FY25 Leon HMA - 06
- Let date
- Tuesday, June 10, 2025
- CCSJ
- 6483-78-001
- District
- Bryan
- County
- Leon
- Highway
- IH0045
- Limits
- Various to Various
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00215287
- Working days
- 180
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $606,000 | ||
| 1 | BIG CREEK CONSTRUCTION, LTD. Low bidder | $539,000 | -11.1% | |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $560,000 | -7.6% | +3.9% |
| 3 | TEXAS MATERIALS GROUP, INC. | $670,750 | +10.7% | +24.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BIG CREEK CONST… | #2 KNIFE RIVER COR… | #3 TEXAS MATERIALS… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8011-7055 | D-GR HMA TY D PG 64-22 (PICKUP) | 1,000 | TON | $90.00 | $82.00 | $78.50 | $83.70 |
| 2 | 8011-7056 | D-GR HMA TY D PG 64-22 (DEL) SITE 1 | 2,000 | TON | $110.00 | $93.00 | $98.50 | $115.75 |
| 3 | 8011-7091 | D-GR HMA TY F PG 64-22 (PICKUP) | 1,000 | TON | $86.00 | $83.00 | $81.50 | $97.15 |
| 4 | 8011-7092 | D-GR HMA TY F PG 64-22 (DEL) SITE 1 | 2,000 | TON | $105.00 | $94.00 | $101.50 | $129.20 |