Bid tab 6372-48-001

Let Nov 4, 2020 · El Paso · El Paso Sign up free

‹ Nov 2020 results

BARRICADES, SIGNS AND TRAFFIC CONTROL

Let date
Wednesday, November 4, 2020
CCSJ
6372-48-001
District
El Paso
County
El Paso
Highway
IH 10
Limits
VARIOUS LOCATIONS to VARIOUS LOCATIONS
Classification
Maintenance
Project number
RMC - 637248001
Working days
365

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$427,500
1 APACHE BARRICADE & SIGN Low bidder $342,860 -19.8%
2 SYNERGY PROJECT CONTRACTORS, INC. $373,282 -12.7% +8.9%
3 DOUBLE H CONTRACTING INC. $382,650 -10.5% +11.6%
4 MIJELUM, L.L.C. $401,401 -6.1% +17.1%
5 LESNA CONSTRUCTION, INC. $548,550 +28.3% +60.0%

Bid tab: unit prices 27 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 APACHE BARRICAD…#2 SYNERGY PROJECT…#3 DOUBLE H CONTRA…#4 MIJELUM, L.L.C.#5 LESNA CONSTRUCT…
1500-6001 MOBILIZATION1LS $15,000.00 $1,000.00 $20,520.00 $4,000.00 $1.00 $20,000.00
2512-6061 PORT CONC TRAF BAR (STKPL,INSTL&RETRN)100LF $15.00 $35.00 $22.80 $10.00 $200.00 $60.00
3545-6002 CRASH CUSH ATTEN (DES SOURCE)2EA $2,500.00 $1,500.00 $1,368.00 $500.00 $10,000.00 $2,000.00
4545-6003 CRASH CUSH ATTEN (MOVE & RESET)1EA $13,400.00 $1,500.00 $1,482.00 $500.00 $5,000.00 $3,500.00
5545-6019 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)1EA $15,000.00 $11,000.00 $13,566.00 $500.00 $20,000.00 $23,000.00
66158-6001 TMSP RADAR SPEED CONTROL MONITOR2EA $500.00 $55.00 $5,130.00 $125.00 $1,000.00 $12,000.00
76185-6002 TMA (STATIONARY)100DAY $155.00 $225.00 $285.00 $250.00 $500.00 $1,000.00
86185-6003 TMA (MOBILE OPERATION)2,350HR $65.00 $85.00 $57.00 $95.00 $80.00 $75.00
97148-6001 1 LN CLOSURE 2 LN RD NO SHOULDERS60HR $105.00 $40.00 $34.20 $40.00 $5.00 $75.00
107148-6002 1 LN CLOSURE 2 LN RD PAVED SHOULDERS60HR $105.00 $40.00 $45.60 $40.00 $20.00 $75.00
117148-6003 1 LN CLOSURE 4 LN RD200HR $135.00 $40.00 $114.00 $90.00 $20.00 $75.00
127148-6004 2 LN CLOSURE 4 LN RD60HR $120.00 $45.00 $76.38 $50.00 $40.00 $75.00
137148-6005 FREEWAY 1 LANE CLOSURE250HR $175.00 $125.00 $188.10 $105.00 $50.00 $150.00
147148-6006 FREEWAY 2 LANE CLOSURE100HR $305.00 $140.00 $210.90 $200.00 $75.00 $500.00
157148-6007 FREEWAY 3 LANE CLOSURE40HR $330.00 $140.00 $222.30 $100.00 $150.00 $700.00
167148-6009 EXIT OR ENTRANCE RAMP CLOSURE250HR $90.00 $25.00 $75.24 $95.00 $50.00 $30.00
177148-6010 FREEWAY CLOSURE SEQUENCE DAYTIME ONLY10HR $150.00 $145.00 $399.00 $125.00 $100.00 $300.00
187148-6011 COMPLETE FREEWAY CLOSURE20HR $345.00 $425.00 $399.00 $450.00 $800.00 $800.00
197148-6012 ONE LANE FRONTAGE ROAD CLOSURE140HR $105.00 $40.00 $45.60 $60.00 $50.00 $40.00
207148-6013 TWO LANE FRONTAGE ROAD CLOSURE40HR $150.00 $40.00 $79.80 $50.00 $50.00 $70.00
217148-6014 ONE LANE CONNECTING RAMP CLOSURE10HR $70.00 $50.00 $68.40 $50.00 $50.00 $70.00
227148-6015 TWO LANE CONNECTING RAMP CLOSURE10HR $70.00 $50.00 $68.40 $40.00 $100.00 $70.00
237148-6016 WORK AREA ON SHOULDER100HR $90.00 $30.00 $22.80 $30.00 $100.00 $50.00
247148-6017 TURN AROUND CLOSURE120HR $80.00 $30.00 $29.64 $20.00 $50.00 $30.00
257148-6019 FURNISH ADDITIONAL FLAGGER20HR $50.00 $90.00 $39.90 $5.00 $50.00 $80.00
267148-6020 PILOT VEHICLE AND OPERATOR10HR $50.00 $85.00 $131.10 $5.00 $50.00 $80.00
277148-6021 FURNISH ADDITIONAL ARROW BOARD50HR $20.00 $10.00 $22.80 $5.00 $100.00 $10.00