161Let jobs
$860,932,831Total low bids
$785,198,770Total estimates
+9.6%Low bids vs estimates
Aug 2019 results
Bid tabs (Excel) ExcelCSV| Let date | CCSJ | County / District | Project | Estimate | Low bid | Low bidder | % vs est. | Bidders |
|---|---|---|---|---|---|---|---|---|
| Aug 6, 2019 | 2686-01-014SSW 2686-1-14 | Bastrop Austin |
PROVIDE ADDITIONAL PAVED SURFACE WIDTHFM 2571 · | $5,241,453 | $7,264,834 | CHASCO CONSTRUCTORS | +38.6% | 4 |
| Aug 6, 2019 | 0081-01-051NH 1902(356) | Tarrant Fort Worth |
PREVENTATIVE MAINTENANCEUS 377 · | $5,214,404 | $6,436,652 | JAGOE-PUBLIC COMPANY | +23.4% | 5 |
| Aug 6, 2019 | 0246-01-036STP 1902(169) | Rusk Tyler |
PLN,SPRPV BS,OCST,PFC SURF,BRG RAIL,MBGF,PV MKUS 79 · | $6,188,566 | $6,403,501 | MADDEN CONTRACTING COMPANY, LLC. | +3.5% | 2 |
| Aug 6, 2019 | 0915-12-602STP 1902(097)MM | Bexar San Antonio |
TRANSGUIDE FACILITY RENOVATIONSVA · | $5,185,770 | $5,866,947 | SPAW GLASS CONTRACTORS, INC. | +13.1% | 1 |
| Aug 6, 2019 | 0005-05-114STP 1902(336)HES | Howard Abilene |
MEDIAN CABLE BARRIERIH 20 · | $7,228,974 | $5,297,532 | GRATIOT CONSTRUCTION, LTD. | -26.7% | 3 |
| Aug 6, 2019 | 6344-65-001RMC - 634465001 | Johnson Fort Worth |
FLEXIBLE PAVEMENT STRUCTURE REPAIRIH 35W · | $2,513,074 | $3,662,171 | NORTHEASTERN PAVERS, LLC | +45.7% | 4 |
| Aug 6, 2019 | 3510-05-045C 3510-5-45 | Harris Houston |
LANDSCAPE DEVELOPMENTSH 99 · | $4,059,577 | $3,484,500 | APEX LANDSCAPE & IRRIGATION, LLC | -14.2% | 4 |
| Aug 6, 2019 | 0063-06-099BR 1902(284) | Shelby Lufkin |
BRIDGE MAINTENANCEUS 96 · | $3,622,328 | $3,364,209 | GIBSON & ASSOCIATES, INC. | -7.1% | 7 |
| Aug 6, 2019 | 0913-20-089BR 2018(205) | Austin Yoakum |
REPLACE BRIDGE AND APPROACHESCR · | $2,298,539 | $3,274,001 | FUQUA CONSTRUCTION CO., INC. | +42.4% | 2 |
| Aug 6, 2019 | 2874-01-006C 2874-1-6 | Fannin Paris |
REHABILITATE EXISTING ROADWAYFM 2815 · | $2,850,289 | $3,077,923 | A. K. GILLIS & SONS, INC. | +8.0% | 6 |
| Aug 6, 2019 | 3409-01-006STP 1902(271) | Bell Waco |
ADD TURN LANESFM 3481 · | $2,216,886 | $3,063,792 | TEXAS MATERIALS GROUP, INC. | +38.2% | 2 |
| Aug 6, 2019 | 0101-04-113STP 1902(301)HES | San Patricio Corpus Christi |
IMPROVE TRAFFIC SIGNALS, INTERCONNECT SIGNALSUS 181 · | $3,089,908 | $2,780,024 | AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | -10.0% | 5 |
| Aug 6, 2019 | 0188-09-042STP 1902(327) | Fort Bend Houston |
WIDEN FROM 2 TO 4 LANESFM 723 · | $2,421,870 | $2,399,432 | MBN ENTERPRISES LLC | -0.9% | 8 |
| Aug 6, 2019 | 1615-02-016STP 1902(043)HES | Clay Wichita Falls |
SAFETY TRT FXD OBJ, ADDL SURF WIDTH, RUMBLE STRIPSFM 1740 · | $1,637,724 | $2,211,991 | A. L. HELMCAMP, INC. | +35.1% | 2 |
| Aug 6, 2019 | 0271-01-079STP 1902(291)HES | Colorado Yoakum |
