$33.29Avg low bid / HR
$69.92Avg of all bids
$61.49Avg engineer's estimate
80Jobs · 32,270 HR
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 5 | 2,616 | $16.22 | $52.74 |
| 2023 | 9 | 5,534 | $11.70 | $63.00 |
| 2022 | 7 | 1,839 | $107.56 | $157.18 |
| 2021 | 6 | 4,518 | $27.95 | $62.47 |
| 2020 | 12 | 2,354 | $33.46 | $56.97 |
| 2019 | 12 | 3,732 | $44.59 | $88.81 |
| 2018 | 10 | 5,380 | $17.33 | $61.96 |
| 2017 | 18 | 5,337 | $40.86 | $62.66 |
| 2016 | 1 | 960 | $90.00 | $70.00 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 3, 2024 | 6463-00-001 | EctorOdessa | 250 HR | $50.00 | FC TRAFFIC CONTROL, INC. |
| May 3, 2024 | 6463-01-001 | PecosOdessa | 250 HR | $60.00 | FC TRAFFIC CONTROL, INC. |
| May 3, 2024 | 6463-02-001 | MidlandOdessa | 250 HR | $45.00 | FC TRAFFIC CONTROL, INC. |
| May 3, 2024 | 6466-30-001 | Tom GreenSan Angelo | 1,860 HR | $1.75 | ROSS SA ENTERPRISE LLC |
| Apr 5, 2024 | 6462-52-001 | DallasDallas | 6 HR | $71.00 | AWP SAFETY |
| Dec 6, 2023 | 6452-11-001 | HarrisHouston | 12 HR | $75.00 | PROFESSIONAL TRAFFIC CONTROL LLC |
| Dec 5, 2023 | 6450-09-001 | DallasDallas | 12 HR | $41.00 | AWP SAFETY |
| May 5, 2023 | 6436-76-001 | PecosOdessa | 250 HR | $53.00 | NIXON ENGINEERING |
| May 5, 2023 | 6436-80-001 | EctorOdessa | 200 HR | $50.00 | NIXON ENGINEERING |
| Feb 2, 2023 | 6420-75-001 | Tom GreenSan Angelo | 1,860 HR | $5.00 | ROSS SA ENTERPRISE LLC |
| Feb 2, 2023 | 6432-30-001 | LubbockLubbock | 1,200 HR | $5.00 | BARRICADES UNLIMITED |
| Feb 2, 2023 | 6432-32-001 | HaleLubbock | 800 HR | $1.00 | FC TRAFFIC CONTROL, INC. |
| Feb 1, 2023 | 6432-28-001 | LambLubbock | 400 HR | $20.00 | FC TRAFFIC CONTROL, INC. |
| Feb 1, 2023 | 6432-26-001 | TerryLubbock | 800 HR | $20.00 | FC TRAFFIC CONTROL, INC. |
| Dec 2, 2022 | 6416-34-001 | DallasDallas | 12 HR | $70.00 | FC TRAFFIC CONTROL, INC. |
| Dec 1, 2022 | 6416-32-001 | DallasDallas | 6 HR | $50.00 | FC TRAFFIC CONTROL, INC. |
| Nov 3, 2022 | 6418-41-001 | HarrisHouston | 6 HR | $285.00 | REPUBLIC TRAFFIC SAFETY, INC. |
| Nov 3, 2022 | 6420-99-001 | BosqueWaco | 1,500 HR | $120.00 | STATEWIDE SAFETY SYSTEMS |
| Jun 30, 2022 | 6407-21-001 | MidlandOdessa | 300 HR | $45.00 | FC TRAFFIC CONTROL, INC. |
| Jun 14, 2022 | 6402-21-001 | HarrisHouston | 10 HR | $70.00 | REPUBLIC TRAFFIC SAFETY, INC. |
| Apr 6, 2022 | 6395-26-001 | HarrisHouston | 5 HR | $150.00 | REPUBLIC TRAFFIC SAFETY, INC. |
| Dec 2, 2021 | 6389-97-001 | DallasDallas | 12 HR | $100.00 | STATEWIDE SAFETY SYSTEMS |
| Dec 2, 2021 | 6392-49-001 | Tom GreenSan Angelo | 2,500 HR | $25.00 | ELITE CASTLE RESOURCES LLC |
