Bid code 251-6026

REWORK BS MTL (TY B) (8") (ORD COMP) · per SY

‹ All bid codes

$2.85Avg low bid / SY
$3.62Avg of all bids
$3.65Avg engineer's estimate
19Jobs · 787,690 SY

Average low bid by year

YearJobsQuantityAvg lowAvg all
2024477,992$6.85$5.82
20233136,849$4.74$10.60
20221770$23.00$31.20
20214306,501$1.72$2.32
2020330,072$3.88$3.92
20192219,377$1.57$2.27
201817,336$2.00$2.85
201718,793$4.47$6.24

Recent low bids

ExcelCSV
Let dateCCSJCounty / DistrictQuantityUnit priceLow bidder
Aug 1, 20240901-28-105 HopkinsParis584 SY $40.00THK CONSTRUCTION LLC
May 3, 20241671-02-012 Van ZandtTyler74,434 SY $6.50BAKER & COMPANY CONSTRUCTION, LLC
Mar 6, 20240435-01-083 LamarParis424 SY $40.00THK CONSTRUCTION LLC
Mar 5, 20241709-02-021 FanninParis2,550 SY $4.00HIGHWAY 19 CONSTRUCTION LLC
Aug 3, 20230312-04-022 WiseFort Worth32,009 SY $3.78SEMA CONSTRUCTION, INC.
Aug 2, 20232653-01-016 RuskTyler104,178 SY $5.00HIGHWAY 19 CONSTRUCTION LLC
Jun 28, 20230901-22-122 HuntParis662 SY $10.00HIGHWAY 19 CONSTRUCTION LLC
Jan 7, 20220901-22-117 HuntParis770 SY $23.00HIGHWAY 19 CONSTRUCTION LLC
Dec 2, 20210348-07-018 AtascosaSan Antonio144,913 SY $1.82HUNTER INDUSTRIES, LTD.
Sep 1, 20211663-03-020 NavarroDallas3,860 SY $3.40A. L. HELMCAMP, INC.
Jun 3, 20210764-03-018 HuntParis47,227 SY $2.35D. L. LENNON INCORPORATED - CONTRACTOR
Mar 5, 20210574-02-021 NavarroDallas110,501 SY $1.25KNIFE RIVER CORPORATION - SOUTH
Nov 4, 20201123-02-016 KarnesCorpus Christi28,771 SY $2.79HUNTER INDUSTRIES, LTD.
Oct 1, 20200982-07-013 HaskellAbilene456 SY $15.00A. L. HELMCAMP, INC.
Sep 3, 20200009-22-005 HuntParis845 SY $35.00HODGES AND SON CONSTRUCTION COMPANY, INC.
Nov 6, 20191815-02-014 FanninParis76,718 SY $1.73A. K. GILLIS & SONS, INC.
Nov 5, 20191145-02-022 LeonBryan142,659 SY $1.48KNIFE RIVER CORPORATION - SOUTH
Mar 6, 20180018-03-049 WebbLaredo7,336 SY $2.00REIM CONSTRUCTION, INC.
Jun 6, 20170848-01-041 MedinaSan Antonio8,793 SY $4.47HUNTER INDUSTRIES, LTD.