CR 244 (FCR 344) @ DEEP CREEK - BR FY 26
0917-30-068 · let Nov 3, 2026 · Burleson, Bryan · Bridge Replacement
$721,844Low bid: C & W SOUTHERN LLC+1.3% vs estimate $712,231
$6,333Left on the table0.9% gap to the second bid
15BiddersSpread 96% low to high
41Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | C & W SOUTHERN LLC | $721,844 | 1.3% | $6,333 | 7+$115,446 | 4-$543,307 | |
| 2 | THK CONSTRUCTION LLC | $728,177 | +0.9% | 2.2% | $7,252 | 8+$93,208 | 3-$536,755 |
| 3 | KNIFE RIVER CORPORATION - SOUTH | $735,430 | +1.9% | 3.3% | $14,520 | 1+$5,323 | 3-$480,193 |
| 4 | E-Z BEL CONSTRUCTION, LLC | $749,950 | +3.9% | 5.3% | $8,550 | 3+$35,522 | 2-$488,990 |
| 5 | TREVWAY, INC. | $758,500 | +5.1% | 6.5% | $34,929 | 4+$112,268 | 4-$543,837 |
| 6 | GARRET SHIELDS INFRASTRUCTURE | $793,429 | +9.9% | 11.4% | $39,240 | ||
| 7 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $832,669 | +15.4% | 16.9% | $10,753 | ||
| 8 | PRESIDIO CONTRACTING, LLC | $843,422 | +16.8% | 18.4% | $3,734 | ||
| 9 | YOKO EXCAVATING, LLC | $847,156 | +17.4% | 18.9% | $20,164 | ||
| 10 | STX CIVIL | $867,320 | +20.2% | 21.8% | $44,053 | ||
| 11 | TAYLOR BRIDGE LLC | $911,373 | +26.3% | 28.0% | $477 | ||
| 12 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $911,850 | +26.3% | 28.0% | $42,587 | ||
| 13 | Rucoba & Maya Construction, LLC | $954,437 | +32.2% | 34.0% | $125,548 | ||
| 14 | RB CONTRACTING, LLC | $1,079,985 | +49.6% | 51.6% | $335,656 | ||
| 15 | FUQUA CONSTRUCTION CO., INC. | $1,415,641 | +96.1% | 98.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
C & W SOUTHERN LLC vs THK CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $10,000.00 | $50,000.00 | $28,021.15 | $40,000 |
| 425-7030 PRESTR CONC BOX BEAM (4B34) | 338 LF | $318.00 | $422.24 | $353.67 | $35,233 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,044 SY | $70.00 | $40.00 | $21.46 | -$31,320 |
| 422-7005 REINF CONC SLAB (BOX BEAM) | 2,225 SF | $30.00 | $22.25 | $35.96 | -$17,244 |
| 344-7010 SP MIXES SP-C SAC-A PG64-22 | 115 TON | $395.00 | $250.00 | $123.74 | -$16,675 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $50,000.00 | $523,850.32 | -$10,000 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 37 CY | $500.00 | $750.00 | $616.83 | $9,250 |
| 416-7006 DRILL SHAFT (36 IN) | 150 LF | $270.00 | $330.75 | $280.58 | $9,113 |
| 400-7010 CEM STABIL BKFL | 88.2 CY | $225.00 | $300.00 | $138.14 | $6,615 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 218 CY | $190.00 | $160.00 | $184.74 | -$6,540 |
| 420-7012 CL C CONC (ABUT) | 37.8 CY | $1,100.00 | $950.00 | $1,307.98 | -$5,670 |
| 425-7031 PRESTR CONC BOX BEAM (5B34) | 169 LF | $333.00 | $300.77 | $345.03 | -$5,447 |
| 450-7008 RAIL (TY T223) | 214 LF | $150.00 | $170.00 | $141.07 | $4,280 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 397 CY | $25.00 | $15.00 | $13.19 | -$3,970 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 1,504 SY | $0.5000 | $3.03 | $0.3117 | $3,805 |
| 164-7007 BROADCAST SEED (TEMP_WARM_COOL) | 1,504 SY | $0.5000 | $3.03 | $0.2110 | $3,805 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 8 CY | $1,800.00 | $1,500.00 | $136.70 | -$2,400 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,000.00 | $1,449.20 | $11,585.04 | -$2,203 |
| 344-7077 TACK COAT | 104 GAL | $30.00 | $10.00 | $3.25 | -$2,080 |
| 105-7032 RMV (12") TRT/UNTRT BASE & ASPH PAV | 898 SY | $15.00 | $13.00 | $7.54 | -$1,796 |
Positive: the low bidder was cheaper on that item. These 20 items account for $6,756 of the $6,333 gap.