| Dec 1, 2021 | 6389-96-001 | DallasDallas | 6 HR | $350.00 | SELECT MAINTENANCE, L.L.C. |
| Nov 3, 2021 | 6389-00-001 | BosqueWaco | 1,500 HR | $20.00 | ELITE CASTLE RESOURCES LLC |
| Mar 5, 2021 | 6376-39-001 | PecosOdessa | 300 HR | $85.00 | BARRICADES UNLIMITED |
| Mar 5, 2021 | 6376-27-001 | EctorOdessa | 200 HR | $25.00 | BARRICADES UNLIMITED |
| Dec 3, 2020 | 6373-84-001 | DallasDallas | 12 HR | $74.60 | BARRICADES UNLIMITED |
| Dec 2, 2020 | 6373-39-001 | HaleLubbock | 350 HR | $10.00 | BARRICADES UNLIMITED |
| Dec 2, 2020 | 6373-83-001 | DallasDallas | 12 HR | $150.00 | STATEWIDE SAFETY SYSTEMS |
| Dec 2, 2020 | 6373-36-001 | TerryLubbock | 350 HR | $1.00 | BARRICADES UNLIMITED |
| Dec 2, 2020 | 6373-37-001 | LambLubbock | 350 HR | $10.00 | BARRICADES UNLIMITED |
| Dec 2, 2020 | 6373-38-001 | LubbockLubbock | 350 HR | $1.00 | BARRICADES UNLIMITED |
| Oct 1, 2020 | 6366-76-001 | DallasDallas | 16 HR | $155.00 | STATEWIDE SAFETY SYSTEMS |
| Oct 1, 2020 | 6366-75-001 | DallasDallas | 16 HR | $150.00 | STATEWIDE SAFETY SYSTEMS |
| Jun 4, 2020 | 6362-22-001 | MidlandOdessa | 300 HR | $100.00 | BARRICADES UNLIMITED |
| May 8, 2020 | 6351-83-001 | HarrisHouston | 258 HR | $20.00 | BATTERSON, LLP |
| Apr 9, 2020 | 6354-03-001 | HarrisHouston | 40 HR | $240.00 | ISI CONTRACTING, INC. |
| Jan 9, 2020 | 6352-29-001 | BosqueWaco | 300 HR | $62.40 | AREA WIDE PROTECTIVE, INC. |
| Oct 2, 2019 | 6350-20-001 | RunnelsSan Angelo | 2,500 HR | $40.00 | NIXON ENGINEERING |
| Sep 6, 2019 | 6344-77-001 | DallasDallas | 16 HR | $93.74 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Sep 5, 2019 | 6344-76-001 | DallasDallas | 16 HR | $93.74 | TOTAL HIGHWAY MAINTENANCE, LLC |
| Jul 10, 2019 | 6346-63-001 | BrazosBryan | 60 HR | $20.00 | NIXON ENGINEERING |
| Jul 10, 2019 | 6346-62-001 | WashingtonBryan | 60 HR | $20.00 | NIXON ENGINEERING |
| May 8, 2019 | 6344-40-001 | EctorOdessa | 200 HR | $50.00 | BARRICADES UNLIMITED |
| May 8, 2019 | 6344-67-001 | MidlandOdessa | 200 HR | $50.00 | BARRICADES UNLIMITED |
| May 8, 2019 | 6344-68-001 | PecosOdessa | 200 HR | $85.00 | BARRICADES UNLIMITED |
| Feb 6, 2019 | 6342-06-001 | HaleLubbock | 120 HR | $50.00 | BARRICADES UNLIMITED |
| Feb 6, 2019 | 6342-07-001 | LambLubbock | 120 HR | $50.00 | BARRICADES UNLIMITED |
| Feb 6, 2019 | 6342-05-001 | LubbockLubbock | 120 HR | $50.00 | BARRICADES UNLIMITED |
| Feb 6, 2019 | 6342-08-001 | TerryLubbock | 120 HR | $50.00 | BARRICADES UNLIMITED |
| Dec 6, 2018 | 6332-83-001 | BosqueWaco | 300 HR | $59.00 | AREA WIDE PROTECTIVE, INC. |
