| 1 | 100-6002 |
PREPARING ROW | 117 | STA |
$4,239.10 |
$4,500.00 |
$1,000.00 |
$2,100.00 |
$1,000.00 |
$5,500.00 |
| 2 | 105-6168 |
REMOVING STAB BASE & ASP PAV (18"-24") | 15,100 | SY |
$21.00 |
$17.00 |
$10.00 |
$12.00 |
$38.00 |
$30.00 |
| 3 | 110-6001 |
EXCAVATION (ROADWAY) | 14,865 | CY |
$20.00 |
$15.00 |
$5.25 |
$23.00 |
$40.00 |
$20.00 |
| 4 | 132-6006 |
EMBANKMENT (FINAL)(DENS CONT)(TY C) | 6,452 | CY |
$32.00 |
$10.00 |
$10.50 |
$28.00 |
$52.00 |
$50.00 |
| 5 | 134-6004 |
BACKFILL (TY A OR B) | 117 | STA |
$456.50 |
$460.00 |
$525.00 |
$255.00 |
$440.00 |
$450.00 |
| 6 | 152-6001 |
ROAD GRADER WORK (ORD COMP) | 117 | STA |
$379.00 |
$300.00 |
$525.00 |
$246.00 |
$100.00 |
$250.00 |
| 7 | 161-6017 |
COMPOST MANUF TOPSOIL (4") | 34,570 | SY |
$2.00 |
$1.05 |
$1.50 |
$1.35 |
$2.60 |
$8.00 |
| 8 | 164-6035 |
DRILL SEEDING (PERM) (RURAL) (CLAY) | 34,570 | SY |
$1.00 |
$0.3500 |
$0.3600 |
$0.2800 |
$0.1800 |
$1.00 |
| 9 | 164-6051 |
DRILL SEED (TEMP)(WARM OR COOL) | 34,570 | SY |
$0.3000 |
$0.3400 |
$0.3400 |
$0.2200 |
$0.1600 |
$1.00 |
| 10 | 168-6001 |
VEGETATIVE WATERING | 5,292 | MG |
$20.00 |
$29.00 |
$2.10 |
$0.0100 |
$1.00 |
$30.00 |
| 11 | 247-6304 |
FL BS (CMP IN PLACE) (TY D GR 1-2)(10") | 32,400 | SY |
$27.00 |
$18.00 |
$35.00 |
$33.00 |
$42.00 |
$28.00 |
| 12 | 260-6002 |
LIME (HYDRATED LIME (SLURRY)) | 570 | TON |
$320.00 |
$325.00 |
$375.00 |
$370.00 |
$380.00 |
$450.00 |
| 13 | 260-6006 |
LIME TRT (EXST MATL) (6") | 32,400 | SY |
$4.00 |
$7.00 |
$5.25 |
$9.50 |
$7.00 |
$8.00 |
| 14 | 310-6028 |
PRIME COAT (MC-30 OR EC-30) | 6,489 | GAL |
$7.00 |
$5.85 |
$6.60 |
$5.00 |
$8.00 |
$10.00 |
| 15 | 354-6002 |
PLAN & TEXT ASPH CONC PAV(0" TO 2") | 2,318 | SY |
$15.00 |
$5.00 |
$7.35 |
$5.35 |
$8.00 |
$20.00 |
| 16 | 467-6395 |
SET (TY II) (24 IN) (RCP) (6: 1) (P) | 6 | EA |
$2,150.00 |
$4,000.00 |
$3,150.00 |
$4,000.00 |
$2,100.00 |
$2,500.00 |
| 17 | 496-6001 |
REMOV STR (BOX CULVERT) | 1 | EA |
$8,000.00 |
$6,000.00 |
$5,250.00 |
$6,000.00 |
$6,500.00 |
$5,000.00 |
| 18 | 496-6006 |
REMOV STR (HEADWALL) | 2 | EA |
$2,500.00 |
$4,000.00 |
$4,200.00 |
$1,800.00 |
$3,300.00 |
$5,000.00 |
| 19 | 500-6001 |
MOBILIZATION | 1 | LS |
$545,572.00 |
$550,000.00 |
$538,000.00 |
$650,499.00 |
$400,000.00 |
$700,000.00 |
| 20 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 | MO |
$15,000.00 |
$4,000.00 |
$26,250.00 |
$22,000.00 |
$7,000.00 |
$8,500.00 |
| 21 | 506-6002 |
ROCK FILTER DAMS (INSTALL) (TY 2) | 440 | LF |
$40.00 |
$40.00 |
$53.03 |
$56.00 |
$45.00 |
$30.00 |
| 22 | 506-6011 |
ROCK FILTER DAMS (REMOVE) | 440 | LF |
$11.00 |
$12.00 |
$23.10 |
$21.00 |
