMENTFM 2931 · | $4,619,386 | $4,665,614 | JAGOE-PUBLIC COMPANY | +1.0% | 4 |
| Aug 3, 2023 | 0109-09-068F 2B23(022) | Walker Bryan |
PROFILE MARKINGSSH 19 · | $4,971,039 | $4,204,818 | D. I. J. CONSTRUCTION, INC. | -15.4% | 5 |
| Aug 3, 2023 | 0009-04-074STP 2B23(089)HES | Rockwall Dallas |
HIGHWAY IMPROVEMENTSH 66 · | $2,727,369 | $4,078,127 | FNH CONSTRUCTION, LLC | +49.5% | 2 |
| Aug 3, 2023 | 0092-14-104F 2B23(095) | Dallas Dallas |
HAZARD ELIMINATION & SAFETYIH 45 · | $3,138,191 | $3,534,464 | ED BELL CONSTRUCTION COMPANY | +12.6% | 4 |
| Aug 3, 2023 | 1895-02-013BR 2B23(016) | Harrison Atlanta |
REPLACE BRIDGE AND APPROACHESFM 726 · | $2,423,931 | $3,496,301 | THK CONSTRUCTION LLC | +44.2% | 4 |
| Aug 3, 2023 | 0104-11-008C 104-11-8 | Presidio El Paso |
REHABILITATE EXISTING ROADWAYBU 67-A · | $2,882,824 | $3,445,494 | DAN WILLIAMS COMPANY | +19.5% | 1 |
| Aug 3, 2023 | 0266-06-050F 2B23(080) | Wharton Yoakum |
CONSTRUCT PEDESTRIAN INFRASTRUCTURESH 71 · | $3,361,294 | $3,057,575 | TI-ZACK CONCRETE, INC. | -9.0% | 3 |
| Aug 3, 2023 | 0910-16-162STP 2023(201)TAPS | Smith Tyler |
CONSTRUCT PEDESTRIAN INFRASTRUCTUREVA · | $3,104,945 | $2,988,319 | THK CONSTRUCTION LLC | -3.8% | 5 |
| Aug 3, 2023 | 0279-02-048STP 2B23(050)HES | Fannin Paris |
HAZARD ELIMINATION & SAFETYSH 78 · | $2,458,605 | $2,680,198 | HIGHWAY 19 CONSTRUCTION LLC | +9.0% | 2 |
| Aug 3, 2023 | 0918-46-327STP 2023(854)HESG | Denton Dallas |
TRAFFIC SIGNAL IMPROVEMENTSCS · | $2,354,414 | $2,578,292 | DURABLE SPECIALTIES, INC. | +9.5% | 1 |
| Aug 3, 2023 | 1095-03-017STP 2B23(261)HES | Karnes Corpus Christi |
TRAFFIC SIGNAL IMPROVEMENTSFM 743 · | $2,598,478 | $2,555,559 | CK NEWBERRY, LLC | -1.7% | 4 |
| Aug 3, 2023 | 0363-01-147F 2B23(136) | Tarrant Fort Worth |
RESURFACE ROADWAYSH 26 · | $2,537,372 | $2,429,785 | AUSTIN BRIDGE & ROAD SERVICES, LP | -4.2% | 5 |
| Aug 3, 2023 | 0909-00-089F 2B23(177) | McLennan Waco |
MAINTENANCE & OPERATIONS PROJECTVA · | $3,582,439 | $2,409,826 | D. I. J. CONSTRUCTION, INC. | -32.7% | 8 |
| Aug 3, 2023 | 0094-05-071STP 2B23(143)HES | Tarrant Fort Worth |
INTERSECTION IMPROVEMENTSH 183 · | $1,675,041 | $2,255,934 | FNH CONSTRUCTION, LLC | +34.7% | 3 |
| Aug 3, 2023 | 0013-05-065STP 2B23(131)HES | Montague Wichita Falls |
HAZARD ELIMINATION & SAFETYUS 81 · | $2,580,022 | $2,243,729 | HJC FARMS, INC. | -13.0% | 4 |
| Aug 3, 2023 | 0535-04-031C 535-4-31 | Gonzales Yoakum |
UPGRADE DYNAMIC MESSAGE SIGN BOARDSIH 10 · | $2,189,204 | $2,182,974 | TRAF-TEX, INC. | -0.3% | 2 |
| Aug 3, 2023 | 6408-77-001RMC - 640877001 | Hays Austin |
METAL BEAM GUARD FENCE REPAIRFM 2001 · | $2,625,873 | $2,162,563 | BK FIELD OPERATIONS LLC | -17.6% | 3 |
| Aug 3, 2023 | 0922-00-077STP 2024(102)HES | Val Verde Laredo |
