SMITH COUNTY SMA FY 27
6500-40-001 · let Jun 2, 2026 · Smith, Tyler · Routine Maintenance Project - Sealed
$5,091,894Low bid: TEXAS MATERIALS GROUP, INC.-1.7% vs estimate $5,179,659
$59,144Left on the table1.2% gap to the second bid
6BiddersSpread 32% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXAS MATERIALS GROUP, INC. | $5,091,894 | -1.7% | $59,144 | 0 | 0 | |
| 2 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $5,151,039 | +1.2% | -0.6% | $374,816 | 0 | 2-$176,233 |
| 3 | LONGVIEW BRIDGE AND ROAD, LTD. | $5,525,855 | +8.5% | 6.7% | $123,255 | 0 | 0 |
| 4 | BIG CREEK CONSTRUCTION, LTD. | $5,649,110 | +10.9% | 9.1% | $407,299 | 1+$630,576 | 0 |
| 5 | ICOS MANAGEMENT, LLC | $6,056,409 | +18.9% | 16.9% | $689,508 | 1+$446,851 | 1-$330,745 |
| 6 | EAST TEXAS BRIDGE, INC. | $6,745,918 | +32.5% | 30.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXAS MATERIALS GROUP, INC. vs DREWERY CONSTRUCTION COMPANY, INCORPORATED, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 3005-7001 MEMBRANE UNDERSEAL | 31,035 GAL | $6.75 | $0.0100 | $4.76 | -$209,176 |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 21,973 TON | $186.98 | $196.00 | $156.93 | $198,196 |
| 354-7052 PLANE ASPH CONC PAV(3") | 124,139 SY | $3.53 | $4.00 | $2.92 | $58,345 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 42 DAY | $60.00 | $500.00 | $87.82 | $18,480 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,800.00 | $2,000.00 | $11,585.04 | -$11,400 |
| 500-7001 MOBILIZATION | 1 LS | $265,000.00 | $275,000.00 | $523,850.32 | $10,000 |
| 505-7001 TMA (STATIONARY) | 42 DAY | $250.00 | $100.00 | $217.57 | -$6,300 |
| 662-7065 WK ZN PAV MRK REMOV (W)6"(BRK) | 5,598 LF | $2.50 | $1.50 | $1.02 | -$5,598 |
| 662-7082 WK ZN PAV MRK REMOV (W)(ARROW) | 36 EA | $60.00 | $200.00 | $166.91 | $5,040 |
| 662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD) | 6,250 LF | $1.25 | $2.00 | $0.8371 | $4,688 |
| 662-7092 WK ZN PAV MRK REMOV (W)(WORD) | 18 EA | $60.00 | $250.00 | $188.03 | $3,420 |
| 662-7098 WK ZN PAV MRK REMOV (Y)6"(BRK) | 2,833 LF | $2.50 | $1.50 | $1.04 | -$2,833 |
| 662-7077 WK ZN PAV MRK REMOV (W)24"(SLD) | 478 LF | $8.00 | $4.00 | $7.79 | -$1,912 |
| 662-7072 WK ZN PAV MRK REMOV (W)8"(SLD) | 628 LF | $4.00 | $2.00 | $1.62 | -$1,256 |
| 662-7074 WK ZN PAV MRK REMOV (W)12"(LNDP) | 100 LF | $8.00 | $2.50 | $3.48 | -$550 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 2 EA | $500.00 | $500.00 | $36.55 | $0 |
Positive: the low bidder was cheaper on that item. These 16 items account for $59,144 of the $59,144 gap.
DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items
Placed 2BIG CREEK CONSTRUCTION, LTD.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7052 PLANE ASPH CONC PAV(3") | 124,139 SY | $8.00 | $2.92 | 2.74x | $630,576 |