FY'26 Pothole Repair
- Let date
- Wednesday, September 9, 2026
- CCSJ
- 6502-08-001
- District
- Dallas
- County
- Kaufman
- Highway
- IH0020
- Limits
- Various Roadways in the Kaufman - to Rockwall Maintenance Section
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00221675
- Working days
- 365
- DBE goal
- 0%
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $425,075 | ||
| 1 | THOMAS 11 DEVELOPMENT LLC Low bidder | $301,500 | -29.1% | |
| 2 | DIGG COMMERCIAL, LLC | $394,520 | -7.2% | +30.9% |
| 3 | JACKSON EXCAVATION, LLC | $438,350 | +3.1% | +45.4% |
| 4 | ADVANCED BARRICADES OF AMERICA, LLC | $797,785 | +87.7% | +164.6% |
| 5 | TEXAS MATERIALS GROUP, INC. | $995,000 | +134.1% | +230.0% |
| 6 | FOUTSCO PAVING COMPANY, LLC | $1,083,320 | +154.9% | +259.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THOMAS 11 DEVEL… | #2 DIGG COMMERCIAL… | #3 JACKSON EXCAVAT… | #4 ADVANCED BARRIC… | #5 TEXAS MATERIALS… | #6 FOUTSCO PAVING … |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 15 | EA | $3,000.00 | $1,000.00 | $1.00 | $1,000.00 | $1,333.00 | $2,000.00 | $2,000.00 |
| 2 | 500-7033 | MOBILIZATION (EMERGENCY) | 5 | EA | $4,000.00 | $2,000.00 | $1.00 | $1,000.00 | $1,333.00 | $3,000.00 | $2,000.00 |
| 3 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 20 | DAY | $110.00 | $300.00 | $500.00 | $10.00 | $225.00 | $250.00 | $1.00 |
| 4 | 505-7001 | TMA (STATIONARY) | 15 | DAY | $100.00 | $700.00 | $4,000.00 | $10.00 | $250.00 | $300.00 | $300.00 |
| 5 | 505-7003 | TMA (MOBILE OPERATION) | 50 | DAY | $200.00 | $700.00 | $2,000.00 | $10.00 | $400.00 | $300.00 | $1.00 |
| 6 | 700-7005 | POTHOLE REPAIR (STANDARD) | 325 | TON | $380.00 | $400.00 | $200.00 | $400.00 | $1,000.00 | $1,100.00 | $800.00 |
| 7 | 700-7010 | POTHOLE REPAIR (SAW - CUT) | 500 | TON | $420.00 | $165.00 | $294.00 | $550.00 | $800.00 | $1,100.00 | $1,550.00 |
| 8 | 700-7012 | EDGE REPAIR | 25 | TON | $515.00 | $500.00 | $500.00 | $500.00 | $715.00 | $720.00 | $150.00 |