HAZARD ELIMINATION & SAFETYVA · | $3,186,040 | $2,156,160 | HIGHWAY BARRICADES AND SERVICES, LLC | -32.3% | 2 |
| Aug 3, 2023 | 1402-03-012F 2023(339) | Montgomery Houston |
SURFACING/ROADWAY RESTORATIONFM 1375 · | $2,681,961 | $2,012,093 | TEXAS MATERIALS GROUP, INC. | -25.0% | 7 |
| Aug 3, 2023 | 0912-72-641STP 2B23(157)HESG | Harris Houston |
HAZARD ELIMINATION & SAFETYCS · | $1,509,547 | $1,979,986 | MAIN LANE INDUSTRIES LTD. | +31.2% | 1 |
| Aug 3, 2023 | 6446-88-001MMC - 644688001 | Hutchinson Amarillo |
DE-ICING SALTSH 207 · | $2,334,572 | $1,979,895 | NSG LOGISTICS, LLC | -15.2% | 3 |
| Aug 3, 2023 | 6445-74-001RMC - 644574001 | Wichita Wichita Falls |
FULL DEPTH CONCRETE REPAIRUS 82 · | $1,472,330 | $1,942,000 | O. TREVINO CONSTRUCTION, LLC | +31.9% | 1 |
| Aug 3, 2023 | 6443-86-001MMC - 644386001 | Hill Waco |
HOT MIXSH 81 · | $1,938,000 | $1,868,470 | TEXAS MATERIALS GROUP, INC. | -3.6% | 3 |
| Aug 3, 2023 | 0172-05-124STP 2B23(097)HES | Ellis Dallas |
HAZARD ELIMINATION & SAFETYUS 287 · | $1,917,299 | $1,859,514 | ED BELL CONSTRUCTION COMPANY | -3.0% | 2 |
| Aug 3, 2023 | 6446-84-001MMC - 644684001 | Randall Amarillo |
FLEXIBLE BASEIH 27 · | $2,007,842 | $1,816,522 | VOLCANIC STONE CO. | -9.5% | 3 |
| Aug 3, 2023 | 0922-00-067C 922-00-67 | Webb Laredo |
INSTALLATION OF ITSVA · | $1,200,954 | $1,775,792 | THE LEVY COMPANY, INC. | +47.9% | 2 |
| Aug 3, 2023 | 6443-82-001MMC - 644382001 | McLennan Waco |
HOT MIXUS 84 · | $1,901,250 | $1,771,123 | TEXAS MATERIALS GROUP, INC. | -6.8% | 3 |
| Aug 3, 2023 | 6429-08-001RMC - 642908001 | Harris Houston |
COMMUNICATION CABLEIH 610 · | $1,846,492 | $1,609,628 | TRAF-TEX, INC. | -12.8% | 2 |
| Aug 3, 2023 | 0920-06-037BR 2023(927) | Newton Beaumont |
BRIDGE REPLACEMENTCR · | $1,615,050 | $1,497,066 | RAYFORD'S TRUCK & TRACTOR | -7.3% | 7 |
| Aug 3, 2023 | 0902-90-244STP 2B23(145)HES | Tarrant Fort Worth |
SIGNAL IMPROVEMENTS,LEDS & GPS CLOCKSVA · | $1,298,882 | $1,495,754 | YUNEX LLC | +15.2% | 3 |
| Aug 3, 2023 | 6444-12-001RMC - 644412001 | Houston Lufkin |
MILL AND INLAYSH 19 · | $1,332,503 | $1,188,488 | TEXAS MATERIALS GROUP, INC. | -10.8% | 2 |
| Aug 3, 2023 | 0253-02-033BR 2B23(128) | Blanco Austin |
BRIDGE MAINTENANCEUS 281 · | $939,269 | $1,151,581 | ALLEN KELLER COMPANY | +22.6% | 4 |
| Aug 3, 2023 | 6400-90-001RMC - 640090001 | Denton Dallas |
REFLECTORIZED PAVEMENT MARKINGS & MARKERSSH 114 · | $1,108,450 | $1,125,566 | TRAFFIC HIGHWAY MAINTENANCE, LLC | +1.5% | 2 |
| Aug 3, 2023 | 0095-05-064STP 2B23(096)HES | Kaufman Dallas |
INSTALL MEDIAN BARRIERUS 80 · | $879,590 | $1,089,056 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | +23.8% | 7 |
| Aug 3, 2023 | 6441-25-001RMC - 644125001 | Kaufman Dallas |