C & W SOUTHERN LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,044 SY | $70.00 | $21.46 | 3.26x | $50,676 |
| 344-7010 SP MIXES SP-C SAC-A PG64-22 | 115 TON | $395.00 | $123.74 | 3.19x | $31,195 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 8 CY | $1,800.00 | $136.70 | 13.17x | $13,306 |
| 105-7032 RMV (12") TRT/UNTRT BASE & ASPH PAV | 898 SY | $15.00 | $7.54 | 1.99x | $6,697 |
| 316-7016 ASPH (RC-250) | 261 GAL | $24.50 | $5.28 | 4.64x | $5,017 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 397 CY | $25.00 | $13.19 | 1.90x | $4,688 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 1,504 SY | $4.00 | $1.43 | 2.80x | $3,866 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,000.00 | $11,585.04 | 0.17x | -$38,340 |
| 100-7002 PREPARING ROW | 4.89 STA | $1,350.00 | $6,072.92 | 0.22x | -$23,095 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $10,000.00 | $28,021.15 | 0.36x | -$18,021 |
THK CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $50,000.00 | $28,021.15 | 1.78x | $21,979 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,044 SY | $40.00 | $21.46 | 1.86x | $19,356 |
| 344-7010 SP MIXES SP-C SAC-A PG64-22 | 115 TON | $250.00 | $123.74 | 2.02x | $14,520 |
| 400-7010 CEM STABIL BKFL | 88.2 CY | $300.00 | $138.14 | 2.17x | $14,276 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 8 CY | $1,500.00 | $136.70 | 10.97x | $10,906 |
| 164-7007 BROADCAST SEED (TEMP_WARM_COOL) | 1,504 SY | $3.03 | $0.2110 | 14.36x | $4,240 |
| 164-7002 BROADCAST SEED (PERM_RURAL_CLAY) | 1,504 SY | $3.03 | $0.3117 | 9.72x | $4,088 |
| 316-7016 ASPH (RC-250) | 261 GAL | $20.00 | $5.28 | 3.79x | $3,843 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,449.20 | $11,585.04 | 0.13x | -$40,543 |
| 100-7002 PREPARING ROW | 4.89 STA | $1,500.00 | $6,072.92 | 0.25x | -$22,362 |
KNIFE RIVER CORPORATION - SOUTH: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 78 SY | $95.00 | $26.75 | 3.55x | $5,323 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,185.00 | $11,585.04 | 0.19x | -$37,600 |
| 100-7002 PREPARING ROW | 4.89 STA | $2,240.00 | $6,072.92 | 0.37x | -$18,743 |
E-Z BEL CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7251 AGGR (TY-B OR L, GR-5) | 8 CY | $2,200.00 | $136.70 | 16.09x | $16,506 |
| 344-7010 SP MIXES SP-C SAC-A PG64-22 | 115 TON | $250.00 | $123.74 | 2.02x | $14,520 |
| 316-7016 ASPH (RC-250) | 261 GAL | $22.50 | $5.28 | 4.26x | $4,495 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $2,800.00 | $11,585.04 | 0.24x | -$35,140 |
TREVWAY, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 344-7010 SP MIXES SP-C SAC-A PG64-22 | 115 TON | $789.00 | $123.74 | 6.38x | $76,505 |
| 316-7251 AGGR (TY-B OR L, GR-5) | 8 CY | $2,652.00 | $136.70 | 19.40x | $20,122 |
| 344-7077 TACK COAT | 104 GAL | $100.00 | $3.25 | 30.79x | $10,062 |
| 316-7016 ASPH (RC-250) | 261 GAL | $26.65 | $5.28 | 5.05x | $5,579 |
| 500-7001 MOBILIZATION | 1 LS | $70,000.00 | $523,850.32 | 0.13x | -$453,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,000.00 | $11,585.04 | 0.09x | -$42,340 |
| 420-7012 CL C CONC (ABUT) | 37.8 CY | $652.00 | $1,307.98 | 0.50x | -$24,796 |
| 100-7002 PREPARING ROW | 4.89 STA | $1,400.00 | $6,072.92 | 0.23x | -$22,851 |