$27.51Avg low bid / LF
$31.14Avg of all bids
$27.32Avg engineer's estimate
42Jobs · 15,610 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 400 | $10.00 | $45.00 |
| 2023 | 4 | 800 | $20.69 | $22.53 |
| 2022 | 4 | 650 | $73.08 | $55.96 |
| 2021 | 6 | 1,000 | $20.94 | $37.12 |
| 2020 | 7 | 1,500 | $30.67 | $41.21 |
| 2019 | 8 | 2,260 | $38.59 | $40.32 |
| 2018 | 4 | 2,100 | $12.57 | $11.12 |
| 2017 | 8 | 6,900 | $26.21 | $25.43 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 6, 2024 | 6457-85-001 | HudspethEl Paso | 400 LF | $10.00 | FC TRAFFIC CONTROL, INC. |
| Dec 5, 2023 | 6454-87-001 | El PasoEl Paso | 200 LF | $30.00 | APACHE BARRICADE & SIGN |
| Nov 1, 2023 | 6451-31-001 | El PasoEl Paso | 100 LF | $20.00 | FC TRAFFIC CONTROL, INC. |
| Nov 1, 2023 | 6455-27-001 | El PasoEl Paso | 100 LF | $17.10 | SYNERGY PROJECT CONTRACTORS, INC. |
| May 5, 2023 | 6435-00-001 | El PasoEl Paso | 400 LF | $17.10 | SYNERGY PROJECT CONTRACTORS, INC. |
| Dec 1, 2022 | 6425-30-001 | El PasoEl Paso | 100 LF | $20.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Nov 2, 2022 | 6421-87-001 | El PasoEl Paso | 50 LF | $10.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Oct 6, 2022 | 6418-81-001 | El PasoEl Paso | 100 LF | $50.00 | DOUBLE H CONTRACTING INC. |
| Feb 4, 2022 | 6394-82-001 | HudspethEl Paso | 400 LF | $100.00 | FC TRAFFIC CONTROL, INC. |
| Nov 4, 2021 | 6389-94-001 | El PasoEl Paso | 100 LF | $27.55 | E. G. L. CONSTRUCTION, INC. |
| Nov 4, 2021 | 6389-40-001 | El PasoEl Paso | 200 LF | $25.00 | APACHE BARRICADE & SIGN |
| Nov 3, 2021 | 6391-39-001 | El PasoEl Paso | 100 LF | $27.00 | APACHE BARRICADE & SIGN |
| Oct 7, 2021 | 6388-50-001 | El PasoEl Paso | 100 LF | $10.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Apr 7, 2021 | 6376-97-001 | El PasoEl Paso | 100 LF | $20.00 | LESNA CONSTRUCTION, INC. |
| Apr 7, 2021 | 6376-98-001 | El PasoEl Paso | 400 LF | $18.72 | SYNERGY PROJECT CONTRACTORS, INC. |
| Nov 4, 2020 | 6372-48-001 | El PasoEl Paso | 100 LF | $35.00 | APACHE BARRICADE & SIGN |
| Sep 3, 2020 | 6363-57-001 | El PasoEl Paso | 100 LF | $10.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Sep 3, 2020 | 6363-58-001 | El PasoEl Paso | 100 LF | $40.00 | E. G. L. CONSTRUCTION, INC. |
| Mar 25, 2020 | 6349-85-001 | CulbersonEl Paso | 300 LF | $25.00 | APACHE BARRICADE & SIGN |
| Mar 5, 2020 | 6356-84-001 | El PasoEl Paso | 200 LF | $40.00 | MIJELUM, L.L.C. |
| Feb 6, 2020 | 6353-33-001 | El PasoEl Paso | 200 LF | $60.00 | LESNA CONSTRUCTION, INC. |
| Feb 6, 2020 | 6353-34-001 | El PasoEl Paso | 500 LF | $20.00 | LESNA CONSTRUCTION, INC. |
| Dec 4, 2019 | 6353-32-001 | El PasoEl Paso | 100 LF | $15.00 | DOUBLE H CONTRACTING INC. |
| Nov 12, 2019 | 6349-85-001 | CulbersonEl Paso | 300 LF | $10.00 | NIXON ENGINEERING |
| Nov 6, 2019 | 0073-07-064 | Live OakCorpus Christi | 660 LF | $100.00 | HUNTER INDUSTRIES, LTD. |
| Aug 7, 2019 | 6344-57-001 | El PasoEl Paso | 100 LF | $20.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Feb 6, 2019 | 6341-01-001 | El PasoEl Paso | 200 LF | $12.54 | SYNERGY PROJECT CONTRACTORS, INC. |
| Feb 6, 2019 | 6341-00-001 | El PasoEl Paso | 500 LF | $12.43 | SYNERGY PROJECT CONTRACTORS, INC. |
| Jan 9, 2019 | 6339-72-001 | El PasoEl Paso | 200 LF | $10.00 | NIXON ENGINEERING |
| Jan 8, 2019 | 6339-71-001 | El PasoEl Paso | 200 LF | $20.00 | APACHE BARRICADE & SIGN |
| Dec 6, 2018 | 6336-70-001 | CulbersonEl Paso | 300 LF | $10.00 | MIJELUM |
| May 2, 2018 | 6330-09-001 | El PasoEl Paso | 300 LF | $25.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| May 1, 2018 | 6330-07-001 | El PasoEl Paso | 600 LF | $10.00 | DAN WILLIAMS COMPANY |
| May 1, 2018 | 6330-08-001 | El PasoEl Paso | 900 LF | $11.00 | DAN WILLIAMS COMPANY |
| Dec 5, 2017 | 6324-50-001 | El PasoEl Paso | 200 LF | $60.00 | LESNA CONSTRUCTION, INC. |
| Dec 5, 2017 | 6324-51-001 | El PasoEl Paso | 300 LF | $60.00 | LESNA CONSTRUCTION, INC. |
| Jun 7, 2017 | 6314-50-001 | El PasoEl Paso | 800 LF | $8.99 | SYNERGY PROJECT CONSULTANTS, INC. |
| Jun 6, 2017 | 6309-17-001 | El PasoEl Paso | 3,000 LF | $25.03 | SYNERGY PROJECT CONSULTANTS, INC. |
| Apr 5, 2017 | 6314-51-001 | El PasoEl Paso | 800 LF | $9.98 | SYNERGY PROJECT CONSULTANTS, INC. |
| Jan 5, 2017 | 6309-13-001 | El PasoEl Paso | 600 LF | $50.00 | LESNA CONSTRUCTION, INC. |
| Jan 5, 2017 | 6309-55-001 | El PasoEl Paso | 600 LF | $50.00 | LESNA CONSTRUCTION, INC. |
| Jan 5, 2017 | 6309-56-001 | CulbersonEl Paso | 600 LF | $1.00 | NIXON ENGINEERING |