IMPROVE GRDRAIL TO DESIGN STANDARDS,ETC.IH 10 · | $1,686,593 | $2,199,681 | 3LW CIVIL LLC | +30.4% | 1 |
| Aug 6, 2019 | 1076-01-038BR 2019(959) | Throckmorton Wichita Falls |
REPLACE BRIDGE AND APPROACHESFM 209 · | $1,496,557 | $2,072,677 | STATELINE CONSTRUCTION, LLC | +38.5% | 5 |
| Aug 6, 2019 | 1513-02-042STP 1902(334)HES | Johnson Fort Worth |
CONSTRUCT FRONTAGE ROADSFM 4 · | $1,619,915 | $1,990,742 | ED BELL CONSTRUCTION COMPANY | +22.9% | 3 |
| Aug 6, 2019 | 0911-04-055C 911-4-55 | Polk Lufkin |
REPAIR AND RESURFACE PAVED AREASVA · | $1,549,868 | $1,899,424 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | +22.6% | 1 |
| Aug 6, 2019 | 1804-01-079BR 1902(310) | Hidalgo Pharr |
BRIDGE MAINTENANCESS 115 · | $1,655,690 | $1,760,708 | CLORE EQUIPMENT LLC | +6.3% | 5 |
| Aug 6, 2019 | 0346-06-049STP 1902(297)HES | Lavaca Yoakum |
SAFETY TREAT FIXED OBJECTSSH 111 · | $1,197,167 | $1,589,955 | CONSTAR CONSTRUCTION | +32.8% | 3 |
| Aug 6, 2019 | 0134-09-066NH 1902(375) | Denton Dallas |
PLANTING AND IRRIGATIONUS 380 · | $1,836,127 | $1,535,126 | CENTRAL NORTH CONSTRUCTION, LLC | -16.4% | 3 |
| Aug 6, 2019 | 0010-08-057STP 1902(303)HES | Morris Atlanta |
PROFILE EDGELINE AND CENTERLINE MARKINGSUS 67 · | $1,545,614 | $1,488,937 | STRIPING TECHNOLOGY, L.P. | -3.7% | 4 |
| Aug 6, 2019 | 6345-56-001RMC - 634556001 | Harris Houston |
ROADSIDE MOWINGSH 249 · | $1,503,159 | $1,373,129 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | -8.7% | 2 |
| Aug 6, 2019 | 2121-02-170NH 1902(351) | El Paso El Paso |
PREVENTIVE MAINTENANCEIH 10 · | $1,987,505 | $1,230,391 | LESNA CONSTRUCTION, INC. | -38.1% | 7 |
| Aug 6, 2019 | 6345-19-001RMC - 634519001 | Kaufman Dallas |
SWEEPING & DEBRIS REMOVALIH 20 · | $1,425,499 | $1,208,014 | SWEEPING SERVICES OF TEXAS - OPERATING, L.P. | -15.3% | 3 |
| Aug 6, 2019 | 0016-16-030STP 1902(326)MM | Hays Austin |
REHABILITATION OF EXISTING ROADRM 967 · | $1,239,810 | $1,175,631 | LONE STAR SITEWORK, LLC | -5.2% | 3 |
| Aug 6, 2019 | 6345-45-001RMC - 634545001 | Harris Houston |
PREV MNT OF SGNL EQUIPIH 610 · | $1,188,290 | $1,114,480 | LINDSEY ELECTRIC, L.P. | -6.2% | 7 |
| Aug 6, 2019 | 0049-12-115STP 2019(461)TAPS | Brazos Bryan |
PEDESTRIAN, SIDEWALKS AND CURB RAMPSSH 6 · | $1,178,919 | $1,105,702 | LARRY YOUNG PAVING, INC. | -6.2% | 8 |
| Aug 6, 2019 | 0091-04-064NH 1902(376) | Collin Dallas |
LANDSCAPE ENHANCEMENTS FOR MEDIANS & RIGHT OF WAYSH 289 · | $1,147,927 | $1,097,507 | CENTRAL NORTH CONSTRUCTION, LLC | -4.4% | 3 |
| Aug 6, 2019 | 0500-03-631NH 1902(329) | Harris Houston |
LANDSCAPE DEVELOPMENTIH 45 · | $1,113,297 | $1,070,059 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | -3.9% | 2 |
| Aug 6, 2019 | 0172-02-076STP 1902(260) | Tarrant Fort Worth |
