$117.54Avg low bid / TON
$125.53Avg of all bids
$129.38Avg engineer's estimate
10Jobs · 59,780.23 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 1 | 3,150.23 | $107.00 | $131.20 |
| 2019 | 4 | 13,167 | $147.94 | $148.97 |
| 2018 | 3 | 16,329 | $114.41 | $122.85 |
| 2017 | 2 | 27,134 | $105.90 | $116.20 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 6, 2020 | 0271-09-023 | WallerHouston | 3,150.23 TON | $107.00 | JAMES CONSTRUCTION GROUP, L.L.C. |
| Sep 5, 2019 | 0138-05-057 | RuskTyler | 1,802 TON | $165.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Aug 7, 2019 | 3465-02-011 | GreggTyler | 3,544 TON | $145.00 | REYNOLDS & KAY, LTD. |
| Mar 6, 2019 | 0206-07-062 | RuskTyler | 1,750 TON | $150.00 | FOUTSCO PAVING COMPANY, LLC |
| Jan 9, 2019 | 3240-01-019 | WoodTyler | 6,071 TON | $144.00 | REYNOLDS & KAY, LTD. |
| Jul 11, 2018 | 0164-01-071 | HendersonTyler | 4,581 TON | $145.00 | LONGVIEW BRIDGE AND ROAD, LTD. |
| Feb 1, 2018 | 1385-02-024 | GreggTyler | 4,191 TON | $125.00 | MADDEN CONTRACTING COMPANY, LLC. |
| Jan 5, 2018 | 0683-01-095 | WilliamsonAustin | 7,557 TON | $90.00 | LONE STAR PAVING COMPANY |
| Mar 8, 2017 | 0049-01-092 | McLennanWaco | 19,738 TON | $95.00 | BIG CREEK CONSTRUCTION, LTD. |
| Mar 8, 2017 | 0245-05-047 | SmithTyler | 7,396 TON | $135.00 | IOC COMPANY LLC |