$172.07Avg low bid / TON
$194.49Avg of all bids
$173.04Avg engineer's estimate
15Jobs · 4,450 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 7 | 2,175 | $169.97 | $193.36 |
| 2025 | 7 | 2,250 | $172.39 | $194.74 |
| 2024 | 1 | 25 | $325.00 | $325.00 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 19, 2026 | 6508-67-001 | El PasoEl Paso | 25 TON | $292.75 | HALL BROTHERS, INC. |
| Oct 15, 2026 | 6510-65-001 | HuntParis | 300 TON | $192.10 | HALL BROTHERS, INC. |
| Jun 4, 2026 | 6500-46-001 | ShackelfordAbilene | 100 TON | $145.50 | ZACK BURKETT CO. |
| Apr 21, 2026 | 6499-16-001 | LubbockLubbock | 500 TON | $180.15 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Apr 21, 2026 | 6499-14-001 | LambLubbock | 500 TON | $175.20 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Apr 21, 2026 | 6499-15-001 | HaleLubbock | 500 TON | $162.50 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Feb 17, 2026 | 6494-36-001 | WhartonYoakum | 250 TON | $125.05 | WALLER COUNTY ASPHALT INC. |
| Nov 24, 2025 | 6470-78-001 | HidalgoPharr | 100 TON | $209.40 | WALLER COUNTY ASPHALT INC. |
| Oct 16, 2025 | 6491-75-001 | HuntParis | 300 TON | $202.00 | RK HALL, LLC |
| May 15, 2025 | 6482-62-001 | LambLubbock | 500 TON | $175.20 | L A FULLER & SONS CONSTRUCTION, LTD. |
| May 15, 2025 | 6482-63-001 | HaleLubbock | 500 TON | $162.50 | L A FULLER & SONS CONSTRUCTION, LTD. |
| May 15, 2025 | 6482-61-001 | TerryLubbock | 500 TON | $183.25 | L A FULLER & SONS CONSTRUCTION, LTD. |
| Feb 18, 2025 | 6476-54-001 | WhartonYoakum | 250 TON | $125.05 | WALLER COUNTY ASPHALT INC. |
| Feb 11, 2025 | 6479-37-001 | JeffersonBeaumont | 100 TON | $146.05 | WALLER COUNTY ASPHALT INC. |
| Nov 26, 2024 | 6474-37-001 | El PasoEl Paso | 25 TON | $325.00 | TOUCHSTONE RESOURCES, LLC |