$144.83Avg low bid / HR
$139.98Avg of all bids
$127.96Avg engineer's estimate
27Jobs · 338 HR
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 2 | $88.69 | $294.35 |
| 2023 | 4 | 35 | $68.57 | $88.13 |
| 2022 | 1 | 10 | $20.00 | $158.54 |
| 2021 | 5 | 41 | $135.98 | $119.12 |
| 2020 | 2 | 20 | $55.00 | $72.93 |
| 2019 | 8 | 125 | $150.73 | $126.33 |
| 2018 | 4 | 89 | $221.35 | $209.54 |
| 2017 | 2 | 16 | $60.00 | $248.20 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 5, 2024 | 6465-24-001 | El PasoEl Paso | 2 HR | $88.69 | PMI PAVEMENT MARKING, LLC |
| Dec 5, 2023 | 6454-87-001 | El PasoEl Paso | 10 HR | $25.00 | APACHE BARRICADE & SIGN |
| Nov 1, 2023 | 6451-31-001 | El PasoEl Paso | 10 HR | $75.00 | FC TRAFFIC CONTROL, INC. |
| May 4, 2023 | 6428-20-001 | El PasoEl Paso | 5 HR | $30.00 | MIJELUM, L.L.C. |
| Mar 8, 2023 | 6428-18-001 | El PasoEl Paso | 10 HR | $125.00 | TRI STATE ELECTRIC, LTD. |
| Mar 3, 2022 | 6393-56-001 | El PasoEl Paso | 10 HR | $20.00 | MIJELUM, L.L.C. |
| Nov 4, 2021 | 6389-40-001 | El PasoEl Paso | 10 HR | $50.00 | APACHE BARRICADE & SIGN |
| Nov 3, 2021 | 6391-39-001 | El PasoEl Paso | 10 HR | $55.00 | APACHE BARRICADE & SIGN |
| Mar 4, 2021 | 6374-75-001 | El PasoEl Paso | 1 HR | $375.00 | TRI STATE ELECTRIC, LTD. |
| Mar 4, 2021 | 6374-76-001 | El PasoEl Paso | 10 HR | $105.00 | TRI STATE ELECTRIC, LTD. |
| Feb 4, 2021 | 6363-59-001 | El PasoEl Paso | 10 HR | $310.00 | PMI PAVEMENT MARKING, LLC |
| Nov 4, 2020 | 6372-48-001 | El PasoEl Paso | 10 HR | $50.00 | APACHE BARRICADE & SIGN |
| Feb 6, 2020 | 6353-33-001 | El PasoEl Paso | 10 HR | $60.00 | LESNA CONSTRUCTION, INC. |
| Dec 4, 2019 | 6353-32-001 | El PasoEl Paso | 10 HR | $70.00 | DOUBLE H CONTRACTING INC. |
| Aug 7, 2019 | 6344-57-001 | El PasoEl Paso | 20 HR | $190.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| Apr 3, 2019 | 6336-60-001 | El PasoEl Paso | 1 HR | $500.00 | TRI STATE ELECTRIC, LTD. |
| Feb 6, 2019 | 6341-00-001 | El PasoEl Paso | 24 HR | $214.70 | SYNERGY PROJECT CONTRACTORS, INC. |
| Feb 6, 2019 | 6341-01-001 | El PasoEl Paso | 40 HR | $148.20 | SYNERGY PROJECT CONTRACTORS, INC. |
| Jan 9, 2019 | 6339-72-001 | El PasoEl Paso | 10 HR | $1.00 | NIXON ENGINEERING |
| Jan 8, 2019 | 6339-71-001 | El PasoEl Paso | 10 HR | $75.00 | APACHE BARRICADE & SIGN |
| Jan 8, 2019 | 6339-73-001 | El PasoEl Paso | 10 HR | $200.00 | TRI STATE ELECTRIC, LTD. |
| Dec 6, 2018 | 6336-60-001 | El PasoEl Paso | 1 HR | $500.00 | NIXON ENGINEERING |
| May 2, 2018 | 6330-09-001 | El PasoEl Paso | 40 HR | $240.00 | INTERNATIONAL EAGLE ENTERPRISES, INC. |
| May 1, 2018 | 6330-07-001 | El PasoEl Paso | 24 HR | $200.00 | DAN WILLIAMS COMPANY |
| May 1, 2018 | 6330-08-001 | El PasoEl Paso | 24 HR | $200.00 | DAN WILLIAMS COMPANY |
| Dec 5, 2017 | 6324-50-001 | El PasoEl Paso | 10 HR | $60.00 | LESNA CONSTRUCTION, INC. |
| Dec 5, 2017 | 6324-51-001 | El PasoEl Paso | 6 HR | $60.00 | LESNA CONSTRUCTION, INC. |