$79.38Avg low bid / TON
$84.00Avg of all bids
$81.40Avg engineer's estimate
10Jobs · 61,305 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2019 | 2 | 11,045 | $99.14 | $102.02 |
| 2018 | 4 | 17,154 | $84.69 | $90.82 |
| 2017 | 4 | 33,106 | $70.03 | $72.79 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 3, 2019 | 0456-01-047 | FreestoneBryan | 1,531 TON | $100.00 | KNIFE RIVER CORPORATION - SOUTH |
| Jun 4, 2019 | 3190-01-012 | KaufmanDallas | 9,514 TON | $99.00 | FOUTSCO PAVING COMPANY, LLC |
| Aug 7, 2018 | 0540-05-048 | BrazosBryan | 1,548 TON | $90.00 | GLENN FUQUA, INC. |
| May 1, 2018 | 1394-02-026 | EllisDallas | 1,639 TON | $85.00 | WEST TEXAS REBAR PLACERS INC. |
| May 1, 2018 | 1407-02-023 | NacogdochesLufkin | 5,566 TON | $102.27 | PINTO CONSTRUCTION CO., INC. |
| Apr 4, 2018 | 6322-17-001 | MadisonBryan | 8,401 TON | $72.00 | KNIFE RIVER CORPORATION - SOUTH |
| Oct 3, 2017 | 6319-04-001 | BurlesonBryan | 11,620 TON | $65.40 | BIG CREEK CONSTRUCTION, LTD. |
| Aug 8, 2017 | 0315-03-059 | GrimesBryan | 14,962 TON | $68.50 | ANGEL BROTHERS HOLDINGS CORP. |
| Apr 4, 2017 | 0050-01-079 | BrazosBryan | 5,172 TON | $70.50 | KNIFE RIVER CORPORATION - SOUTH |
| Jan 4, 2017 | 1562-03-018 | GrimesBryan | 1,352 TON | $125.00 | GLENN FUQUA, INC. |