FY26 Plainview ASPPM
- Let date
- Tuesday, April 21, 2026
- CCSJ
- 6499-15-001
- District
- Lubbock
- County
- Hale
- Highway
- IH0027
- Limits
- VARIOUS LOCATIONS to VARIOUS LOCATIONS
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00220173
- Working days
- 180
- DBE goal
- 0%
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $437,500 | ||
| 1 | L A FULLER & SONS CONSTRUCTION, LTD. Low bidder | $428,175 | -2.1% | |
| 2 | TOUCHSTONE RESOURCES, LLC | $528,500 | +20.8% | +23.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 L A FULLER & SO… | #2 TOUCHSTONE RESO… |
|---|---|---|---|---|---|---|---|
| 1 | 8012-7097 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST1) | 500 | TON | $175.00 | $166.30 | $225.00 |
| 2 | 8012-7098 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST2) | 500 | TON | $175.00 | $162.50 | $222.00 |
| 3 | 8012-7099 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST3) | 500 | TON | $175.00 | $169.40 | $220.00 |
| 4 | 8012-7100 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST4) | 500 | TON | $175.00 | $175.75 | $190.00 |
| 5 | 8012-7101 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST5) | 500 | TON | $175.00 | $182.40 | $200.00 |