$16.00 |
$15.00 |
| 23 | 506-6020 |
CONSTRUCTION EXITS (INSTALL) (TY 1) | 560 | SY |
$32.00 |
$45.00 |
$16.00 |
$46.00 |
$10.00 |
$40.00 |
| 24 | 506-6024 |
CONSTRUCTION EXITS (REMOVE) | 560 | SY |
$12.00 |
$12.00 |
$8.00 |
$15.00 |
$5.00 |
$20.00 |
| 25 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 1,634 | LF |
$6.00 |
$5.00 |
$3.26 |
$5.50 |
$4.50 |
$4.00 |
| 26 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 1,634 | LF |
$2.00 |
$1.00 |
$1.05 |
$1.40 |
$0.6000 |
$2.00 |
| 27 | 506-6042 |
BIODEG EROSN CONT LOGS (INSTL) (18") | 200 | LF |
$11.00 |
$8.00 |
$6.83 |
$11.00 |
$6.50 |
$18.00 |
| 28 | 506-6043 |
BIODEG EROSN CONT LOGS (REMOVE) | 200 | LF |
$5.00 |
$1.25 |
$1.31 |
$4.00 |
$1.00 |
$9.00 |
| 29 | 508-6001 |
CONSTRUCTING DETOURS | 1,563 | SY |
$100.00 |
$200.00 |
$157.50 |
$145.00 |
$140.00 |
$75.00 |
| 30 | 533-6005 |
RUMBLE STRIPS (SHOULDER) CONCRETE | 386 | LF |
$0.7500 |
$9.00 |
$10.00 |
$6.00 |
$13.00 |
$10.00 |
| 31 | 536-6004 |
CONC DIRECTIONAL ISLAND | 295 | SY |
$450.00 |
$45.00 |
$126.00 |
$160.00 |
$175.00 |
$150.00 |
| 32 | 644-6001 |
IN SM RD SN SUP&AM TY10BWG(1)SA(P) | 36 | EA |
$750.00 |
$671.72 |
$787.50 |
$700.00 |
$700.00 |
$1,500.00 |
| 33 | 644-6004 |
IN SM RD SN SUP&AM TY10BWG(1)SA(T) | 4 | EA |
$895.00 |
$762.63 |
$840.00 |
$800.00 |
$850.00 |
$1,500.00 |
| 34 | 644-6007 |
IN SM RD SN SUP&AM TY10BWG(1)SA(U) | 1 | EA |
$1,000.00 |
$959.60 |
$892.50 |
$1,000.00 |
$1,100.00 |
$1,500.00 |
| 35 | 644-6009 |
IN SM RD SN SUP&AM TY10BWG(1)SB(P) | 6 | EA |
$830.80 |
$722.22 |
$945.00 |
$635.00 |
$700.00 |
$1,500.00 |
| 36 | 644-6113 |
REMOVE SM RD SN (FOUNDATION ONLY) | 32 | EA |
$110.00 |
$116.16 |
$262.50 |
$135.00 |
$130.00 |
$200.00 |
| 37 | 662-6064 |
WK ZN PAV MRK REMOV (W)6"(BRK) | 4,813 | LF |
$2.00 |
$0.8800 |
$2.10 |
$0.9000 |
$0.9000 |
$3.00 |
| 38 | 662-6067 |
WK ZN PAV MRK REMOV (W)6"(SLD) | 20,846 | LF |
$1.50 |
$0.8300 |
$1.84 |
$0.8500 |
$0.8500 |
$2.00 |
| 39 | 662-6075 |
WK ZN PAV MRK REMOV (W)24"(SLD) | 12 | LF |
$10.40 |
$7.29 |
$21.00 |
$7.35 |
$7.50 |
$20.00 |
| 40 | 662-6098 |
WK ZN PAV MRK REMOV (Y)6"(SLD) | 22,119 | LF |
$2.00 |
$0.8300 |
$1.84 |
$0.8600 |
$0.8500 |
$2.00 |
| 41 | 666-6062 |
REFL PAV MRK TY I(W)(UTURN ARW)(090MIL) | 10 | EA |
$205.50 |
$260.26 |
$288.75 |
$275.00 |
$270.00 |
$300.00 |
| 42 | 666-6101 |
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL) | 3 | EA |
$70.00 |
$72.87 |
$210.00 |
$75.00 |
$75.00 |
$250.00 |
| 43 | 666-6225 |
PAVEMENT SEALER 6" | 57,516 | LF |
$0.8000 |
$0.2100 |
$0.3200 |
$0.2100 |
$0.2000 |
$0.5000 |
| 44 | 666-6226 |
PAVEMENT SEALER 8" | 9,867 | LF |
$0.7400 |