RESURFACE ROADWAYBU 287P · | $1,090,735 | $1,029,421 | ED BELL CONSTRUCTION COMPANY | -5.6% | 2 |
| Aug 6, 2019 | 6339-12-001RMC - 633912001 | Taylor Abilene |
INSTALLATION OF PAVEMENT MARKINGSIH 20 · | $1,036,280 | $987,407 | STRIPE-A-ZONE, INC. | -4.7% | 5 |
| Aug 6, 2019 | 0055-08-122STP 1902(127)HES | McLennan Waco |
INSTALL CABLE MEDIAN BARRIERUS 84 · | $1,177,268 | $986,493 | MASSANA CONSTRUCTION INC. | -16.2% | 5 |
| Aug 6, 2019 | 6343-20-001RMC - 634320001 | Palo Pinto Fort Worth |
FLEXIBLE PAVEMENT REPAIRSH 16 · | $1,013,778 | $977,100 | NORTHEASTERN PAVERS, LLC | -3.6% | 4 |
| Aug 6, 2019 | 6342-36-001RMC - 634236001 | McLennan Waco |
MBGF, CABLE BARRIER, BRIDGE RAIL REP/INSUS 84 · | $812,766 | $971,242 | T&L CLEANING SERVICES LLC | +19.5% | 3 |
| Aug 6, 2019 | 6345-31-001RMC - 634531001 | Harris Houston |
MNT OF COMMUNICATION CABLEIH 610 · | $1,043,974 | $925,713 | FLORIDA TRAFFIC CONTROL DEVICES, INC. | -11.3% | 3 |
| Aug 6, 2019 | 0596-01-021STP 1902(017)HRR | Hill Waco |
SAFETY TREAT FIXED OBJECTSFM 66 · | $854,447 | $849,409 | BEAR CREEK CONTRACTING, LLC | -0.6% | 6 |
| Aug 6, 2019 | 0161-01-030STP 2019(979)HES | Val Verde Laredo |
TRAFFIC SIGNAL IMPROVEMENTSUP 277 · | $791,064 | $846,878 | LIGHT IT UP ELECTRIC | +7.1% | 3 |
| Aug 6, 2019 | 0901-29-081BR 1402(210) | Lamar Paris |
BRIDGE REPLACEMENTCR · | $767,029 | $777,277 | HIGHWAY 19 CONSTRUCTION LLC | +1.3% | 6 |
| Aug 6, 2019 | 0043-17-032STP 1902(337)HES | Wichita Wichita Falls |
MILLED CENTERLINE RUMBLE STRIPSBU 287J · | $836,945 | $761,013 | TOTAL HIGHWAY MAINTENANCE, LLC | -9.1% | 5 |
| Aug 6, 2019 | 0367-06-063NH 1902(328) | Galveston Houston |
LANDSCAPE DEVELOPMENTSH 87 · | $877,322 | $758,074 | ENVIRONMENTAL SOUTHWEST | -13.6% | 3 |
| Aug 6, 2019 | 0902-90-038STP 1902(202)HES | Tarrant Fort Worth |
SAFETY IMPROVEMENT PROJECTCS · | $3,162,855 | $711,530 | AMERICAN LIGHTING AND SIGNALIZATION, LLC | -77.5% | 2 |
| Aug 6, 2019 | 0412-05-037STP 1902(191)HES | Val Verde Laredo |
REPLACE GUARDRAILSH 163 · | $606,347 | $705,850 | K-BAR SERVICES, INC. | +16.4% | 5 |
| Aug 6, 2019 | 6338-96-001RMC - 633896001 | Tarrant Fort Worth |
THERMOPLASTIC STRIPING-RPM'S-ELIMINATIONUS 81 · | $779,800 | $697,793 | TRP CONSTRUCTION GROUP, LLC | -10.5% | 4 |
| Aug 6, 2019 | 0025-09-079STP 1902(315)HES | Bexar San Antonio |
HAZARD ELIMINATION & SAFETYFM 78 · | $664,861 | $627,875 | THE LEVY COMPANY, INC. | -5.6% | 6 |
| Aug 6, 2019 | 6316-91-001RMC - 631691001 | Stephens Brownwood |
REPAIR/REPLACE CULVERTSUS 183 · | $540,941 | $576,697 | 3LW CIVIL LLC | +6.6% | 3 |
| Aug 6, 2019 | 6344-62-001BPM - 634462001 | Comanche Brownwood |
MISCELLANEOUS BRIDGE REPAIRSSH 16 · | $708,119 | $575,288 | BECK-REIT & SONS, LTD. | -18.8% | 6 |
