$410.34Avg low bid / CY
$451.26Avg of all bids
$377.12Avg engineer's estimate
7Jobs · 322.3 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2013 | 7 | 322.3 | $410.34 | $451.26 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 9, 2013 | 0888-01-020 | HillWaco | 68 CY | $365.00 | KNIFE RIVER CORPORATION - SOUTH |
| Oct 8, 2013 | 3136-01-172 | TravisAustin | 19 CY | $650.00 | AUSTIN BRIDGE & ROAD, LP |
| Oct 8, 2013 | 0053-12-057 | NolanAbilene | 23.1 CY | $453.45 | PRICE CONSTRUCTION, LTD. |
| Sep 11, 2013 | 0534-01-019 | RandallAmarillo | 42 CY | $500.00 | DCI CONTRACTING, INC. |
| Sep 11, 2013 | 0867-03-026 | CoryellWaco | 125 CY | $370.00 | KNIFE RIVER CORPORATION - SOUTH |
| Sep 11, 2013 | 0047-18-068 | GraysonParis | 19 CY | $320.00 | RAGLE CONSTRUCTION, INC. |
| Sep 11, 2013 | 0700-04-045 | LlanoAustin | 26.2 CY | $430.50 | ALLEN KELLER COMPANY |