Bid Tab X-ray: 6502-08-001

Sep 9, 2026 · Kaufman Sign up free
Set your company to personalize scores

FY'26 Pothole Repair

6502-08-001 · let Sep 9, 2026 · Kaufman, Dallas · Routine Maintenance Project - Sealed

$301,500Low bid: THOMAS 11 DEVELOPMENT LLC-29.1% vs estimate $425,075
$93,020Left on the table30.9% gap to the second bid
6BiddersSpread 259% low to high
8Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1THOMAS 11 DEVELOPMENT LLC $301,500-29.1% $93,020 4+$40,776 1-$129,381
2DIGG COMMERCIAL, LLC $394,520+30.9%-7.2% $43,830 3+$153,500 2-$13,217
3JACKSON EXCAVATION, LLC $438,350+45.4%3.1% $359,435 0 2-$14,093
4ADVANCED BARRICADES OF AMERICA, LLC $797,785+164.6%87.7% $197,215 3+$403,445 0
5TEXAS MATERIALS GROUP, INC. $995,000+230.0%134.1% $88,320 4+$606,726 0
6FOUTSCO PAVING COMPANY, LLC $1,083,320+259.3%154.9%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

THOMAS 11 DEVELOPMENT LLC vs DIGG COMMERCIAL, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
505-7003 TMA (MOBILE OPERATION)50 DAY $700.00$2,000.00$229.60 $65,000
700-7005 POTHOLE REPAIR (STANDARD)325 TON $400.00$200.00$371.25 -$65,000
700-7010 POTHOLE REPAIR (SAW - CUT)500 TON $165.00$294.00$423.76 $64,500
505-7001 TMA (STATIONARY)15 DAY $700.00$4,000.00$217.57 $49,500
500-7002 MOBILIZATION (CALLOUT)15 EA $1,000.00$1.00$600.85 -$14,985
500-7033 MOBILIZATION (EMERGENCY)5 EA $2,000.00$1.00$844.81 -$9,995
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN20 DAY $300.00$500.00$87.82 $4,000
700-7012 EDGE REPAIR25 TON $500.00$500.00$507.50 $0

Positive: the low bidder was cheaper on that item. These 8 items account for $93,020 of the $93,020 gap.

THOMAS 11 DEVELOPMENT LLC: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)50 DAY $700.00$229.603.05x$23,520
505-7001 TMA (STATIONARY)15 DAY $700.00$217.573.22x$7,236
500-7033 MOBILIZATION (EMERGENCY)5 EA $2,000.00$844.812.37x$5,776
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN20 DAY $300.00$87.823.42x$4,244
700-7010 POTHOLE REPAIR (SAW - CUT)500 TON $165.00$423.760.39x-$129,381

DIGG COMMERCIAL, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)50 DAY $2,000.00$229.608.71x$88,520
505-7001 TMA (STATIONARY)15 DAY $4,000.00$217.5718.38x$56,736
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN20 DAY $500.00$87.825.69x$8,244
500-7002 MOBILIZATION (CALLOUT)15 EA $1.00$600.850.00x-$8,998
500-7033 MOBILIZATION (EMERGENCY)5 EA $1.00$844.810.00x-$4,219

JACKSON EXCAVATION, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
505-7003 TMA (MOBILE OPERATION)50 DAY $10.00$229.600.04x-$10,980
505-7001 TMA (STATIONARY)15 DAY $10.00$217.570.05x-$3,114

ADVANCED BARRICADES OF AMERICA, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
700-7005 POTHOLE REPAIR (STANDARD)325 TON $1,000.00$371.252.69x$204,344
700-7010 POTHOLE REPAIR (SAW - CUT)500 TON $800.00$423.761.89x$188,119
500-7002 MOBILIZATION (CALLOUT)15 EA $1,333.00$600.852.22x$10,982

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
700-7010 POTHOLE REPAIR (SAW - CUT)500 TON $1,100.00$423.762.60x$338,119
700-7005 POTHOLE REPAIR (STANDARD)325 TON $1,100.00$371.252.96x$236,844
500-7002 MOBILIZATION (CALLOUT)15 EA $2,000.00$600.853.33x$20,987
500-7033 MOBILIZATION (EMERGENCY)5 EA $3,000.00$844.813.55x$10,776