SH19,US80-IH20,SP2
0108-01-030 · let Nov 6, 2025 · Van Zandt, Tyler · Super-2 Highway
$11,187,838Low bid: BIG CREEK CONSTRUCTION, LTD.-25.4% vs estimate $14,999,624
$559,226Left on the table5.0% gap to the second bid
9BiddersSpread 46% low to high
133Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $11,187,838 | -25.4% | $559,226 | 1+$432,150 | 3-$1,987,008 | |
| 2 | BAKER & COMPANY CONSTRUCTION, LLC | $11,747,064 | +5.0% | -21.7% | $1,011,960 | 4+$330,912 | 4-$2,388,872 |
| 3 | A. L. HELMCAMP, INC. | $12,759,024 | +14.0% | -14.9% | $120,774 | 3+$968,167 | 1-$1,975,906 |
| 4 | EAST TEXAS BRIDGE, INC. | $12,879,798 | +15.1% | -14.1% | $116,514 | 0 | 1-$1,533,290 |
| 5 | HIGHWAY 19 CONSTRUCTION LLC | $12,996,312 | +16.2% | -13.4% | $305,704 | 5+$1,451,015 | 2-$2,103,430 |
| 6 | REYNOLDS & KAY, LTD. | $13,302,016 | +18.9% | -11.3% | $784,772 | ||
| 7 | TEXAS MATERIALS GROUP, INC. | $14,086,787 | +25.9% | -6.1% | $1,452,511 | ||
| 8 | GREY SKY CONSTRUCTION LLC | $15,539,298 | +38.9% | 3.6% | $749,073 | ||
| 9 | TRUE ROADS CONSTRUCTION LLC | $16,288,371 | +45.6% | 8.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs BAKER & COMPANY CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $956,000.00 | $390,000.00 | $523,850.32 | -$566,000 |
| 316-7068 ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR) | 87,545 GAL | $3.75 | $8.75 | $5.18 | $437,725 |
| 344-7019 SP MIXES SP-C PG70-22 | 17,169 TON | $125.00 | $147.50 | $142.22 | $386,303 |
| 110-7001 EXCAV (ROADWAY) | 25,152 CY | $17.00 | $4.80 | $11.68 | -$306,854 |
| 100-7002 PREPARING ROW | 395.9 STA | $1,500.00 | $930.00 | $6,072.92 | -$225,663 |
| 530-7010 DRIVEWAYS (ACP) | 8,095 SY | $30.00 | $48.00 | $54.96 | $145,710 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $5,000.00 | $13,330.00 | $11,585.04 | $141,610 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 7,323 TON | $130.00 | $148.50 | $120.21 | $135,476 |
| 505-7003 TMA (MOBILE OPERATION) | 275 DAY | $125.00 | $525.00 | $229.60 | $110,000 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 9,579 CY | $17.00 | $23.50 | $13.19 | $62,264 |
| 316-7148 AGGR (TY-PD, GR-4)(SAC-A) | 2,084 CY | $180.00 | $208.00 | $145.44 | $58,352 |
| 505-7001 TMA (STATIONARY) | 275 DAY | $100.00 | $290.00 | $217.57 | $52,250 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 12,406 SY | $5.00 | $8.30 | $3.04 | $40,940 |
| 530-7018 TURNOUTS (ACP) | 457 SY | $50.00 | $127.00 | $82.59 | $35,189 |
| 662-7123 WK ZN PAV MRK SHT TERM RMV (Y)(6") | 35,161 LF | $1.00 | $2.00 | $1.21 | $35,161 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 175,342 SY | $2.00 | $1.80 | $2.24 | -$35,068 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 126,919 SY | $0.7500 | $0.5000 | $1.43 | -$31,730 |
| 164-7076 BOND FBR MTRX SEED (PERM)(RURAL)(SAND) | 126,919 SY | $0.5500 | $0.8000 | $0.5910 | $31,730 |
| 530-7002 INTERSECTIONS (ACP) | 1,577 SY | $50.00 | $70.00 | $50.74 | $31,540 |
| 134-7001 BACKFILL (TY A) | 395.9 STA | $250.00 | $179.00 | $224.26 | -$28,109 |
Positive: the low bidder was cheaper on that item. These 20 items account for $510,824 of the $559,226 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $956,000.00 | $523,850.32 | 1.82x | $432,150 |
| 100-7002 PREPARING ROW | 395.9 STA | $1,500.00 | $6,072.92 | 0.25x | -$1,810,420 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $5,000.00 | $11,585.04 | 0.43x | -$111,946 |
| 466-7179 WINGWALL (PW - 1) (HW=9 FT) | 2 EA | $20,000.00 | $52,321.35 | 0.38x | -$64,643 |
BAKER & COMPANY CONSTRUCTION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7006 EMBANK (FNL)(DC)(TY C) | 9,579 CY | $23.50 | $13.19 | 1.78x | $98,741 |
| 530-7007 DRIVEWAYS (CONC) (HES) | 875 SY | $220.00 | $122.10 | 1.80x | $85,663 |
| 505-7003 TMA (MOBILE OPERATION) | 275 DAY | $525.00 | $229.60 | 2.29x | $81,236 |
| 275-7003 CEMENT TRT (EXIST MATL)(8") | 12,406 SY | $8.30 | $3.04 | 2.73x | $65,272 |
| 100-7002 PREPARING ROW | 395.9 STA | $930.00 | $6,072.92 | 0.15x | -$2,036,083 |
| 110-7001 EXCAV (ROADWAY) | 25,152 CY | $4.80 | $11.68 | 0.41x | -$173,101 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 126,919 SY | $0.5000 | $1.43 | 0.35x | -$117,946 |
| 466-7179 WINGWALL (PW - 1) (HW=9 FT) | 2 EA | $21,450.00 | $52,321.35 | 0.41x | -$61,743 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 3EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 395.9 STA | $2,200.00 | $6,072.92 | 0.36x | -$1,533,290 |
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 126,919 SY | $2.71 | $1.43 | 1.90x | $162,545 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 9,579 CY | $30.00 | $13.19 | 2.27x | $161,005 |
| 505-7001 TMA (STATIONARY) | 275 DAY | $500.00 | $217.57 | 2.30x | $77,668 |
| 344-7077 TACK COAT | 23,364 GAL | $6.40 | $3.25 | 1.97x | $73,648 |
| 100-7002 PREPARING ROW | 395.9 STA | $1,150.00 | $6,072.92 | 0.19x | -$1,948,985 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $2,500.00 | $11,585.04 | 0.22x | -$154,446 |