METAL BEAM GUARD FENCE REPAIRIH 20 · | $1,608,110 | $1,042,859 | FIREMAN EXCAVATING, INC. | -35.2% | 4 |
| Aug 3, 2023 | 0260-02-051STP 2B23(098)HES | Ellis Dallas |
HAZARD ELIMINATION & SAFETYUS 67 · | $1,110,150 | $1,035,719 | SCOUT 5 CONSTRUCTION LLC | -6.7% | 5 |
| Aug 3, 2023 | 0914-19-033BR 2B20(089) | Gillespie Austin |
BRIDGE REPLACEMENTCR · | $847,359 | $1,025,365 | DELGADO'S CONTRACTORS, LLC | +21.0% | 6 |
| Aug 3, 2023 | 6405-44-001RMC - 640544001 | Travis Austin |
DEBRIS REMOVALIH 35 · | $1,243,461 | $937,598 | T.F.R. ENTERPRISES, INC. | -24.6% | 3 |
| Aug 3, 2023 | 0086-14-101STP 2023(870)HES | Webb Laredo |
INTERCHANGE IMPROVEMENTSS 260 · | $1,099,372 | $916,544 | TRIPLE H FIELD SERVICES, LLC | -16.6% | 2 |
| Aug 3, 2023 | 6441-35-001RMC - 644135001 | Jefferson Beaumont |
FULL DEPTH CONCRETE REPAIRIH 10 · | $927,053 | $886,093 | ICOS MANAGEMENT, LLC | -4.4% | 4 |
| Aug 3, 2023 | 0909-36-165BR 1802(814) | Bell Waco |
REHABILITATE BRIDGE AND APPROACHESCS · | $705,810 | $881,150 | SCR CIVIL CONSTRUCTION, LLC | +24.8% | 3 |
| Aug 3, 2023 | 6436-90-001RMC - 643690001 | Kaufman Dallas |
TRAFFIC CONTROL SERVICESIH 20 · | $1,070,375 | $861,750 | AWP SAFETY | -19.5% | 4 |
| Aug 3, 2023 | 6430-79-001BPM - 643079001 | Taylor Abilene |
BRIDGE PREVENTATIVE MAINTENANCEIH 20 · | $955,894 | $850,490 | PATHFIELD INVESTMENTS LLC | -11.0% | 9 |
| Aug 3, 2023 | 6446-90-001MMC - 644690001 | Hansford Amarillo |
WINTER WEATHER MATERIALSH 15 · | $780,848 | $772,453 | VOLCANIC STONE CO. | -1.1% | 1 |
| Aug 3, 2023 | 0902-39-029BR 2022(022) | Palo Pinto Fort Worth |
BRIDGE REPLACEMENTCR · | $691,303 | $724,492 | PMCO CONSTRUCTION LLC | +4.8% | 3 |
| Aug 3, 2023 | 0495-05-061F 2B23(180) | Smith Tyler |
RESURFACE ROADWAYIH 20 · | $577,549 | $693,237 | FNH CONSTRUCTION, LLC | +20.0% | 2 |
| Aug 3, 2023 | 0917-18-082BR 2021(235) | Robertson Bryan |
BRIDGE REPLACEMENTCS · | $481,799 | $663,959 | FUQUA CONSTRUCTION CO., INC. | +37.8% | 4 |
| Aug 3, 2023 | 6439-70-001RMC - 643970001 | Harris Houston |
REFLECTIVE PAVEMENT MARKINGS (GRAPHICS)IH 69 · | $693,675 | $630,506 | PROFESSIONAL TRAFFIC CONTROL LLC | -9.1% | 5 |
| Aug 3, 2023 | 6408-75-001MMC - 640875001 | Travis Austin |
WINTER WEATHER MATERIALIH 35 · | $648,127 | $614,755 | NSG LOGISTICS, LLC | -5.1% | 2 |
| Aug 3, 2023 | 6443-26-001MMC - 644326001 | Grimes Bryan |
WINTER WEATHER MATERIALSH 30 · | $546,000 | $551,200 | SOUTHWEST ENVIROTX PARTNERS, LLC | +1.0% | 1 |
| Aug 3, 2023 | 0910-36-134STP 2B23(066)HES | Cherokee Tyler |
HAZARD ELIMINATION & SAFETYVA · | $644,986 | $532,753 | GARRET SHIELDS INFRASTRUCTURE | -17.4% | 3 |
| Aug 3, 2023 | 6434-04-001RMC - 643404001 | Erath Fort Worth |
METAL BEAM GUARD FENCE REPAIRUS 377 · | $774,139 | $498,349 | SHORT-LINE CORPORATION | -35.6% | 4 |
| Aug 3, 2023 | 0906-32-060STP 2B23(013)HESG | Midland Odessa |
