FM 1462 - W of Troon Dr to BS 35-C
1414-03-043 · let Oct 6, 2026 · Brazoria, Houston · Safety Improvement Projects
$974,716Low bid: DURWOOD GREENE CONSTRUCTION CO.-9.6% vs estimate $1,078,722
$46,902Left on the table4.8% gap to the second bid
2BiddersSpread 5% low to high
39Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DURWOOD GREENE CONSTRUCTION CO. | $974,716 | -9.6% | $46,902 | 1+$65,989 | 1-$483,850 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,021,617 | +4.8% | -5.3% | 3+$106,574 | 2-$510,920 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
DURWOOD GREENE CONSTRUCTION CO. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 354-7074 PLANE ASPH CONC PAV (1.5") | 40,110 SY | $3.00 | $3.55 | $1.35 | $22,061 |
| 3006-7001 UNDERSEAL COURSE | 8,828 GAL | $2.00 | $4.15 | $3.65 | $18,980 |
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 3,414 TON | $169.00 | $174.00 | $129.17 | $17,070 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 210 SY | $90.00 | $140.00 | $77.78 | $10,500 |
| 500-7001 MOBILIZATION | 1 LS | $40,000.00 | $30,500.00 | $523,850.32 | -$9,500 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $7,000.00 | $2,800.00 | $11,585.04 | -$8,400 |
| 505-7001 TMA (STATIONARY) | 28 DAY | $350.00 | $180.00 | $217.57 | -$4,760 |
| 6006-7002 VIVDS CAM ASSY FXD LNS | 12 EA | $2,700.00 | $3,075.00 | $4,074.68 | $4,500 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 140 SY | $50.00 | $74.00 | $35.01 | $3,360 |
| 6006-7007 VIVDS CABLING | 3,125 LF | $2.75 | $1.85 | $2.85 | -$2,813 |
| 624-7013 REMOVE GROUND BOX | 24 EA | $300.00 | $212.00 | $377.64 | -$2,112 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 1,170 EA | $2.50 | $0.7900 | $0.5715 | -$2,001 |
| 618-7055 CONDT (PVC) (SCH 80) (2") (BORE) | 295 LF | $20.00 | $26.50 | $20.33 | $1,918 |
| 134-7004 BACKFILL (TY A OR B) | 2 STA | $650.00 | $1,500.00 | $211.21 | $1,700 |
| 618-7054 CONDT (PVC) (SCH 80) (2") | 280 LF | $20.00 | $16.00 | $12.03 | -$1,120 |
| 505-7003 TMA (MOBILE OPERATION) | 9 DAY | $300.00 | $180.00 | $229.60 | -$1,080 |
| 624-7007 GROUND BOX TY D (162922) | 2 EA | $1,080.00 | $1,590.00 | $1,420.34 | $1,020 |
| 662-7035 WK ZN PAV MRK NON-REMOV (Y)4"(SLD) | 10,802 LF | $0.5500 | $0.5000 | $0.4002 | -$540 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 600 LF | $8.00 | $7.40 | $7.19 | -$360 |
| 662-7012 WK ZN PAV MRK NON-REMOV (W)8"(SLD) | 860 LF | $1.50 | $1.15 | $0.6092 | -$301 |
Positive: the low bidder was cheaper on that item. These 20 items account for $48,122 of the $46,902 gap.
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 1TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7074 PLANE ASPH CONC PAV (1.5") | 40,110 SY | $3.55 | $1.35 | 2.62x | $88,049 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 210 SY | $140.00 | $77.78 | 1.80x | $13,067 |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4") | 140 SY | $74.00 | $35.01 | 2.11x | $5,458 |
| 500-7001 MOBILIZATION | 1 LS | $30,500.00 | $523,850.32 | 0.06x | -$493,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $2,800.00 | $11,585.04 | 0.24x | -$17,570 |