FY25 Walker HMA -01
- Let date
- Tuesday, March 11, 2025
- CCSJ
- 6478-09-001
- District
- Bryan
- County
- Walker
- Highway
- IH0045
- Limits
- Various to Various
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00213197
- Working days
- 180
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $680,000 | ||
| 1 | BIG CREEK CONSTRUCTION, LTD. Low bidder | $626,200 | -7.9% | |
| 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $683,800 | +0.6% | +9.2% |
| 3 | TOUCHSTONE RESOURCES, LLC | $782,400 | +15.1% | +24.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BIG CREEK CONST… | #2 VULCAN CONSTRUC… | #3 TOUCHSTONE RESO… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8011-7055 | D-GR HMA TY D PG 64-22 (PICKUP) | 200 | TON | $110.00 | $70.00 | $91.00 | $105.00 |
| 2 | 8011-7056 | D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 2,000 | TON | $120.00 | $99.00 | $103.00 | $120.00 |
| 3 | 8011-7091 | D-GR HMA TY F PG 64-22 (PICKUP) | 200 | TON | $90.00 | $71.00 | $98.00 | $107.00 |
| 4 | 8011-7092 | D-GR HMA TY F PG 64-22 (DEL) SITE 1 | 4,000 | TON | $100.00 | $100.00 | $110.00 | $125.00 |