INTERSECTION IMPROVEMENTCS · | $494,356 | $496,353 | TI-ZACK CONCRETE, INC. | +0.4% | 3 |
| Aug 3, 2023 | 0039-07-260F 2B23(061) | Cameron Pharr |
HAZARD ELIMINATION & SAFETYIH 69E · | $767,032 | $489,585 | PAVEMENT MARKINGS INC. | -36.2% | 3 |
| Aug 3, 2023 | 6447-22-001MMC - 644722001 | Hunt Paris |
DENSE GRADED HOT MIXUS 69 · | $469,125 | $439,560 | RK HALL, LLC | -6.3% | 3 |
| Aug 3, 2023 | 1094-02-017F 2B23(174) | Tarrant Fort Worth |
LANDSCAPE DEVELOPMENTFM 731 · | $483,670 | $434,716 | CENTRAL NORTH CONSTRUCTION, LLC | -10.1% | 2 |
| Aug 3, 2023 | 6447-08-001MMC - 644708001 | Hunt Paris |
LIMESTONE ROCK ASPHALTIH 30 · | $403,750 | $412,863 | MARTIN MARIETTA MATERIALS, INC. | +2.3% | 2 |
| Aug 3, 2023 | 0921-06-356STP 2B23(056)HESG | Cameron Pharr |
HAZARD ELIMINATION & SAFETYCS · | $435,962 | $368,889 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | -15.4% | 3 |
| Aug 3, 2023 | 6436-98-001RMC - 643698001 | Brown Brownwood |
CRACK SEALUS 377 · | $715,355 | $342,333 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | -52.1% | 5 |
| Aug 3, 2023 | 6442-62-001RMC - 644262001 | Hood Fort Worth |
METAL BEAM GUARD FENCE REPAIRUS 377 · | $450,250 | $339,319 | T&L CLEANING SERVICES LLC | -24.6% | 4 |
| Aug 3, 2023 | 6439-12-001TMC - 643912001 | Travis Austin |
ROW TRAFFIC MATERIALSIH 35 · | $194,000 | $338,750 | ROAD SOLUTIONS L.L.C. | +74.6% | 1 |
| Aug 3, 2023 | 6441-03-001RMC - 644103001 | Ellis Dallas |
REMOVAL AND DISPOSAL OF DRIFTWOODFM 813 · | $374,148 | $332,030 | RHINO EQUITY, LLC | -11.3% | 5 |
| Aug 3, 2023 | 6447-67-001MMC - 644767001 | Hopkins Paris |
ANTI-ICER - COMPLEX CHLORIDESH 11 · | $390,235 | $329,772 | NSG LOGISTICS, LLC | -15.5% | 3 |
| Aug 3, 2023 | 6438-82-001RMC - 643882001 | Dallas Dallas |
REFLECTORIZED PAVEMENT MARKINGS & MARKERSUS 75 · | $305,760 | $329,052 | TRP CONSTRUCTION GROUP, LLC | +7.6% | 2 |
| Aug 3, 2023 | 6444-48-001RMC - 644448001 | Harris Houston |
HIGH EDGE REMOVALSL 8 · | $394,400 | $328,000 | RHINO EQUITY, LLC | -16.8% | 5 |
| Aug 3, 2023 | 0916-35-239STP 2B23(211)HESG | Nueces Corpus Christi |
TRAFFIC SIGNAL IMPROVEMENTSCS · | $307,257 | $302,655 | HIGHWAY BARRICADES AND SERVICES, LLC | -1.5% | 1 |
| Aug 3, 2023 | 2642-01-049STP 2B23(070)HES | Gregg Tyler |
HAZARD ELIMINATION & SAFETYSL 281 · | $246,510 | $225,255 | THK CONSTRUCTION LLC | -8.6% | 8 |
| Aug 3, 2023 | 6445-98-001RMC - 644598001 | McLennan Waco |
CULVERT CLEANINGFM 2957 · | $180,863 | $199,083 | SHALOM SERVICES CORPORATION | +10.1% | 2 |
| Aug 3, 2023 | 0921-02-508STP 2B23(057)HESG | Hidalgo Pharr |
HAZARD ELIMINATION & SAFETYCS · | $178,884 | $192,173 | THE LEVY COMPANY, INC. | +7.4% | 3 |
1–100 of 217Next ›
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.