$0.3100 |
$0.5300 |
$0.3200 |
$0.3000 |
$0.6500 |
| 45 | 666-6230 |
PAVEMENT SEALER 24" | 16,582 | LF |
$2.35 |
$1.77 |
$2.89 |
$1.80 |
$1.70 |
$3.00 |
| 46 | 666-6231 |
PAVEMENT SEALER (ARROW) | 15 | EA |
$45.00 |
$33.31 |
$78.75 |
$34.00 |
$32.00 |
$300.00 |
| 47 | 666-6232 |
PAVEMENT SEALER (WORD) | 10 | EA |
$50.00 |
$40.60 |
$131.25 |
$41.00 |
$39.00 |
$250.00 |
| 48 | 666-6236 |
PAVEMENT SEALER (UTURN ARROW) | 10 | EA |
$35.00 |
$49.97 |
$157.50 |
$51.00 |
$48.00 |
$250.00 |
| 49 | 666-6243 |
PAVEMENT SEALER (YLD TRI) | 3 | EA |
$20.00 |
$14.31 |
$105.00 |
$15.00 |
$14.00 |
$250.00 |
| 50 | 666-6257 |
RE PM TY I(W)6"(BRK)(090MIL)(CALLOUT) | 5,538 | LF |
$0.6500 |
$0.7700 |
$0.7900 |
$0.7800 |
$0.8000 |
$1.00 |
| 51 | 666-6258 |
RE PM TY I(W)6"(SLD)(090MIL)(CALLOUT) | 24,462 | LF |
$0.6500 |
$0.7300 |
$0.7400 |
$0.7400 |
$0.7500 |
$1.00 |
| 52 | 666-6259 |
RE PM TY I(W)8"(SLD)(090MIL)(CALLOUT) | 9,867 | LF |
$0.8500 |
$1.07 |
$1.26 |
$1.10 |
$1.10 |
$1.50 |
| 53 | 666-6265 |
RE PM TY I(W)24"(SLD)(090MIL)(CALLOUT) | 48 | LF |
$7.50 |
$10.41 |
$7.88 |
$10.70 |
$10.00 |
$8.00 |
| 54 | 666-6267 |
RE PM TY I(W)(ARROW)(090MIL)(CALLOUT) | 15 | EA |
$97.50 |
$193.63 |
$157.50 |
$193.00 |
$186.00 |
$250.00 |
| 55 | 666-6273 |
RE PM TY I(W)(WORD)(090MIL)(CALLOUT) | 10 | EA |
$125.00 |
$237.36 |
$199.50 |
$240.00 |
$230.00 |
$250.00 |
| 56 | 666-6279 |
RE PM TY I(Y)24"(SLD)(090MIL)(CALLOUT) | 16,534 | LF |
$6.75 |
$7.55 |
$4.52 |
$7.65 |
$7.50 |
$5.00 |
| 57 | 666-6289 |
REF PROF PAV MRK TY I(Y)6"(SLD)(090MIL) | 27,516 | LF |
$1.20 |
$1.41 |
$1.58 |
$1.42 |
$1.40 |
$2.00 |
| 58 | 672-6009 |
REFL PAV MRKR TY II-A-A | 25 | EA |
$7.00 |
$5.21 |
$6.30 |
$5.45 |
$5.00 |
$6.00 |
| 59 | 672-6010 |
REFL PAV MRKR TY II-C-R | 220 | EA |
$5.25 |
$5.21 |
$6.30 |
$5.45 |
$5.00 |
$6.00 |
| 60 | 677-6002 |
ELIM EXT PAV MRK & MRKS (6") | 98,317 | LF |
$1.00 |
$0.8300 |
$0.7100 |
$0.9000 |
$0.8000 |
$1.00 |
| 61 | 730-6107 |
FULL - WIDTH MOWING | 3 | CYC |
$6,400.00 |
$10,000.00 |
$10,000.00 |
$2,900.00 |
$2,800.00 |
$5,000.00 |
| 62 | 3077-6001 |
SP MIXES SP-B PG64-22 | 6,338 | TON |
$150.00 |
$145.00 |
$144.00 |
$145.00 |
$172.00 |
$140.00 |
| 63 | 3077-6023 |
SP MIXES SP-C SAC-B PG70-22 | 3,462 | TON |
$155.00 |
$150.00 |
$142.00 |
$165.00 |
$186.00 |
$200.00 |
| 64 | 3077-6075 |
TACK COAT | 2,004 | GAL |
$5.00 |
$2.00 |
$2.35 |
$4.50 |
$7.00 |
$10.00 |
| 65 | 4216-6002 |
THERMOPLASTIC PIPE (PP) (24") | 608 | LF |
$40.00 |
$78.73 |
$63.00 |
$150.00 |
$80.00 |
$250.00 |
| 66 | 6185-6005 |
TMA (MOBILE OPERATION) | 15 | DAY |
$500.00 |
$908.59 |
$1,155.00 |
$435.00 |
$200.00 |
$250.00 |