US 90 BRIDGE REPLACEMENT 2304-1
0026-06-033 · let Feb 5, 2026 · Colorado, Yoakum · Bridge Replacement
$3,715,521Low bid: R CONSTRUCTION CIVIL, LLC-28.0% vs estimate $5,159,024
$130,664Left on the table3.5% gap to the second bid
14BiddersSpread 58% low to high
64Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | R CONSTRUCTION CIVIL, LLC | $3,715,521 | -28.0% | $130,664 | 3+$107,054 | 6-$5,917,752 | |
| 2 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $3,846,185 | +3.5% | -25.4% | -$113,616 | 3+$89,884 | 4-$5,291,701 |
| 3 | HUNTER INDUSTRIES, LTD. | $3,732,569 | +0.5% | -27.6% | $1,043,532 | 0 | 3-$4,946,448 |
| 4 | RAGLE CONSTRUCTION, INC. | $4,776,101 | +28.5% | -7.4% | -$708,025 | 3+$508,123 | 1-$5,484,944 |
| 5 | TUCAN CONTRACTING, LLC | $4,068,076 | +9.5% | -21.1% | $139,063 | 1+$23,049 | 4-$5,115,597 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $4,207,139 | +13.2% | -18.5% | $479,952 | ||
| 7 | ALTUS CONSTRUCTION LLC | $4,687,091 | +26.1% | -9.1% | -$67,790 | ||
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $4,619,302 | +24.3% | -10.5% | -$44,239 | ||
| 9 | DEAN WORD COMPANY, LTD. | $4,575,063 | +23.1% | -11.3% | -$54,207 | ||
| 10 | CASTILLO ARANDA LLC | $4,520,855 | +21.7% | -12.4% | $707,792 | ||
| 11 | TEXAS MATERIALS GROUP, INC. | $5,228,647 | +40.7% | 1.3% | -$175,526 | ||
| 12 | C. E. BARKER, LTD. | $5,053,121 | +36.0% | -2.1% | $812,114 | ||
| 13 | HARPER BROTHERS CONSTRUCTION LLC | $5,865,235 | +57.9% | 13.7% | -$454,695 | ||
| 14 | FORDE CONSTRUCTION COMPANY, INC. | $5,410,540 | +45.6% | 4.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
R CONSTRUCTION CIVIL, LLC vs TEXAS STEEL INDUSTRIAL PLACING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $35,000.00 | $381,153.43 | $523,850.32 | $346,153 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 4,156 SY | $100.00 | $65.74 | $77.78 | -$142,385 |
| 420-7022 CL C CONC (CAP) | 140.9 CY | $775.00 | $1,700.00 | $1,543.38 | $130,333 |
| 800-7001 NO. OF WORKING DAYS | 10,091 $/D | $120.00 | $130.00 | $612.55 | $100,910 |
| 422-7001 REINF CONC SLAB | 24,840 SF | $24.00 | $20.00 | $24.45 | -$99,360 |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 1,589 TON | $155.00 | $110.63 | $116.75 | -$70,504 |
| 341-7001 D-GR HMA TY-B PG64-22 | 1,622 TON | $145.00 | $103.98 | $97.82 | -$66,534 |
| 508-7001 CONSTRUCTING DETOURS | 781 SY | $50.00 | $120.00 | $83.58 | $54,670 |
| 450-7008 RAIL (TY T223) | 1,128 LF | $205.00 | $160.00 | $141.07 | -$50,760 |
| 420-7038 CL C CONC (COLUMN) | 52.7 CY | $820.00 | $1,700.00 | $1,548.37 | $46,376 |
| 416-7006 DRILL SHAFT (36 IN) | 1,320 LF | $265.00 | $300.00 | $280.58 | $46,200 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,947 SY | $8.00 | $4.00 | $1.43 | -$35,788 |
| 420-7012 CL C CONC (ABUT) | 56.6 CY | $635.00 | $1,200.00 | $1,307.98 | $31,979 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 887 CY | $215.00 | $185.00 | $184.74 | -$26,610 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $75,000.00 | $100,000.00 | $378,521.97 | $25,000 |
| 100-7002 PREPARING ROW | 14 STA | $2,400.00 | $1,000.00 | $6,072.92 | -$19,600 |
| 168-7001 VEGETATIVE WATERING | 75 TGL | $250.00 | $1.00 | $8.43 | -$18,675 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 3,216 LF | $175.00 | $170.00 | $217.69 | -$16,080 |
| 400-7010 CEM STABIL BKFL | 114 CY | $105.00 | $225.00 | $138.14 | $13,680 |
| 454-7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 182 LF | $175.00 | $250.00 | $221.89 | $13,650 |
Positive: the low bidder was cheaper on that item. These 20 items account for $262,655 of the $130,664 gap.
R CONSTRUCTION CIVIL, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,947 SY | $8.00 | $1.43 | 5.60x | $58,788 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $24,000.00 | $9,253.78 | 2.59x | $29,492 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 115 CY | $275.00 | $111.76 | 2.46x | $18,773 |
| 800-7001 NO. OF WORKING DAYS | 10,091 $/D | $120.00 | $612.55 | 0.20x | -$4,970,303 |
| 500-7001 MOBILIZATION | 1 LS | $35,000.00 | $523,850.32 | 0.07x | -$488,850 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $75,000.00 | $378,521.97 | 0.20x | -$303,522 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $4,300.00 | $11,585.04 | 0.37x | -$65,565 |
| 100-7002 PREPARING ROW | 14 STA | $2,400.00 | $6,072.92 | 0.40x | -$51,421 |
| 420-7012 CL C CONC (ABUT) | 56.6 CY | $635.00 | $1,307.98 | 0.49x | -$38,091 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $30,000.00 | $9,253.78 | 3.24x | $41,492 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 115 CY | $332.55 | $111.76 | 2.98x | $25,391 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,947 SY | $4.00 | $1.43 | 2.80x | $23,000 |
| 800-7001 NO. OF WORKING DAYS | 10,091 $/D | $130.00 | $612.55 | 0.21x | -$4,869,393 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $100,000.00 | $378,521.97 | 0.26x | -$278,522 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $3,500.00 | $11,585.04 | 0.30x | -$72,765 |
| 100-7002 PREPARING ROW | 14 STA | $1,000.00 | $6,072.92 | 0.16x | -$71,021 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 14 STA | $25,000.00 | $6,072.92 | 4.12x | $264,979 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $35,700.00 | $11,585.04 | 3.08x | $217,035 |
| 110-7001 EXCAV (ROADWAY) | 144 CY | $193.00 | $11.68 | 16.52x | $26,110 |
| 800-7001 NO. OF WORKING DAYS | 10,091 $/D | $69.00 | $612.55 | 0.11x | -$5,484,944 |
TUCAN CONTRACTING, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 4,981 GAL | $8.80 | $4.17 | 2.11x | $23,049 |
| 800-7001 NO. OF WORKING DAYS | 10,091 $/D | $154.00 | $612.55 | 0.25x | -$4,627,209 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $55,000.00 | $378,521.97 | 0.15x | -$323,522 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $2,200.00 | $11,585.04 | 0.19x | -$84,465 |
| 100-7002 PREPARING ROW | 14 STA | $330.00 | $6,072.92 | 0.05x | -$80,401 |