Bid Tab X-ray: 6505-19-001

Oct 14, 2026 · Ellis Sign up free
Set your company to personalize scores

Rock/Riprap Materials 09 1026

6505-19-001 · let Oct 14, 2026 · Ellis, Dallas · Material Maintenance Project

$105,000Low bid: TOUCHSTONE RESOURCES, LLC+10.5% vs estimate $95,000
$1,400Left on the table1.3% gap to the second bid
5BiddersSpread 28% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1TOUCHSTONE RESOURCES, LLC $105,00010.5% $1,400 0 0
2SOUTHERN SOURCING SOLUTIONS, LLC $106,400+1.3%12.0% $6,100 0 0
3A. L. HELMCAMP, INC. $112,500+7.1%18.4% $16,820 0 0
4TRADERS INN LLC $129,320+23.2%36.1% $4,680 0 0
5KNIFE RIVER CORPORATION - SOUTH $134,000+27.6%41.1% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

TOUCHSTONE RESOURCES, LLC vs SOUTHERN SOURCING SOLUTIONS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8004-7122 RIPRAP(STN CMN DRY)(3"X5")(DEL)(ST1)500 TON $40.00$47.91$37.54 $3,955
8004-7167 RIPRAP(STN CMN DRY)(18"X24")(DEL)(ST2)500 TON $65.00$58.49$63.64 -$3,255
8004-7123 RIPRAP(STN CMN DRY)(3"X5")(DEL)(ST2)500 TON $45.00$46.83$39.00 $915
8004-7166 RIPRAP(STN CMN DRY)(18"X24")(DEL)(ST1)500 TON $60.00$59.57$54.06 -$215

Positive: the low bidder was cheaper on that item. These 4 items account for $1,400 of the $1,400 gap.