RAISED PAVEMENT MARKERS
- Let date
- Friday, August 2, 2024
- CCSJ
- 6467-34-001
- District
- Atlanta
- County
- Bowie
- Highway
- US 59
- Limits
- VARIOUS ROADWAYS to VARIOUS ROADWAYS
- Classification
- Maintenance
- Project number
- RMC - 646734001
- Working days
- 254
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,075,005 | ||
| 1 | TRP INFRASTRUCTURE SERVICES, LLC Low bidder | $858,521 | -20.1% | |
| 2 | CENTERLINE TECHNOLOGIES, LLC | $913,613 | -15.0% | +6.4% |
| 3 | FC TRAFFIC CONTROL, INC. | $969,455 | -9.8% | +12.9% |
| 4 | STRIPE-A-ZONE, LLC | $988,390 | -8.1% | +15.1% |
| 5 | CROSS PLUS CONSTRUCTION, LLC | $1,251,818 | +16.4% | +45.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TRP INFRASTRUCT… | #2 CENTERLINE TECH… | #3 FC TRAFFIC CONT… | #4 STRIPE-A-ZONE, … | #5 CROSS PLUS CONS… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 18 | EA | $2,000.00 | $1.00 | $1.00 | $3,000.00 | $100.00 | $1.00 |
| 2 | 672-6006 | REFL PAV MRKR TY I-A | 400 | EA | $4.20 | $4.22 | $10.00 | $4.50 | $4.75 | $7.00 |
| 3 | 672-6007 | REFL PAV MRKR TY I-C | 18,000 | EA | $4.90 | $4.22 | $4.48 | $4.50 | $4.58 | $6.00 |
| 4 | 672-6009 | REFL PAV MRKR TY II-A-A | 150,000 | EA | $4.90 | $4.22 | $4.48 | $4.50 | $4.58 | $6.00 |
| 5 | 672-6010 | REFL PAV MRKR TY II-C-R | 35,000 | EA | $4.90 | $4.22 | $4.48 | $4.50 | $4.60 | $6.00 |
| 6 | 6185-6005 | TMA (MOBILE OPERATION) | 155 | DAY | $275.00 | $1.00 | $1.00 | $1.00 | $350.00 | $200.00 |