BRIDGE MAINTENANCE
- Let date
- Wednesday, August 7, 2019
- CCSJ
- 0508-04-176
- District
- Beaumont
- County
- Jefferson
- Highway
- SH 73
- Limits
- VARIOUS to VARIOUS
- Classification
- Construction
- Project number
- NH 1902(358)
- Working days
- 26
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $120,808 | ||
| 1 | CHAMPION INFRASTRUCTURE, LLC Low bidder | $113,770 | -5.8% | |
| 2 | TEXAS MATERIALS GROUP, INC. | $144,687 | +19.8% | +27.2% |
| 3 | FNH CONSTRUCTION, LLC | $191,800 | +58.8% | +68.6% |
| 4 | FUQUA CONSTRUCTION CO., INC. | $436,382 | +261.2% | +283.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CHAMPION INFRAS… | #2 TEXAS MATERIALS… | #3 FNH CONSTRUCTIO… | #4 FUQUA CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 104-6009 | REMOVING CONC (RIPRAP) | 35 | SY | $15.00 | $60.00 | $130.00 | $100.00 | |
| 2 | 110-6002 | EXCAVATION (CHANNEL) | 15 | CY | $15.00 | $70.00 | $695.00 | $100.00 | |
| 3 | 401-6001 | FLOWABLE BACKFILL | 3 | CY | $350.00 | $340.00 | $1,560.00 | $350.00 | |
| 4 | 420-6070 | CL C CONC (PILE ENCASEMENT) | 18.2 | CY | $4,800.00 | $3,200.00 | $4,340.00 | $5,000.00 | |
| 5 | 432-6006 | RIPRAP (CONC)(CL B) | 6 | CY | $600.00 | $780.00 | $1,125.00 | $1,000.00 | |
| 6 | 438-6001 | CLEANING AND SEALING EXISTING JOINTS | 414 | LF | $18.00 | $45.00 | $11.00 | $100.00 | |
| 7 | 500-6001 | MOBILIZATION | 1 | LS | $10,346.00 | $15,000.00 | $21,300.00 | $20,000.00 | |
| 8 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $3,500.00 | $3,500.00 | $3,200.00 | $8,500.00 | |
| 9 | 506-6041 | BIODEG EROSN CONT LOGS (INSTL) (12") | 200 | LF | $4.00 | $8.00 | $6.70 | $18.00 | |
| 10 | 506-6043 | BIODEG EROSN CONT LOGS (REMOVE) | 200 | LF | $1.00 | $2.00 | $1.50 | $9.00 | |
| 11 | 6185-6002 | TMA (STATIONARY) | 9 | DAY | $250.00 | $450.00 | $600.00 | $550.00 |