IH10_W_OF_WFM11_TO_FM2886
0140-03-052 · let Feb 5, 2026 · Pecos, Odessa · Rehabilitation of Existing Road
$14,714,263Low bid: FNF CONSTRUCTION, INC.-22.1% vs estimate $18,879,654
$113,297Left on the table0.8% gap to the second bid
7BiddersSpread 50% low to high
65Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FNF CONSTRUCTION, INC. | $14,714,263 | -22.1% | $113,297 | 2+$1,130,534 | 2-$505,989 | |
| 2 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $14,827,560 | +0.8% | -21.5% | $1,925,114 | 3+$661,274 | 0 |
| 3 | RK HALL, LLC | $16,752,674 | +13.9% | -11.3% | $560,470 | 2+$305,309 | 0 |
| 4 | RAGLE CONSTRUCTION, INC. | $17,313,144 | +17.7% | -8.3% | $309,375 | 5+$3,192,364 | 2-$871,931 |
| 5 | A. L. HELMCAMP, INC. | $17,622,519 | +19.8% | -6.7% | $552,426 | 4+$995,861 | 0 |
| 6 | CK NEWBERRY, LLC | $18,174,945 | +23.5% | -3.7% | $3,835,245 | ||
| 7 | KIEWIT INFRASTRUCTURE SOUTH CO. | $22,010,190 | +49.6% | 16.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
FNF CONSTRUCTION, INC. vs JONES BROS. DIRT & PAVING CONTRACTORS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 346-7023 STONE-MTRX-ASPH SMAR-F SAC-A | 31,921 TON | $115.00 | $0.00 | $122.43 | -$3,670,915 |
| 500-7001 MOBILIZATION | 1 LS | $1,447,000.00 | $985,000.00 | $523,850.32 | -$462,000 |
| 344-7008 SP MIXES SP-B SAC-B PG76-22 | 57,443 TON | $92.00 | $84.50 | $117.26 | -$430,823 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 16,000 SY | $15.00 | $35.00 | $35.01 | $320,000 |
| 316-7007 ASPH (AC-20-5TR) | 96,680 GAL | $1.75 | $4.53 | $3.27 | $268,770 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 2,122 CY | $50.00 | $145.00 | $137.54 | $201,590 |
| 251-7083 REWORK BS MTL (TY D)(SURF)(ORD COMP) | 290,191 SY | $0.3000 | $0.8500 | $0.5657 | $159,605 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $22,500.00 | $15,000.00 | $11,585.04 | -$142,500 |
| 134-7002 BACKFILL (TY B) | 300 STA | $110.00 | $495.00 | $206.94 | $115,500 |
| 505-7003 TMA (MOBILE OPERATION) | 414 DAY | $350.00 | $100.00 | $229.60 | -$103,500 |
| 6069-7002 TEMP Q-DETECT (TY1) (2 SYS) | 414 DAY | $100.00 | $335.50 | $60.85 | $97,497 |
| 105-7026 RMV (6") TRT/UNTRT BASE & ASPH PAV | 174,072 SY | $5.00 | $4.44 | $5.12 | -$97,480 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 290,191 SY | $2.00 | $1.67 | $2.13 | -$95,763 |
| 451-7025 RETROFIT RAIL (TY SSTR)(HPC) | 764 LF | $150.00 | $258.50 | $173.55 | $82,894 |
| 3007-7001 BONDING COURSE | 20,353 GAL | $4.50 | $2.44 | $3.32 | -$41,927 |
| 344-7077 TACK COAT | 29,019 GAL | $5.00 | $3.79 | $3.25 | -$35,113 |
| 310-7001 PRIME COAT (AE-P) | 58,038 GAL | $5.00 | $4.41 | $5.11 | -$34,242 |
| 480-7001 CLEAN EXIST CULVERTS | 32 EA | $1,200.00 | $2,200.00 | $1,712.97 | $32,000 |
| 505-7001 TMA (STATIONARY) | 414 DAY | $150.00 | $82.50 | $217.57 | -$27,945 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 91 CY | $1,000.00 | $797.50 | $616.83 | -$18,428 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$3,882,779 of the $113,297 gap.
FNF CONSTRUCTION, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,447,000.00 | $523,850.32 | 2.76x | $923,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $22,500.00 | $11,585.04 | 1.94x | $207,384 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 16,000 SY | $15.00 | $35.01 | 0.43x | -$320,238 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 2,122 CY | $50.00 | $137.54 | 0.36x | -$185,751 |
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 2RK HALL, LLC: unbalanced items
Placed 3RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 19 MO | $97,650.00 | $11,585.04 | 8.43x | $1,635,234 |
| 500-7001 MOBILIZATION | 1 LS | $1,725,000.00 | $523,850.32 | 3.29x | $1,201,150 |
| 251-7083 REWORK BS MTL (TY D)(SURF)(ORD COMP) | 290,191 SY | $1.00 | $0.5657 | 1.77x | $126,030 |
| 134-7002 BACKFILL (TY B) | 300 STA | $616.00 | $206.94 | 2.98x | $122,717 |
| 480-7001 CLEAN EXIST CULVERTS | 32 EA | $5,064.00 | $1,712.97 | 2.96x | $107,233 |
| 105-7026 RMV (6") TRT/UNTRT BASE & ASPH PAV | 174,072 SY | $2.00 | $5.12 | 0.39x | -$543,958 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 290,191 SY | $1.00 | $2.13 | 0.47x | -$327,974 |
A. L. HELMCAMP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,100,000.00 | $523,850.32 | 2.10x | $576,150 |
| 451-7025 RETROFIT RAIL (TY SSTR)(HPC) | 764 LF | $430.00 | $173.55 | 2.48x | $195,929 |
| 677-7001 ELIM EXT PM & MRKS (4") | 71,886 LF | $2.00 | $0.2643 | 7.57x | $124,773 |
| 6069-7002 TEMP Q-DETECT (TY1) (2 SYS) | 414 DAY | $300.00 | $60.85 | 4.93x | $99,010 |