FY'26 Pothole Repair
6502-08-001 · let Sep 9, 2026 · Kaufman, Dallas · Routine Maintenance Project - Sealed
$301,500Low bid: THOMAS 11 DEVELOPMENT LLC-29.1% vs estimate $425,075
$93,020Left on the table30.9% gap to the second bid
6BiddersSpread 259% low to high
8Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | THOMAS 11 DEVELOPMENT LLC | $301,500 | -29.1% | $93,020 | 4+$40,776 | 1-$129,381 | |
| 2 | DIGG COMMERCIAL, LLC | $394,520 | +30.9% | -7.2% | $43,830 | 3+$153,500 | 2-$13,217 |
| 3 | JACKSON EXCAVATION, LLC | $438,350 | +45.4% | 3.1% | $359,435 | 0 | 2-$14,093 |
| 4 | ADVANCED BARRICADES OF AMERICA, LLC | $797,785 | +164.6% | 87.7% | $197,215 | 3+$403,445 | 0 |
| 5 | TEXAS MATERIALS GROUP, INC. | $995,000 | +230.0% | 134.1% | $88,320 | 4+$606,726 | 0 |
| 6 | FOUTSCO PAVING COMPANY, LLC | $1,083,320 | +259.3% | 154.9% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
THOMAS 11 DEVELOPMENT LLC vs DIGG COMMERCIAL, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $700.00 | $2,000.00 | $229.60 | $65,000 |
| 700-7005 POTHOLE REPAIR (STANDARD) | 325 TON | $400.00 | $200.00 | $371.25 | -$65,000 |
| 700-7010 POTHOLE REPAIR (SAW - CUT) | 500 TON | $165.00 | $294.00 | $423.76 | $64,500 |
| 505-7001 TMA (STATIONARY) | 15 DAY | $700.00 | $4,000.00 | $217.57 | $49,500 |
| 500-7002 MOBILIZATION (CALLOUT) | 15 EA | $1,000.00 | $1.00 | $600.85 | -$14,985 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $2,000.00 | $1.00 | $844.81 | -$9,995 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $300.00 | $500.00 | $87.82 | $4,000 |
| 700-7012 EDGE REPAIR | 25 TON | $500.00 | $500.00 | $507.50 | $0 |
Positive: the low bidder was cheaper on that item. These 8 items account for $93,020 of the $93,020 gap.
THOMAS 11 DEVELOPMENT LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $700.00 | $229.60 | 3.05x | $23,520 |
| 505-7001 TMA (STATIONARY) | 15 DAY | $700.00 | $217.57 | 3.22x | $7,236 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $2,000.00 | $844.81 | 2.37x | $5,776 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $300.00 | $87.82 | 3.42x | $4,244 |
| 700-7010 POTHOLE REPAIR (SAW - CUT) | 500 TON | $165.00 | $423.76 | 0.39x | -$129,381 |
DIGG COMMERCIAL, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 50 DAY | $2,000.00 | $229.60 | 8.71x | $88,520 |
| 505-7001 TMA (STATIONARY) | 15 DAY | $4,000.00 | $217.57 | 18.38x | $56,736 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 20 DAY | $500.00 | $87.82 | 5.69x | $8,244 |
| 500-7002 MOBILIZATION (CALLOUT) | 15 EA | $1.00 | $600.85 | 0.00x | -$8,998 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $1.00 | $844.81 | 0.00x | -$4,219 |
JACKSON EXCAVATION, LLC: unbalanced items
Placed 3ADVANCED BARRICADES OF AMERICA, LLC: unbalanced items
Placed 4TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 700-7010 POTHOLE REPAIR (SAW - CUT) | 500 TON | $1,100.00 | $423.76 | 2.60x | $338,119 |
| 700-7005 POTHOLE REPAIR (STANDARD) | 325 TON | $1,100.00 | $371.25 | 2.96x | $236,844 |
| 500-7002 MOBILIZATION (CALLOUT) | 15 EA | $2,000.00 | $600.85 | 3.33x | $20,987 |
| 500-7033 MOBILIZATION (EMERGENCY) | 5 EA | $3,000.00 | $844.81 | 3.55x | $10,776 |