Bid code 310-6021

PRIME COAT & BLOTTER (MC-30) · per GAL

‹ All bid codes

$5.17Avg low bid / GAL
$5.07Avg of all bids
$5.26Avg engineer's estimate
33Jobs · 642,079 GAL

Average low bid by year

YearJobsQuantityAvg lowAvg all
2024499,635$6.85$6.69
2023129,649$6.00$5.74
20221896$10.00$7.00
20216139,800$4.88$4.92
20204126,485$5.01$5.17
2019457,134$4.94$5.03
20183112,863$4.69$4.77
20171075,617$4.28$4.38

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Aug 1, 20240046-03-038 BowieAtlanta4,893 GAL $20.00DRAKE COMPANIES LLC
May 2, 20240520-02-068 UpshurAtlanta14,124 GAL $6.00LONGVIEW BRIDGE AND ROAD, LTD.
Apr 4, 20241385-01-045 UpshurAtlanta43,624 GAL $5.95MADDEN CONTRACTING COMPANY, LLC.
Feb 1, 20240085-02-054 BowieAtlanta36,994 GAL $6.50LONGVIEW BRIDGE AND ROAD, LTD.
Jan 5, 20231226-02-016 TitusAtlanta29,649 GAL $6.00H. H. HOWARD & SONS, INC.
Mar 3, 20220910-07-072 GreggTyler896 GAL $10.00RAGLE CONSTRUCTION, INC.
Nov 4, 20210221-05-065 TitusAtlanta13,293 GAL $4.25LONGVIEW BRIDGE AND ROAD, LTD.
Oct 7, 20211337-02-012 LipscombAmarillo51,334 GAL $5.60J. LEE MILLIGAN, INC.
Aug 5, 20210108-02-033 Van ZandtTyler10,587 GAL $4.00BIG CREEK CONSTRUCTION, LTD.
May 5, 20210165-02-065 SmithTyler24,903 GAL $5.75MADDEN CONTRACTING COMPANY, LLC.
Apr 8, 20210222-01-056 TitusAtlanta12,667 GAL $4.50EAST TEXAS BRIDGE, INC.
Jan 7, 20213403-01-001 CampAtlanta27,016 GAL $3.56R & G CONSTRUCTION, LLC
Aug 5, 20202073-01-010 GreggTyler22,378 GAL $5.00EAST TEXAS BRIDGE, INC.
Apr 9, 20201819-01-015 LipscombAmarillo69,980 GAL $5.20J. LEE MILLIGAN, INC.
Apr 8, 20202073-01-009 GreggTyler18,094 GAL $5.00EAST TEXAS BRIDGE, INC.
Feb 6, 20201575-05-022 HarrisonAtlanta16,033 GAL $4.20MADDEN CONTRACTING COMPANY, LLC.
May 8, 20190208-02-045 HarrisonAtlanta14,567 GAL $4.50H. V. CAVER, INC.
May 7, 20190495-08-116 HarrisonAtlanta6,969 GAL $7.50EAST TEXAS BRIDGE, INC.
Apr 2, 20190206-04-042 CherokeeTyler17,261 GAL $5.00MADDEN CONTRACTING COMPANY, LLC.
Mar 5, 20190632-04-032 HarrisonAtlanta18,337 GAL $4.25H. V. CAVER, INC.
Aug 7, 20180484-01-023 JonesAbilene78,312 GAL $5.00J. H. STRAIN & SONS, INC.
Jul 10, 20180191-03-081 SmithTyler21,069 GAL $3.99HIGHWAY 19 CONSTRUCTION LLC
Apr 3, 20180245-02-031 Van ZandtTyler13,482 GAL $4.00BIG CREEK CONSTRUCTION, LTD.
Aug 9, 20170843-07-016 HarrisonAtlanta1,265 GAL $4.25LONGVIEW BRIDGE AND ROAD, LTD.
Aug 9, 20170110-04-129 MontgomeryHouston5,421 GAL $3.50SMITH & COMPANY
Aug 9, 20170108-11-019 RainsParis44,256 GAL $4.05OLDCASTLE MATERIALS TEXAS, INC.
Jul 12, 20170610-06-088 BowieAtlanta1,909 GAL $5.75LONGVIEW BRIDGE AND ROAD, LTD.
Jun 7, 20170221-05-064 TitusAtlanta5,128 GAL $4.00LONGVIEW BRIDGE AND ROAD, LTD.
Jun 7, 20170522-02-037 Van ZandtTyler4,966 GAL $4.90LONGVIEW BRIDGE AND ROAD, LTD.
Apr 4, 20170096-04-066 GreggTyler3,293 GAL $4.90LONGVIEW BRIDGE AND ROAD, LTD.
Feb 3, 20172526-02-010 BowieAtlanta5,399 GAL $4.25CDM HOLDINGS, LLC
Jan 5, 20170843-06-019 HarrisonAtlanta1,243 GAL $5.00FRITCHER CONSTRUCTION SERVICES
Jan 4, 20172879-01-010 BowieAtlanta2,737 GAL $7.00H. V. CAVER, INC.