BRIDGE JOINT CLEANING AND SEALING
- Let date
- Tuesday, December 8, 2020
- CCSJ
- 6354-93-001
- District
- Tyler
- County
- Gregg
- Highway
- US 259
- Limits
- VARIOUS LOCATIONS IN to GREGG AND SMITH COUNTIES
- Classification
- Local Let
- Project number
- BPM - 635493001
- Working days
- 60
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $207,353 | ||
| 1 | TALBRAN ENTERPRISES LLC Low bidder | $161,490 | -22.1% | |
| 2 | MAD ENERGY SERVICE LLC | $172,061 | -17.0% | +6.5% |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $174,640 | -15.8% | +8.1% |
| 4 | RED BARON BUILDING COMPANY, LLC | $175,998 | -15.1% | +9.0% |
| 5 | JAMES CONSTRUCTION GROUP, L.L.C. | $219,402 | +5.8% | +35.9% |
| 6 | DBI SERVICES, LLC | $238,842 | +15.2% | +47.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TALBRAN ENTERPR… | #2 MAD ENERGY SERV… | #3 SCR CIVIL CONST… | #4 RED BARON BUILD… | #5 JAMES CONSTRUCT… | #6 DBI SERVICES, L… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 429-6002 | CONC STR REPAIR (EPOXY MORTAR) | 25 | SF | $165.00 | $145.00 | $100.00 | $210.00 | $265.00 | $300.00 | $300.00 |
| 2 | 500-6001 | MOBILIZATION | 1 | LS | $10,000.00 | $93,000.00 | $1.00 | $17,400.00 | $37,975.00 | $20,347.09 | $20,000.00 |
| 3 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO | $4,000.00 | $250.00 | $1.00 | $3,500.00 | $1,500.00 | $6,500.00 | $2,000.00 |
| 4 | 713-6001 | JT SEALING AND CLEANING(TRANS CNTR JTS) | 300 | LF | $36.00 | $15.00 | $39.50 | $25.00 | $22.50 | $20.00 | $55.00 |
| 5 | 713-6004 | JT SEALING AND CLEANING(EXPANSION JTS) | 3,948 | LF | $36.00 | $15.00 | $39.50 | $30.00 | $26.00 | $35.00 | $41.50 |
| 6 | 6001-6001 | PORTABLE CHANGEABLE MESSAGE SIGN | 85 | DAY | $180.00 | $1.00 | $20.00 | $50.00 | $100.00 | $75.00 | $200.00 |
| 7 | 6185-6002 | TMA (STATIONARY) | 60 | DAY | $150.00 | $1.00 | $1.00 | $130.00 | $125.00 | $250.00 | $100.00 |