FY27 Supplemental BPM 1
6508-47-001 · let Nov 3, 2026 · Childress, Childress · Bridge Preventative Maintenance - Sealed
$792,433Low bid: ICOS MANAGEMENT, LLC-30.7% vs estimate $1,143,630
$29,593Left on the table3.7% gap to the second bid
15BiddersSpread 174% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ICOS MANAGEMENT, LLC | $792,433 | -30.7% | $29,593 | 1+$12,702 | 5-$644,669 | |
| 2 | BLACKSMITH VENTURES LLC | $822,026 | +3.7% | -28.1% | $70,465 | 1+$19,927 | 4-$646,096 |
| 3 | PREMIER CONTRACTORS LLC | $892,491 | +12.6% | -22.0% | $19,585 | 1+$23,327 | 5-$627,527 |
| 4 | COPPELL CONSTRUCTION CO., INC. | $912,076 | +15.1% | -20.2% | $110,278 | 2+$54,473 | 4-$788,553 |
| 5 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,022,354 | +29.0% | -10.6% | $104,682 | 2+$37,948 | 2-$475,038 |
| 6 | PATHFIELD INVESTMENTS LLC | $1,127,036 | +42.2% | -1.5% | $9,649 | ||
| 7 | O. TREVINO CONSTRUCTION, LLC | $1,136,685 | +43.4% | -0.6% | $145,041 | ||
| 8 | STRUCTURAL INTEGRITY GROUP LLC | $1,281,726 | +61.7% | 12.1% | $24,407 | ||
| 9 | THK CONSTRUCTION LLC | $1,306,133 | +64.8% | 14.2% | $33,025 | ||
| 10 | SCR CIVIL CONSTRUCTION, LLC | $1,339,158 | +69.0% | 17.1% | $18,906 | ||
| 11 | RAGLE CONSTRUCTION, INC. | $1,358,064 | +71.4% | 18.8% | $79,072 | ||
| 12 | REAR CONTRACTORS LLC | $1,437,136 | +81.4% | 25.7% | $558,514 | ||
| 13 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,995,650 | +151.8% | 74.5% | $146,760 | ||
| 14 | SOUTHERN ROAD & BRIDGE, LLC | $2,142,410 | +170.4% | 87.3% | $25,590 | ||
| 15 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $2,168,000 | +173.6% | 89.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ICOS MANAGEMENT, LLC vs BLACKSMITH VENTURES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 3,216 SF | $94.50 | $119.00 | $150.68 | $78,792 |
| 500-7001 MOBILIZATION | 1 LS | $43,000.00 | $1.00 | $523,850.32 | -$42,999 |
| 429-7006 CONC STR REPR(RAPID DECK REP(FULL DPT)) | 2,070 SF | $141.75 | $125.00 | $153.06 | -$34,673 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $12,600.00 | $30,000.00 | $70,292.48 | $17,400 |
| 4010-7020 STEEL BRIDGE ZONE PAINTING REF STR #18 | 1 EA | $12,600.00 | $30,000.00 | $36,300.00 | $17,400 |
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 540 SF | $126.00 | $95.00 | $85.28 | -$16,740 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $1,575.00 | $2,000.00 | $827.85 | $7,225 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 165 SF | $73.50 | $95.00 | $151.82 | $3,548 |
| 4010-7019 STEEL BRIDGE ZONE PAINTING REF STR #17 | 1 EA | $12,600.00 | $10,000.00 | $22,450.00 | -$2,600 |
| 505-7001 TMA (STATIONARY) | 35 DAY | $210.00 | $274.00 | $217.57 | $2,240 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $1.00 | $11,585.04 | $0 |
Positive: the low bidder was cheaper on that item. These 11 items account for $29,593 of the $29,593 gap.
ICOS MANAGEMENT, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $1,575.00 | $827.85 | 1.90x | $12,702 |
| 500-7001 MOBILIZATION | 1 LS | $43,000.00 | $523,850.32 | 0.08x | -$480,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $12,600.00 | $70,292.48 | 0.18x | -$57,692 |
| 4010-7020 STEEL BRIDGE ZONE PAINTING REF STR #18 | 1 EA | $12,600.00 | $36,300.00 | 0.35x | -$23,700 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 165 SF | $73.50 | $151.82 | 0.48x | -$12,922 |
BLACKSMITH VENTURES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $2,000.00 | $827.85 | 2.42x | $19,927 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $523,850.32 | 0.00x | -$523,849 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $30,000.00 | $70,292.48 | 0.43x | -$40,292 |
| 4010-7019 STEEL BRIDGE ZONE PAINTING REF STR #17 | 1 EA | $10,000.00 | $22,450.00 | 0.45x | -$12,450 |
PREMIER CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $2,200.00 | $827.85 | 2.66x | $23,327 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $11,585.04 | 0.00x | -$69,504 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $15,000.00 | $70,292.48 | 0.21x | -$55,292 |
| 4010-7020 STEEL BRIDGE ZONE PAINTING REF STR #18 | 1 EA | $15,000.00 | $36,300.00 | 0.41x | -$21,300 |
| 505-7001 TMA (STATIONARY) | 35 DAY | $1.00 | $217.57 | 0.00x | -$7,580 |
COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7004 CONC STR REPAIR(RAPID DECK REP(PRT DPT) | 540 SF | $165.00 | $85.28 | 1.93x | $43,046 |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $1,500.00 | $827.85 | 1.81x | $11,427 |
| 500-7001 MOBILIZATION | 1 LS | $80,000.00 | $523,850.32 | 0.15x | -$443,850 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 3,216 SF | $61.00 | $150.68 | 0.40x | -$288,411 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $27,500.00 | $70,292.48 | 0.39x | -$42,792 |
| 429-7002 CONC STR REPAIR (EPOXY MORTAR) | 165 SF | $70.00 | $151.82 | 0.46x | -$13,500 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7060 CL C CONC (PILE ENCASEMENT) | 17 CY | $2,668.00 | $827.85 | 3.22x | $31,283 |
| 505-7001 TMA (STATIONARY) | 35 DAY | $408.00 | $217.57 | 1.88x | $6,665 |
| 500-7001 MOBILIZATION | 1 LS | $102,000.00 | $523,850.32 | 0.19x | -$421,850 |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $17,105.00 | $70,292.48 | 0.24x | -$53,187 |