| 1 | 100-2001 |
PREPARING ROW | 0.56 | AC |
$6,878.99 |
$10,000.00 |
$28,000.00 |
$100,000.00 |
$11,000.00 |
$70,000.00 |
$2,000.00 |
| 2 | 110-2002 |
EXCAVATION (CHANNEL) | 659 | CY |
$4.26 |
$9.00 |
$19.00 |
$25.00 |
$12.40 |
$25.00 |
$12.00 |
| 3 | 132-2004 |
EMBANKMENT (FINAL)(DENS CONT)(TY B) | 5,367 | CY |
$2.65 |
$16.00 |
$20.00 |
$20.00 |
$24.00 |
$20.00 |
$16.00 |
| 4 | 160-2003 |
FURNISHING AND PLACING TOPSOIL (4") | 2,540.07 | SY |
$0.6100 |
$1.75 |
$4.00 |
$2.00 |
$4.00 |
$2.00 |
$5.00 |
| 5 | 162-2002 |
BLOCK SODDING | 2,540.07 | SY |
$2.20 |
$3.00 |
$5.00 |
$5.00 |
$2.80 |
$4.00 |
$8.00 |
| 6 | 166-2001 |
FERTILIZER | 0.56 | AC |
$370.47 |
$400.00 |
$435.00 |
$500.00 |
$1,200.00 |
$400.00 |
$1,000.00 |
| 7 | 168-2001 |
VEGETATIVE WATERING | 95 | MG |
$9.64 |
$20.00 |
$44.00 |
$50.00 |
$60.00 |
$35.00 |
$100.00 |
| 8 | 169-2006 |
SOIL RETENTION BLANKETS (CL 2) (TY F) | 285 | SY |
$0.9200 |
$4.00 |
$2.50 |
$3.00 |
$7.00 |
$3.00 |
$3.00 |
| 9 | 401-2001 |
FLOWABLE BACKFILL | 54.25 | CY |
$58.37 |
$300.00 |
$130.00 |
$150.00 |
$200.00 |
$150.00 |
$250.00 |
| 10 | 402-2001 |
TRENCH EXCAVATION PROTECTION | 300 | LF |
$1.37 |
$1.00 |
$2.50 |
$5.00 |
$6.50 |
$1.00 |
$10.00 |
| 11 | 420-2007 |
CL C CONC (CULV) | 96.1 | CY |
$552.07 |
$500.00 |
$1,500.00 |
$700.00 |
$1,050.00 |
$1,200.00 |
$750.00 |
| 12 | 432-2041 |
RIPRAP (STONE COMMON)(DRY)(18 IN) | 8.88 | CY |
$67.89 |
$100.00 |
$120.00 |
$100.00 |
$81.00 |
$180.00 |
$300.00 |
| 13 | 459-2017 |
GABIONS (3FT X 1.5FT)(PVC) | 0.88 | CY |
$209.83 |
$250.00 |
$550.00 |
$800.00 |
$1,202.00 |
$450.00 |
$2,000.00 |
| 14 | 462-2015 |
CONC BOX CULV (7 FT X 4 FT) | 3.23 | LF |
$258.60 |
$500.00 |
$475.00 |
$800.00 |
$1,400.00 |
$385.00 |
$1,200.00 |
| 15 | 462-2021 |
CONC BOX CULV (8 FT X 6 FT) | 30 | LF |
$415.49 |
$500.00 |
$350.00 |
$400.00 |
$550.00 |
$450.00 |
$750.00 |
| 16 | 462-2029 |
CONC BOX CULV (10 FT X 5 FT) | 350 | LF |
$415.46 |
$500.00 |
$425.00 |
$490.00 |
$567.00 |
$550.00 |
$600.00 |
| 17 | 464-2013 |
RC PIPE (CL III)(60 IN) | 30.44 | LF |
$113.57 |
$200.00 |
$300.00 |
$200.00 |
$350.00 |
$400.00 |
$500.00 |
| 18 | 464-2015 |
RC PIPE (CL III)(72 IN) | 9.7 | LF |
$235.66 |
$300.00 |
$320.00 |
$250.00 |
$490.00 |
$450.00 |
$600.00 |
| 19 | 465-2006 |
MANH (COMPL)(JUNCT BOX)(TY M) | 2 | EA |
$4,329.52 |
$1,000.00 |
$1,450.00 |
$2,000.00 |
$720.00 |
$2,000.00 |
$56,000.00 |
| 20 | 466-2021 |
WINGWALL (FW-0)(HW=5 FT) | 1 | EA |
$5,970.14 |
$5,000.00 |
$7,500.00 |
$15,000.00 |
$5,000.00 |
$8,000.00 |
$5,000.00 |
| 21 | 466-2022 |
WINGWALL (FW-0)(HW=6 FT) | 1 | EA |
$7,512.32 |
$6,000.00 |
$7,000.00 |
$12,000.00 |
$5,400.00 |
$7,000.00 |
$7,000.00 |
| 22 | 500-2001 |
MOBILIZATION | 1 | LS |
$28,629.62 |
$25,000.00 |
$28,000.00 |
$60,000.00 |
$50,000.00 |
$50,000.00 |
$20,000.00 |
| 23 | 502-2001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 | MO |
$3,734.87 |
$3,000.00 |
$4,500.00 |
$2,000.00 |
$1,300.00 |
$500.00 |
$1,500.00 |
| 24 | 1122-2037 |
TEMPORARY SEDIMENT CONTROL FENCE INSTLL | 800 | LF |
$2.09 |
$3.00 |
$6.00 |
$5.00 |
$2.00 |
$3.00 |
$5.00 |
| 25 | 1122-2057 |
TEMPORARY SEDIMENT CONTROL FENCE REMOVE | 800 | LF |
$0.6000 |
$0.1000 |
$0.9000 |
$1.00 |
$0.6500 |
$1.00 |
$1.00 |