$133.56Avg low bid / SY
$133.42Avg of all bids
$117.62Avg engineer's estimate
8Jobs · 2,828 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 374 | $279.00 | $252.00 |
| 2021 | 2 | 1,025 | $124.24 | $147.26 |
| 2020 | 1 | 180 | $96.00 | $154.07 |
| 2019 | 1 | 600 | $67.13 | $99.04 |
| 2018 | 2 | 479 | $135.01 | $106.65 |
| 2017 | 1 | 170 | $140.00 | $114.83 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 2, 2024 | 0179-04-104 | MatagordaYoakum | 374 SY | $279.00 | MORTMARA CONSTRUCTION, INC. |
| Dec 1, 2021 | 2740-02-016 | LubbockLubbock | 557 SY | $111.00 | WEBBER, LLC |
| Sep 2, 2021 | 0675-07-097 | WalkerBryan | 468 SY | $140.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Sep 4, 2020 | 2399-01-074 | BrazosBryan | 180 SY | $96.00 | KNIFE RIVER CORPORATION - SOUTH |
| Feb 5, 2019 | 0880-04-032 | LubbockLubbock | 600 SY | $67.13 | ALLEN BUTLER CONSTRUCTION, INC. |
| Jun 6, 2018 | 0100-05-184 | KarnesCorpus Christi | 129 SY | $119.92 | RELMCO, INC. |
| May 1, 2018 | 0025-02-160 | BexarSan Antonio | 350 SY | $140.57 | WEBBER, LLC |
| Aug 9, 2017 | 0675-03-081 | LeonBryan | 170 SY | $140.00 | BIG CREEK CONSTRUCTION, LTD. |