MATERIAL ONLY DELIVERY OF HMA
- Let date
- Tuesday, April 14, 2020
- CCSJ
- 6359-26-001
- District
- San Antonio
- County
- Bexar
- Highway
- IH 410
- Limits
- VARIOUS LOCATIONS IN_THE EAST BEXAR to MAINTENANCE SECTION
- Classification
- Local Let
- Project number
- MMC - 635926001
- Working days
- 120
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $295,000 | ||
| 1 | CENTURY ASPHALT, LTD. Low bidder | $271,550 | -7.9% | |
| 2 | TEXAS MATERIALS GROUP, INC. | $273,850 | -7.2% | +0.8% |
| 3 | AUSTIN MATERIALS, LLC | $294,000 | -0.3% | +8.3% |
| 4 | VULCAN CONSTRUCTION MATERIALS, LLC | $296,450 | +0.5% | +9.2% |
| 5 | COLORADO MATERIALS, LTD. | $372,000 | +26.1% | +37.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CENTURY ASPHALT… | #2 TEXAS MATERIALS… | #3 AUSTIN MATERIAL… | #4 VULCAN CONSTRUC… | #5 COLORADO MATERI… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 8011-6003 | D-GR HMA(SQ) TY D PG 70-22 (PICKUP) | 150 | TON | $50.00 | $52.00 | $50.00 | $49.00 | $47.00 | $62.00 |
| 2 | 8011-6004 | D-GR HMA(SQ) TY D PG 70-22 (DELIVERY) | 800 | TON | $55.00 | $59.00 | $57.00 | $62.00 | $58.20 | $73.00 |
| 3 | 8011-6014 | D-GR HMA(SQ)TY B PG 64-22 (PICKUP) | 250 | TON | $50.00 | $43.00 | $43.00 | $41.00 | $44.00 | $58.00 |
| 4 | 8011-6015 | D-GR HMA(SQ)TY B PG 64-22(DELIVERY) | 4,200 | TON | $55.00 | $49.00 | $50.00 | $54.00 | $55.20 | $69.00 |