FY 27 West Hot Mix Cold-Laid
6496-52-001 · let Sep 2, 2026 · Blanco, Austin · Material Maintenance Project
$2,803,000Low bid: BRAUNTEX MATERIALS, INC.+0.8% vs estimate $2,782,000
$202,750Left on the table7.2% gap to the second bid
4BiddersSpread 20% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BRAUNTEX MATERIALS, INC. | $2,803,000 | 0.8% | $202,750 | 0 | 0 | |
| 2 | LONE STAR PAVING COMPANY | $3,005,750 | +7.2% | 8.0% | $236,750 | 0 | 0 |
| 3 | TEXAS MATERIALS GROUP, INC. | $3,242,500 | +15.7% | 16.6% | $121,500 | 0 | 0 |
| 4 | COLORADO MATERIALS, LTD. | $3,364,000 | +20.0% | 20.9% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BRAUNTEX MATERIALS, INC. vs LONE STAR PAVING COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8013-7019 HMCL ACP TYPE D (DEL)(SITE 3) | 6,000 TON | $80.00 | $95.25 | $86.52 | $91,500 |
| 8013-7017 HMCL ACP TYPE D (DEL)(SITE 1) | 4,000 TON | $77.00 | $87.75 | $93.03 | $43,000 |
| 8013-7021 HMCL ACP TYPE D (DEL)(SITE 5) | 6,000 TON | $93.00 | $97.50 | $92.10 | $27,000 |
| 8013-7004 HMCL ACP TYPE B (DEL)(SITE 3) | 2,000 TON | $78.00 | $91.25 | $84.15 | $26,500 |
| 8013-7002 HMCL ACP TYPE B (DEL)(SITE 1) | 1,000 TON | $75.00 | $83.75 | $93.51 | $8,750 |
| 8013-7020 HMCL ACP TYPE D (DEL)(SITE 4) | 4,000 TON | $89.00 | $90.50 | $101.29 | $6,000 |
| 8013-7003 HMCL ACP TYPE B (DEL)(SITE 2) | 2,000 TON | $85.00 | $83.25 | $101.11 | -$3,500 |
| 8013-7006 HMCL ACP TYPE B (DEL)(SITE 5) | 1,000 TON | $91.00 | $93.50 | $89.30 | $2,500 |
| 8013-7018 HMCL ACP TYPE D (DEL)(SITE 2) | 6,000 TON | $87.00 | $87.25 | $92.98 | $1,500 |
| 8013-7005 HMCL ACP TYPE B (DEL)(SITE 4) | 1,000 TON | $87.00 | $86.50 | $97.85 | -$500 |
Positive: the low bidder was cheaper on that item. These 10 items account for $202,750 of the $202,750 gap.