Bid tab 0910-16-039

Let Mar 5, 2019 · Tyler · Smith Sign up free

‹ Mar 2019 results

REPLACE BRIDGE & APPROACHES

Let date
Tuesday, March 5, 2019
CCSJ
0910-16-039
District
Tyler
County
Smith
Highway
CS
Limits
N AZALEA DR & CAMELLIA ST to AT W MUD CREEK TRIBUTARY IN TYLER
Classification
Construction
Project number
BR 94(104)
Working days
45

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$497,859
1 EAST TEXAS BRIDGE, INC. Low bidder $469,506 -5.7%
2 LONGVIEW BRIDGE AND ROAD, LTD. $541,094 +8.7% +15.2%
3 HODGES AND SON CONSTRUCTION COMPANY, INC. $548,788 +10.2% +16.9%
4 PIERCE R & B LLC $599,169 +20.3% +27.6%
5 HIGHWAY 19 CONSTRUCTION LLC $649,319 +30.4% +38.3%
6 FNH CONSTRUCTION, LLC $669,044 +34.4% +42.5%
7 STATELINE CONSTRUCTION, LLC $708,539 +42.3% +50.9%
8 RED BARON BUILDING COMPANY, L.L.C. $708,613 +42.3% +50.9%

Bid tab: unit prices 38 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 EAST TEXAS BRID…#2 LONGVIEW BRIDGE…#3 HODGES AND SON …#4 PIERCE R & B LLC#5 HIGHWAY 19 CONS…#6 FNH CONSTRUCTIO…#7 STATELINE CONST…#8 RED BARON BUILD…
1100-6002 PREPARING ROW2STA $800.00 $3,000.00 $1,250.00 $5,000.00 $2,500.00 $5,000.00 $25,000.00 $10,000.00 $800.00
2104-6009 REMOVING CONC (RIPRAP)177SY $19.00 $14.00 $25.00 $20.00 $20.00 $25.00 $20.00 $22.00 $28.00
3104-6022 REMOVING CONC (CURB AND GUTTER)228LF $9.00 $6.00 $11.25 $10.00 $15.00 $10.00 $20.00 $12.00 $10.00
4105-6018 REMOVING STAB BASE AND ASPH PAV (7")187SY $5.00 $8.00 $13.75 $20.00 $27.00 $10.00 $20.00 $19.00 $27.00
5110-6001 EXCAVATION (ROADWAY)69CY $12.00 $18.00 $18.50 $30.00 $54.00 $50.00 $20.00 $100.00 $20.00
6132-6005 EMBANKMENT (FINAL)(ORD COMP)(TY C)3CY $14.00 $50.00 $200.00 $100.00 $105.00 $50.00 $100.00 $1,000.00 $28.00
7160-6003 FURNISHING AND PLACING TOPSOIL (4")228SY $2.25 $5.00 $20.00 $10.00 $5.00 $5.00 $6.00 $8.00 $10.00
8162-6002 BLOCK SODDING228SY $4.00 $7.00 $8.80 $8.00 $9.00 $7.00 $6.00 $8.00 $12.00
9164-6055 BONDED FBR MTRX SEED (TEMP)(WARM)115SY $1.00 $6.00 $11.00 $6.00 $6.00 $6.00 $5.00 $15.00 $10.00
10164-6056 BONDED FBR MTRX SEED (TEMP)(COOL)115SY $1.00 $5.50 $11.00 $6.00 $6.00 $6.00 $5.00 $15.00 $10.00
11168-6001 VEGETATIVE WATERING2.5MG $12.00 $10.00 $25.00 $1.00 $35.00 $100.00 $1,000.00 $10.00 $200.00
12340-6034 D-GR HMA(SQ) TY-C PG64-2219TON $185.00 $270.00 $240.00 $200.00 $465.00 $350.00 $140.00 $600.00 $215.00
13340-6106 D-GR HMA(SQ) TY-D PG64-2296TON $185.00 $170.00 $190.00 $200.00 $235.00 $250.00 $160.00 $445.00 $215.00
14416-6002 DRILL SHAFT (24 IN)744LF $135.00 $149.00 $180.00 $120.00 $165.00 $250.00 $200.00 $185.00 $311.45
15420-6013 CL C CONC (ABUT)54CY $950.00 $830.00 $1,005.00 $1,200.00 $1,100.00 $1,000.00 $800.00 $1,125.00 $450.00
