FY25 Brownfield ASPPM
- Let date
- Thursday, May 15, 2025
- CCSJ
- 6482-61-001
- District
- Lubbock
- County
- Terry
- Highway
- US0062
- Limits
- VARIOUS LOCATIONS to VARIOUS LOCATIONS
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00214795
- Working days
- 180
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $525,000 | ||
| 1 | L A FULLER & SONS CONSTRUCTION, LTD. Low bidder | $556,900 | +6.1% | |
| 2 | SOUTHERN SOURCING SOLUTIONS, LLC | $580,860 | +10.6% | +4.3% |
| 3 | A. L. HELMCAMP, INC. | $601,320 | +14.5% | +8.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 L A FULLER & SO… | #2 SOUTHERN SOURCI… | #3 A. L. HELMCAMP,… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8012-7097 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST1) | 500 | TON | $175.00 | $185.70 | $207.00 | $200.44 |
| 2 | 8012-7098 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST2) | 500 | TON | $175.00 | $183.25 | $194.37 | $200.44 |
| 3 | 8012-7099 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST3) | 500 | TON | $175.00 | $180.30 | $192.50 | $200.44 |
| 4 | 8012-7100 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST4) | 500 | TON | $175.00 | $183.50 | $189.75 | $200.44 |
| 5 | 8012-7101 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST5) | 500 | TON | $175.00 | $193.15 | $195.50 | $200.44 |
| 6 | 8012-7102 | ASPH CONC PAT MAT(ASPPM)(DEL)(ST6) | 500 | TON | $175.00 | $187.90 | $182.60 | $200.44 |