IH 35: 0017-09-106; OV
0017-09-106 · let Feb 4, 2026 · Bexar, San Antonio · Overlay
$15,028,560Low bid: LONE STAR PAVING COMPANY-18.8% vs estimate $18,518,603
$951,951Left on the table6.3% gap to the second bid
4BiddersSpread 21% low to high
129Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | LONE STAR PAVING COMPANY | $15,028,560 | -18.8% | $951,951 | 0 | 0 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $15,980,512 | +6.3% | -13.7% | $136,822 | 0 | 0 |
| 3 | HUNTER INDUSTRIES, LTD. | $16,117,333 | +7.2% | -13.0% | $2,101,839 | 1+$465,539 | 0 |
| 4 | CLARK CONSTRUCTION OF TEXAS, INC. | $18,219,172 | +21.2% | -1.6% | 3+$710,834 | 1-$159,546 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
LONE STAR PAVING COMPANY vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 346-7016 STONE-MTRX-ASPH SMA-D SAC-A HPG | 45,420 TON | $162.50 | $172.50 | $180.83 | $454,200 |
| 500-7001 MOBILIZATION | 1 LS | $400,000.00 | $720,000.00 | $523,850.32 | $320,000 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 1,023.8 CY | $515.00 | $723.00 | $616.83 | $212,950 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 71,051 SY | $39.50 | $37.75 | $49.06 | -$124,339 |
| 3006-7001 UNDERSEAL COURSE | 16,842 GAL | $4.80 | $0.0500 | $3.65 | -$80,000 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 1,920 LF | $65.00 | $24.00 | $52.29 | -$78,720 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 17,550 LF | $20.25 | $24.25 | $25.60 | $70,200 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $6,800.00 | $10,700.00 | $11,585.04 | $66,300 |
| 505-7001 TMA (STATIONARY) | 304 DAY | $300.00 | $100.00 | $217.57 | -$60,800 |
| 354-7035 PLANE ASPH CONC PAV(0" TO 6") | 47,972 SY | $2.50 | $3.60 | $4.49 | $52,769 |
| 3007-7001 BONDING COURSE | 79,277 GAL | $3.00 | $3.55 | $3.32 | $43,602 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 31 EA | $2,015.00 | $3,200.00 | $2,218.70 | $36,735 |
| 354-7051 PLANE ASPH CONC PAV(2") | 346,881 SY | $1.90 | $2.00 | $1.86 | $34,688 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 806 CY | $9.50 | $49.00 | $16.96 | $31,837 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 1,920 LF | $40.00 | $24.00 | $12.08 | -$30,720 |
| 351-7033 FLEX. PAVE. STRUCTURE REPAIR 6" TO 9" | 2,981 SY | $45.00 | $54.45 | $45.00 | $28,170 |
| 505-7003 TMA (MOBILE OPERATION) | 126 DAY | $300.00 | $100.00 | $229.60 | -$25,200 |
| 341-7030 D-GR HMA TY-C PG76-22 | 913 TON | $118.00 | $98.00 | $93.60 | -$18,260 |
| 247-7348 FL BS (CIP)(TY A GR 1-2 OR 5) FINAL POS | 2,222 CY | $80.00 | $72.00 | $77.43 | -$17,776 |
| 104-7005 REMOV CONC (MOWSTRIP) | 5,512.5 LF | $11.00 | $14.00 | $9.49 | $16,538 |
Positive: the low bidder was cheaper on that item. These 20 items account for $932,175 of the $951,951 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $989,388.88 | $523,850.32 | 1.89x | $465,539 |
CLARK CONSTRUCTION OF TEXAS, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,000,000.00 | $523,850.32 | 1.91x | $476,150 |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 617 TON | $322.53 | $115.04 | 2.80x | $128,024 |
| 351-7033 FLEX. PAVE. STRUCTURE REPAIR 6" TO 9" | 2,981 SY | $80.78 | $45.00 | 1.80x | $106,660 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 17 MO | $2,200.00 | $11,585.04 | 0.19x | -$159,546 |