| Aug 6, 2019 | 0944-02-011STP 1902(331)HES | Waller Houston |
INST ADVANCE WARNING SIGNALS & FLASHING CHEVRONSFM 362 · | $619,451 | $519,843 | STATEWIDE TRAFFIC SIGNAL COMPANY | -16.1% | 5 |
| Aug 6, 2019 | 0199-01-084NH 1902(286) | Cherokee Tyler |
SIDEWALKS, DRIVEWAYS, DRNG, STRS, PV MKUS 69 · | $598,150 | $502,100 | HIGHWAY 19 CONSTRUCTION LLC | -16.1% | 6 |
| Aug 6, 2019 | 0913-28-066BR 2014(600) | Fayette Yoakum |
REPLACE BRIDGE AND APPROACHESCR · | $412,052 | $479,284 | TREVWAY, INC. | +16.3% | 6 |
| Aug 6, 2019 | 6344-33-001RMC - 634433001 | Navarro Dallas |
REPAIR/REPLACE CONCRETE BARRIERIH 45 · | $450,508 | $477,499 | GIBSON & ASSOCIATES, INC. | +6.0% | 2 |
| Aug 6, 2019 | 6341-11-001RMC - 634111001 | Gonzales Yoakum |
THERMOPLASTIC PAVEMENT MARKINGSFM 795 · | $355,930 | $402,393 | L&L COMPANY | +13.1% | 6 |
| Aug 6, 2019 | 0919-03-059BR 2019(351) | Harrison Atlanta |
BRIDGE REPLACEMENTCR · | $369,828 | $398,057 | LONGVIEW BRIDGE AND ROAD, LTD. | +7.6% | 6 |
| Aug 6, 2019 | 0902-90-088NH 1902(264) | Tarrant Fort Worth |
INSTALL/REPLACE SIGNSVA · | $609,090 | $370,947 | SYNERGY SIGNS & SERVICES LLC | -39.1% | 8 |
| Aug 6, 2019 | 6344-18-001RMC - 634418001 | Parker Fort Worth |
TREE TRIMMING AND BRUSH AND TREE REMOVALFM 51 · | $384,582 | $359,144 | C.E.S. CONTRACTOR | -6.6% | 3 |
| Aug 6, 2019 | 6335-80-001BPM - 633580001 | Mason Austin |
BRIDGE PREVENTATIVE MAINTENANCEUS 87 · | $370,419 | $338,504 | SJ&J CONSTRUCTION, LLC | -8.6% | 5 |
| Aug 6, 2019 | 0495-08-117BR 1902(306) | Harrison Atlanta |
CONCRETE STRUCTURE REPAIR AND JOINT CLEANINGIH 20 · | $290,550 | $329,387 | R & G CONSTRUCTION, LLC | +13.4% | 6 |
| Aug 6, 2019 | 0902-90-037STP 1902(262)HES | Tarrant Fort Worth |
INSTALL TRAFFIC SIGNALCS · | $228,487 | $262,694 | HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. | +15.0% | 4 |
| Aug 6, 2019 | 0915-00-226NH 1902(352) | Bexar San Antonio |
WILDFLOWER PLANTING DISTRICTWIDE · | $278,088 | $238,000 | K-BAR SERVICES, INC. | -14.4% | 2 |
| Aug 6, 2019 | 0055-04-031STP 2019(999)HES | Coryell Waco |
INSTALL INTERSECTION FLASHING BEACONUS 84 · | $166,380 | $139,750 | CHAMPION INFRASTRUCTURE, LLC | -16.0% | 4 |
| Aug 6, 2019 | 1606-01-034STP 1902(348)HES | Wise Fort Worth |
HAZARD ELIMINATION & SAFETYFM 1658 · | $93,070 | $80,011 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | -14.0% | 4 |
101–161 of 161‹ Prev
Source: TxDOT Bid Tabulations (data.texas.gov), which covers state and local lettings from the previous 24 months. Bid Potato keeps every month it has loaded, so history grows past that window. Totals are as read at the letting; on packaged proposals the low bid can be the whole package total. Confirm against TxDOT's official tabulations.