16422-6007 REINF CONC SLAB (SLAB BEAM)2,248SF $20.00 $15.35 $15.50 $22.00 $24.00 $20.00 $15.00 $19.25 $27.00
17422-6013 BRIDGE SIDEWALK558SF $25.00 $20.00 $20.00 $20.00 $26.00 $35.00 $20.00 $46.00 $9.00
18425-6009 PRESTR CONC SLAB BEAM (4SB12)550.76LF $140.00 $145.00 $150.00 $160.00 $135.00 $174.00 $145.00 $185.00 $190.00
19432-6002 RIPRAP (CONC)(5 IN)57CY $600.00 $480.00 $495.00 $500.00 $550.00 $500.00 $550.00 $500.00 $400.00
20432-6003 RIPRAP (CONC)(6 IN)30CY $600.00 $480.00 $525.00 $550.00 $750.00 $500.00 $650.00 $600.00 $450.00
21442-6007 STR STEEL (MISC NON - BRIDGE)398LB $9.00 $15.00 $16.00 $20.00 $20.00 $25.00 $20.00 $85.00 $15.00
22450-6006 RAIL (TY T223)98LF $110.00 $88.00 $95.00 $110.00 $115.00 $60.00 $135.00 $155.00 $175.00
23450-6032 RAIL (TY C223)98LF $120.00 $130.00 $160.00 $120.00 $160.00 $100.00 $150.00 $165.00 $100.00
24496-6009 REMOV STR (BRIDGE 0 - 99 FT LENGTH)2EA $12,000.00 $5,000.00 $8,000.00 $10,000.00 $18,500.00 $10,000.00 $30,000.00 $5,500.00 $20,000.00
25500-6001 MOBILIZATION1LS $45,000.00 $45,000.00 $50,000.00 $48,000.00 $56,000.00 $60,000.00 $60,000.00 $65,000.00 $100,300.00
26502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING4MO $3,000.00 $2,000.00 $2,500.00 $7,600.00 $2,000.00 $5,000.00 $8,500.00 $4,500.00 $2,500.00
27506-6002 ROCK FILTER DAMS (INSTALL) (TY 2)18LF $35.00 $40.00 $44.00 $5.00 $58.00 $75.00 $30.00 $38.00 $40.00
28506-6011 ROCK FILTER DAMS (REMOVE)18LF $10.00 $10.00 $16.50 $1.00 $25.00 $10.00 $15.00 $12.00 $15.00
29506-6030 BACKHOE WORK (EROSION & SEDMT CONT)20HR $100.00 $40.00 $250.00 $5.00 $75.00 $50.00 $150.00 $55.00 $60.00
30506-6038 TEMP SEDMT CONT FENCE (INSTALL)110LF $3.00 $4.00 $5.50 $1.00 $6.00 $3.00 $4.00 $3.00 $5.00
31506-6039 TEMP SEDMT CONT FENCE (REMOVE)110LF $1.00 $1.00 $2.20 $1.00 $1.50 $1.00 $2.00 $1.00 $2.00
32506-6042 BIODEG EROSN CONT LOGS (INSTL) (18")91LF $6.00 $5.00 $5.50 $5.00 $10.00 $5.00 $18.00 $8.00 $5.00
33506-6043 BIODEG EROSN CONT LOGS (REMOVE)91LF $1.50 $2.00 $1.10 $1.00 $3.00 $1.00 $10.00 $2.00 $1.00
34529-6002 CONC CURB (TY II)30LF $18.00 $17.00 $40.00 $60.00 $75.00 $50.00 $25.00 $46.00 $22.00
35529-6008 CONC CURB & GUTTER (TY II)202LF $24.00 $32.00 $45.00 $40.00 $40.00 $50.00 $35.00 $65.00 $28.00
36531-6013 CURB RAMPS (TY 10)4EA $2,000.00 $1,500.00 $1,650.00 $2,500.00 $2,500.00 $1,800.00 $2,000.00 $3,500.00 $500.00
37658-6053 INSTL OM ASSM (OM-3L)(TWT)GND4EA $210.00 $260.00 $330.00 $100.00 $250.00 $45.00 $100.00 $55.00 $500.00
38658-6057 INSTL OM ASSM (OM-3R)(TWT)GND4EA $210.00 $260.00 $330.00 $100.00 $250.00 $45.00 $100.00 $55.00 $250.00