WNF | IH 14 | IH 35
2502-01-024 · let Oct 6, 2026 · Bell, Waco · Widen Non-Freeway
$22,052,184Low bid: BIG CREEK CONSTRUCTION, LTD.-10.6% vs estimate $24,664,269
$1,084,960Left on the table4.9% gap to the second bid
6BiddersSpread 14% low to high
169Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $22,052,184 | -10.6% | $1,084,960 | 3+$1,952,025 | 2-$863,277 | |
| 2 | PATIN CONSTRUCTION LLC | $23,137,144 | +4.9% | -6.2% | $453,883 | 6+$2,743,902 | 4-$2,286,267 |
| 3 | JAMES CONSTRUCTION GROUP, LLC | $23,591,027 | +7.0% | -4.4% | $53,258 | 4+$3,127,606 | 3-$533,292 |
| 4 | TEXAS MATERIALS GROUP, INC. | $23,644,285 | +7.2% | -4.1% | $737,056 | 2+$2,168,511 | 3-$1,209,600 |
| 5 | JORDAN FOSTER CONSTRUCTION, LLC | $24,381,341 | +10.6% | -1.1% | $797,454 | 3+$2,265,092 | 0 |
| 6 | JOE BLAND CONSTRUCTION LLC | $25,178,796 | +14.2% | 2.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs PATIN CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,100,000.00 | $200,000.00 | $523,850.32 | -$1,900,000 |
| 400-7010 CEM STABIL BKFL | 7,572 CY | $155.00 | $250.00 | $138.14 | $719,340 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 33,581 CY | $18.00 | $34.00 | $18.71 | $537,296 |
| 162-7002 BLOCK SODDING | 53,147 SY | $4.25 | $14.00 | $4.39 | $518,183 |
| 508-7001 CONSTRUCTING DETOURS | 28,268 SY | $58.00 | $41.00 | $83.58 | -$480,556 |
| 512-7021 PORT CTB (DES SOURCE)(LOW PROF)(TY 1) | 14,460 LF | $10.00 | $35.00 | $11.62 | $361,500 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 81,571 SY | $4.30 | $8.00 | $3.93 | $301,813 |
| 619-7001 ITS MULTI-DUCT CND (PVC-40) | 13,290 LF | $19.25 | $40.00 | $23.76 | $275,768 |
| 314-7004 EMULS ASPH (BS OR SUBGR TRT)(CSS-1H) | 97,880 GAL | $5.25 | $2.50 | $3.12 | -$269,170 |
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 6,086 LF | $28.50 | $60.00 | $26.77 | $191,709 |
| 416-7005 DRILL SHAFT (30 IN) | 400 LF | $800.00 | $350.00 | $239.74 | -$180,000 |
| 247-7191 FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS) | 13,600 CY | $57.00 | $70.00 | $62.11 | $176,800 |
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 8,642 TON | $110.00 | $130.00 | $137.95 | $172,840 |
| 341-7001 D-GR HMA TY-B PG64-22 | 13,060 TON | $90.00 | $103.00 | $97.82 | $169,780 |
| 110-7001 EXCAV (ROADWAY) | 21,125 CY | $18.00 | $10.00 | $11.68 | -$169,000 |
| 529-7009 CONC CURB & GUTTER (TY II) | 20,150 LF | $27.00 | $20.00 | $32.57 | -$141,050 |
| 465-7022 INLET (COMPL)(PCO)(5FT)(LEFT) | 53 EA | $10,510.00 | $8,000.00 | $9,691.96 | -$133,030 |
| 432-7001 RIPRAP (CONC)(4 IN) | 1,178 CY | $610.00 | $500.00 | $573.24 | -$129,580 |
| 100-7002 PREPARING ROW | 101 STA | $550.00 | $1,800.00 | $6,072.92 | $126,250 |
| 619-7006 ITS MULTI-DUCT CND (PVC-80)(BORE) | 6,086 LF | $38.50 | $58.00 | $35.59 | $118,677 |
Positive: the low bidder was cheaper on that item. These 20 items account for $267,569 of the $1,084,960 gap.
BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,100,000.00 | $523,850.32 | 4.01x | $1,576,150 |
| 416-7005 DRILL SHAFT (30 IN) | 400 LF | $800.00 | $239.74 | 3.34x | $224,106 |
| 6027-7006 FIBER OPTIC CBL(SINGLE-MODE)(144 FIBER) | 25,498 LF | $9.75 | $3.80 | 2.57x | $151,769 |
| 100-7002 PREPARING ROW | 101 STA | $550.00 | $6,072.92 | 0.09x | -$557,815 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $3,100.00 | $11,585.04 | 0.27x | -$305,462 |
PATIN CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 7,572 CY | $250.00 | $138.14 | 1.81x | $846,976 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 33,581 CY | $34.00 | $18.71 | 1.82x | $513,353 |
| 162-7002 BLOCK SODDING | 53,147 SY | $14.00 | $4.39 | 3.19x | $510,865 |
| 512-7021 PORT CTB (DES SOURCE)(LOW PROF)(TY 1) | 14,460 LF | $35.00 | $11.62 | 3.01x | $338,091 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 81,571 SY | $8.00 | $3.93 | 2.04x | $332,361 |
| 618-7061 CONDT (PVC) (SCH 80) (3") (BORE) | 6,086 LF | $60.00 | $26.77 | 2.24x | $202,257 |
| 508-7001 CONSTRUCTING DETOURS | 28,268 SY | $41.00 | $83.58 | 0.49x | -$1,203,790 |
| 100-7002 PREPARING ROW | 101 STA | $1,800.00 | $6,072.92 | 0.30x | -$431,565 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $2,500.00 | $11,585.04 | 0.22x | -$327,062 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
JAMES CONSTRUCTION GROUP, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,353,364.03 | $523,850.32 | 4.49x | $1,829,514 |
| 100-7002 PREPARING ROW | 101 STA | $15,708.00 | $6,072.92 | 2.59x | $973,143 |
| 416-7005 DRILL SHAFT (30 IN) | 400 LF | $726.87 | $239.74 | 3.03x | $194,854 |
| 6027-7006 FIBER OPTIC CBL(SINGLE-MODE)(144 FIBER) | 25,498 LF | $8.90 | $3.80 | 2.34x | $130,096 |
| 529-7034 CONC CURB (DOWEL)(MOD) | 17,689 LF | $10.69 | $25.07 | 0.43x | -$254,401 |
| 105-7049 RMV (0"-9") TRT/UNTRT BASE & ASPH PAV | 51,385 SY | $2.14 | $5.10 | 0.42x | -$151,992 |
| 162-7002 BLOCK SODDING | 53,147 SY | $2.00 | $4.39 | 0.46x | -$126,899 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,360,000.00 | $523,850.32 | 4.51x | $1,836,150 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 81,571 SY | $8.00 | $3.93 | 2.04x | $332,361 |
| 100-7002 PREPARING ROW | 101 STA | $500.00 | $6,072.92 | 0.08x | -$562,865 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 36 MO | $2,500.00 | $11,585.04 | 0.22x | -$327,062 |
| 529-7034 CONC CURB (DOWEL)(MOD) | 17,689 LF | $7.00 | $25.07 | 0.28x | -$319,674 |