| Nov 7, 2018 | 6333-46-001 | HillWaco | 48 HR | $5.00 | CROSS PLUS CONSTRUCTION, LLC |
| Oct 3, 2018 | 6336-66-001 | RunnelsSan Angelo | 2,500 HR | $1.00 | NIXON ENGINEERING |
| Sep 7, 2018 | 6332-53-001 | DallasDallas | 16 HR | $65.32 | ALTUS TRAFFIC MANAGEMENT LLC |
| Sep 7, 2018 | 6332-83-001 | BosqueWaco | 900 HR | $0.1000 | NIXON ENGINEERING |
| Sep 6, 2018 | 6331-56-001 | DallasDallas | 16 HR | $78.90 | AREA WIDE PROTECTIVE, INC. |
| Apr 4, 2018 | 6325-88-001 | HarrisHouston | 100 HR | $200.00 | BATTERSON, LLP |
| Apr 3, 2018 | 6323-01-001 | WalkerBryan | 500 HR | $24.49 | AREA WIDE PROTECTIVE, INC. |
| Apr 3, 2018 | 6328-48-001 | MidlandOdessa | 500 HR | $40.00 | BARRICADES UNLIMITED |
| Feb 1, 2018 | 6323-03-001 | BrazosBryan | 500 HR | $36.33 | AREA WIDE PROTECTIVE, INC. |
| Dec 5, 2017 | 6317-30-001 | PecosOdessa | 500 HR | $95.00 | BARRICADES UNLIMITED |
| Nov 7, 2017 | 6319-58-001 | CollinDallas | 40 HR | $69.29 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 3, 2017 | 6315-22-001 | DallasDallas | 16 HR | $65.71 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 2, 2017 | 6323-02-001 | WashingtonBryan | 500 HR | $121.54 | ALTUS TRAFFIC MANAGEMENT LLC |
| Nov 2, 2017 | 6315-21-001 | DallasDallas | 16 HR | $64.78 | ALTUS TRAFFIC MANAGEMENT LLC |
| Sep 14, 2017 | 6320-66-001 | El PasoEl Paso | 30 HR | $34.50 | KEGLEY, INC. |
| Sep 7, 2017 | 6317-15-001 | El PasoEl Paso | 200 HR | $1.00 | VIZCAINO, L.P. |
| Aug 31, 2017 | 6321-61-001 | CulbersonEl Paso | 180 HR | $0.0100 | CHAMPION INFRASTRUCTURE, LLC |
| Aug 31, 2017 | 6321-62-001 | Jeff DavisEl Paso | 240 HR | $0.0100 | CHAMPION INFRASTRUCTURE, LLC |
| Aug 31, 2017 | 6321-48-001 | El PasoEl Paso | 150 HR | $0.0100 | CHAMPION INFRASTRUCTURE, LLC |
| Aug 10, 2017 | 6317-05-001 | El PasoEl Paso | 30 HR | $26.45 | KEGLEY, INC. |
| Aug 10, 2017 | 6317-16-001 | El PasoEl Paso | 120 HR | $26.45 | KEGLEY, INC. |
| Jul 12, 2017 | 6318-15-001 | BosqueWaco | 1,350 HR | $10.00 | NIXON ENGINEERING |
| Jun 6, 2017 | 6309-17-001 | El PasoEl Paso | 120 HR | $76.86 | SYNERGY PROJECT CONSULTANTS, INC. |
| Jan 5, 2017 | 6308-54-001 | El PasoEl Paso | 45 HR | $45.00 | TRI STATE ELECTRIC, LTD. |
| Jan 5, 2017 | 6309-13-001 | El PasoEl Paso | 750 HR | $45.00 | LESNA CONSTRUCTION, INC. |
| Jan 5, 2017 | 6309-55-001 | El PasoEl Paso | 750 HR | $45.00 | LESNA CONSTRUCTION, INC. |
| Jan 5, 2017 | 6309-56-001 | CulbersonEl Paso | 300 HR | $25.00 | NIXON ENGINEERING |
| Nov 4, 2016 | 6309-71-001 | RunnelsSan Angelo | 960 HR | $90.00 | BARRICADES UNLIMITED |